[go: up one dir, main page]

CN1198990C - Layered Mesh Reinforced Gabion Retaining Wall for Slope Reinforcement - Google Patents

Layered Mesh Reinforced Gabion Retaining Wall for Slope Reinforcement Download PDF

Info

Publication number
CN1198990C
CN1198990C CN 02159704 CN02159704A CN1198990C CN 1198990 C CN1198990 C CN 1198990C CN 02159704 CN02159704 CN 02159704 CN 02159704 A CN02159704 A CN 02159704A CN 1198990 C CN1198990 C CN 1198990C
Authority
CN
China
Prior art keywords
retaining wall
reinforced
gabion
reinforced gabion
slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 02159704
Other languages
Chinese (zh)
Other versions
CN1512011A (en
Inventor
张路青
杨志法
祝介旺
刘�英
尚彦军
许兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Institute of Geology and Geophysics of CAS
Original Assignee
Institute of Geology and Geophysics of CAS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Institute of Geology and Geophysics of CAS filed Critical Institute of Geology and Geophysics of CAS
Priority to CN 02159704 priority Critical patent/CN1198990C/en
Publication of CN1512011A publication Critical patent/CN1512011A/en
Application granted granted Critical
Publication of CN1198990C publication Critical patent/CN1198990C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Revetment (AREA)

Abstract

本发明是一种用于边坡加固的层状网式钢筋石笼挡墙,包括成排成层地堆砌成台阶状的钢筋石笼,在钢筋石笼层间浇注有混凝土层,所述钢筋石笼框架的竖向钢筋长于笼体的高度,其末端插入所述钢筋石笼层间的混凝土层内部;在钢筋石笼侧面空隙间浇注有砂浆层;以及还包括有排水系统。该钢筋石笼挡墙具有整体强度高、抗锈蚀能力强、有效排水、易于绿化、易于监测等优点。

Figure 02159704

The present invention relates to a layered net-type reinforced gabion retaining wall for slope reinforcement, which comprises step-like reinforced gabions piled up in rows and layers, and concrete layers are poured between the layers of the reinforced gabions. The vertical steel bar of the gabion frame is longer than the height of the cage body, and its end is inserted into the concrete layer between the steel bar gabion layers; a mortar layer is poured between the side spaces of the bar bar cage; and a drainage system is also included. The reinforced gabion retaining wall has the advantages of high overall strength, strong corrosion resistance, effective drainage, easy greening, and easy monitoring.

Figure 02159704

Description

The stratified net-mesh reinforced stone-gabion that is used for slope reinforcement
Technical field
The present invention relates to a kind of barricade that is used for slope reinforcement, relate in particular to a kind of stratified net-mesh reinforced stone-gabion that is used for medium and small slope reinforcement.
Background technology
At present, the domestic structure that is used for the supporting slope of highway is the plain edition steel bar stone cage retaining wall.Also plain edition steel bar stone cage retaining wall structure is used for aspects such as anti-erosion or scour protection abroad.In view of many advantages of this wall-retaining structure, some country in the U.S. and Europe is used for it supporting of medium and small side slope under the difficult area (as the mountain area) more at large, and has developed corresponding design manual and professional production merchant.
Plain edition reinforced gabion as shown in Figure 3, its construction mainly was divided into for two steps: make one with reinforcing bar and steel wire by certain specification earlier and be rectangular-shaped reinforcing cage, fill the rubble (or gravel) of gathering materials on the spot again in cage.Then, each reinforced gabion is in a row piled up to stratification on demand be barricade.For gabion is closely contacted with treating reinforcing side slope, between barricade and side slope face, fill up rubble (or gravel).In specific design and work progress, strengthen the shearing resistance and the anti-upset ability of barricade sometimes according to actual needs at barricade bottom pouring concrete pedestal.Although the plain edition steel bar stone cage retaining wall has advantages such as can gathering materials on the spot, be easy to construct, be beneficial to draining, yet still there are many weak points in existing design and construction:
Bulk strength is lower.Because the plain edition steel bar stone cage retaining wall is to be formed by simply piling up of a plurality of reinforced gabions, its integrality is to keep by the frictional force between the gabion.Be easy to produce relative to slip under external force between each gabion, relative displacement such as rotate, severe patient can make reinforced gabion disintegrate.
Resistant tarnishing is poor.Because the reinforcing bar of plain edition reinforced gabion and steel wire directly touch the sky G﹠W, very easily by corrosion.If reinforcing bar and steel wire corrosion are serious, the plain edition reinforced gabion then will face the danger of disintegration, thereby reduce the intensity of this barricade greatly and be reinforced the stability of side slope.
Drainage performance is limited.Because the drainability of plain edition steel bar stone cage retaining wall can not satisfy the drainage requirement of side slope, the underground water of side slope inside is in from oozing state, and this might threaten the stability of side slope.
In addition, the plain edition steel bar stone cage retaining wall is difficult to realize that the state to side slope and barricade monitors.And be reinforced original vegetation on the side slope surface because remove or covered in the work progress, the plain edition steel bar stone cage retaining wall again can't restore vegetation, is unfavorable for environmental protection.
Summary of the invention
The objective of the invention is at above-mentioned problems of the prior art, proposed a kind of steel bar stone cage retaining wall that has high bulk strength, strong anti-corrosion, effectively draining, is easy to afforest, be easy to monitoring and other advantages.
For achieving the above object, a kind of stratified net-mesh reinforced stone-gabion that is used for slope reinforcement of the present invention, be piled into step-like reinforced gabion with comprising stratification in a row, be cast with layer of concrete at the reinforced gabion interlayer, the vertical reinforcement of described reinforced gabion framework is longer than the height of cage body, its terminal layer of concrete inside of inserting described reinforced gabion interlayer; Between the reinforced gabion side gap, be cast with screed; And also include drainage system.
The vertical reinforcement two ends of described reinforced gabion framework are the hook shape.
Described layer of concrete is formed by steel mesh reinforcement and concrete pouring.
Described drainage system comprises:
Below, described reinforced gabion side has along the longitudinal drainage pipe of side slope tendency direction;
Be provided with along side slope every layer of described reinforced gabion side and move towards the transverse drain that direction is communicated with two adjacent reinforced gabions; And
In side slope, be provided with the drain hole that communicates with the rubble of described reinforced gabion inside.
On each step of described steel bar stone cage retaining wall, be provided with the catch basin that moves towards direction along side slope, and weep pipe is set.
On each step of described steel bar stone cage retaining wall, also be provided with soil box, be used for serike, in the hope of reaching the purpose that barricade is afforested.Can utilize catch basin and weep pipe to water.
In reinforced concrete floor, be embedded with the extensometer that extends in the side slope boring, the monitoring slope deforming, corresponding deformation data can use dial gage to obtain.Burying load that sensor bears barricade or inner stress, strain etc. in reinforced concrete floor or screed underground monitors.
Thus, the present invention has following tangible advantage with respect to other slope reinforcement measures:
(1) construction is simple and convenient, cheap, and the braiding of reinforcing cage can be concentrated making near the barricade of waiting to construct, and the interior stone of reinforced gabion can be gathered materials on the spot.The rule of reinforced gabion is piled up, between gabion the construction of the steps such as laying, the slurry placement between the gabion side, the layout of gabion interlayer steel mesh reinforcement and the cast of layer of concrete of communicating pipe very easy and do not need the workload of high-tech.
(2) bulk strength height, reinforced concrete floor between each layer reinforced gabion, the built-in fitting at the vertical reinforcement two ends of each reinforced gabion framework all inserts up and down in the reinforced concrete floor, filling mortar between space, reinforced gabion both sides, make this wall-retaining structure that very high bulk strength and certain deformability be arranged, reduce the possibility that reinforced gabion disintegrates, thereby help the stable of side slope.
(3) resistant tarnishing is strong, can prevent effectively that with interstitial reinforced concrete floor in reinforced gabion both sides or screed reinforcing bar and steel wire are owing to being exposed to water and air and by corrosion between each layer reinforced gabion.
(4) drainage performance is good, fill rubble or gravel in the reinforced gabion with height water permeability, the reinforced gabion side is provided with to be communicated with in the transverse drain of adjacent reinforced gabion and every layer of reinforced gabion along side slope tendency direction and is provided with the longitudinal drainage pipe that moves towards direction along side slope.According to the needs of design, also can be at the inner drain hole that communicates with piece stone gap in the gabion of laying of side slope.Said structure makes many drainage channels that have of steel bar stone cage retaining wall, realizes efficient draining.
(5) be easy to monitoring, in reinforced concrete floor, be embedded with the extensometer that extends in the side slope boring and monitor slope deforming, in reinforced concrete floor or screed, bury the stress, strain etc. of load that sensor bears barricade or inside underground and monitor.
(6) be beneficial to environmental protection, whole steel bar stone cage retaining wall is without any need for timber, free from environmental pollution and can plant in the soil box on the barricade step and be fit to growing plants.
Description of drawings
Fig. 1 is structure and the reinforcing principle schematic that is used for the stratified net-mesh reinforced stone-gabion of slope reinforcement of the present invention;
Fig. 2 is the structural representation that is used for the stratified net-mesh reinforced stone-gabion reinforcing cage of slope reinforcement of the present invention;
Fig. 3 is the structure of plain edition steel bar stone cage retaining wall and reinforces principle schematic.
The specific embodiment
A kind of steel bar stone cage retaining wall as shown in Figure 1 is a specific embodiment of the present invention, and Fig. 2 is the structural representation of reinforcing cage.The loose top layer of at first excavating position, barricade pedestal place is to projected depth, and fluid concrete makes up pedestal layer of concrete 13.Pedestal layer of concrete 13 sectionals or laminated pouring, the size of its segmentation unlikely concrete of just having poured into a mould of stepping on of personnel when putting reinforcing cage is advisable.In case of necessity, can in concrete, add retarding agent and delay concrete initial set, so as for reinforcing cage put and the reinforcing cage bottom surface can be immersed concrete grout exercisable condition is provided.After pouring every section concrete; unsealed reinforcing bar verdant in a row can be put the position of design; bottom layer of the reinforcing steel gabion vertical reinforcement terminal 5 is inserted concrete grout, and guarantee that reinforcing bar and steel wire on the reinforcing cage bottom surface are wrapped up to form the topping of anti-corrosion by concrete grout.Reinforcing bar end 5 is the hook shape, and the vertical reinforcement lower end built-in fitting length of bottom layer of the reinforcing steel gabion framework is greater than the length of the vertical reinforcement two ends built-in fitting of built-in fitting and other layers reinforced gabion framework on the vertical reinforcement of bottom layer of the reinforcing steel gabion framework.When putting reinforcing cage, should stay space, the 4cm left and right sides to be used for the filling mortar between two adjacent reinforcing cages and form screed 6.The mesh 18 that longitudinal drainage pipe 10 is passed through bottom, reinforced gabion side is communicated with adjacent reinforced gabion along side slope tendency direction, and longitudinal drainage pipe 10 should insert the interior certain distance of reinforcing cage to prevent the mortar plugging.In side slope 1, be provided with the drain hole 16 that communicates with the rubble of described reinforced gabion inside.Establish the transverse drain 7 that moves towards direction along side slope in the reinforced gabion side.It is fixed that the diameter of longitudinal drainage pipe 10 and transverse drain 7 should be come by the size of the mesh 18 of the hydrologic condition of locality and reinforced gabion side, is not advisable not weave special preformed hole as far as possible for this reason.After the layer of concrete of cast reaches certain intensity, the rubble (or gravel) that filling is gathered materials on the spot in unsealed reinforcing cage.All spaces near side slope 1 one sides that are reinforced all are filled with rubble (or gravel).The stone that is loaded should have certain grating, so that the stone in the cage is closely contacted, near the remaining space of side slope one side, does not put reinforcing cage because the space is less, but will with grating preferably rubble come filling.Be woven into the end face of reinforced gabion with steel wire 17, all reinforcing cages of filling stone are sealed.With the space slurry placement between the reinforced gabion side, and make mortar closely knit as far as possible, protect the reinforcing bar of reinforced gabion side and steel wire not by corrosion to form screed 6.In screed 6, bury the sensor 15 that is used to monitor barricade load and internal stress or strain underground.So far, finished the laying work of bottom layer of the reinforcing steel gabion.Outside the bottom layer of the reinforcing steel gabion, be provided with along side slope and move towards the catch basin 11 of direction and the soil box 12 of serike.The longitudinal drainage pipe 10 that effluxes the reinforced gabion side leads to catch basin 11.Soil box 12 certain distances are provided with gutter 14 outside distance bottom layer of the reinforcing steel gabion.
On one deck reinforced gabion of having constructed, lay steel mesh reinforcement 4, and will reserve certain clearance between steel mesh reinforcement 4 and lower floor's reinforced gabion end face.Subsequently, pour into a mould the thick concrete of 4cm~6cm on steel mesh reinforcement 4, corresponding section construction should help putting of last layer reinforcing cage.After every section concrete construction finishes, the upper end built-in fitting 5 of lower floor's reinforced gabion vertical reinforcement will be embedded in the concrete grout.The concrete tamping so that form reinforced concrete floors 3 with steel mesh reinforcement 4, and is wrapped up reinforcing bar and the steel wire on lower floor's reinforced gabion end face, form the topping of anti-corrosion.In reinforced concrete floor 3, bury the sensor 15 that is used to monitor barricade load and internal stress or strain underground, in reinforced concrete floor 3, be embedded with and extend to the extensometer 2 that is reinforced in the side slope 1, the monitoring slope deforming.When putting reinforcing cage, except that being undertaken by above-mentioned requirements, the interlaced arrangement of also the adjacent two layers reinforced gabion should being tried one's best, the upper strata effluxes reinforcing cage and lower floor and effluxes reinforced gabion and have certain distance to form step.Add on the barricade step surface and smear surperficial screed 9, prevent the corrosion of barricade free face, fixing soil box 12 simultaneously is used for serike.In addition, the catch basin 11 that moves towards direction along side slope is set also on the barricade step surface, the gutter of weep pipe 8 and corresponding connected set tank 11 and weep pipe 8 is set on step surface at interval.
Adopt above-mentioned construction sequence, make up each reinforced gabion layer until the engineering design height.Top layer reinforced gabion upper surface is laid steel mesh reinforcement 4, fluid concrete, form reinforced concrete floor 3, in reinforced concrete floor 3 or screed 6, bury the sensor 15 that is used to monitor barricade load and internal stress or strain underground, bury the extensometer 2 that extends in the side slope 1 that is reinforced underground, the monitoring slope deforming.Weep pipe 8 is set on reinforced concrete floor 3 at interval.
Steel bar stone cage retaining wall of the present invention is gathered materials on the spot except having, the easy construction, with low cost, advantage such as adaptive is strong, compare also with the plain edition steel bar stone cage retaining wall and to have the following advantages:
1, stronger slope reinforcement function
The reinforced concrete floor of reinforced gabion interlayer, the built-in fitting that inserts the reinforced gabion vertical reinforcement in the reinforced concrete floor and the mortar between gabion etc. can closely connect to each gabion an integral body, cause corresponding bulk strength very high.And this steel bar stone cage retaining wall still belongs to a kind of flexible structure.Because there is certain deformability in this flexible structure, so can suitably reduce that slope deforming causes and act directly on load on the barricade.This have certain deformability and the bigger wall-retaining structure of bulk strength and can significantly reduce the possibility that reinforced gabion disintegrates, thereby help the stable of side slope.
2, stronger anti-corrosion ability
The reinforcing bar of all gabions and steel wire are all wrapped up by concrete or mortar cover, cause this new reinforcing steel bar gabion baffling to have stronger anti-corrosion ability.Only in this way, reinforcing bar and the steel wire of forming barricade could keep its due intensity for a long time, and can satisfy the basic demand of slope reinforcement.
3, can realize efficient draining
Though itself has had good drain function the plain edition steel bar stone cage retaining wall, on drainage condition after all also less than the former side slope that does not have barricade.When the discharging of slope underground water became the key factor that influences stability of slope, it obviously was very important improving corresponding drainage condition.At this situation, when design new reinforcing steel bar gabion baffling, can in side slope, beat special drain hole according to actual needs, its aperture communicates with rubble (or gravel) in the gabion.Like this, the gutter that is communicated with reinforced gabion by the space between the rubble (or gravel) in slope drainage hole, the cage, along side slope trend and tendency direction, and the catch basin on the barricade step surface, gutter and weep pipe, the common drainage system that constitutes barricade can make this wall-retaining structure have drain function efficiently.
4, be easy to realize greening to barricade
Fixing soil box can be planted and is fit to the local environment growing plants on the barricade step surface, ruinate original vegetation in the time of can recovering the barricade construction.The efficient reinforcing function that this barricade had is enough to guarantee the long-term stability of soil box, can avoid the harmful effect of plant growing to barricade when utilizing soil box to afforest.The required water of soil box implants growth is mainly rainwater, and from side slope inside ooze out and flow through slope drainage hole, reinforced gabion rubble gap, gutter, catch basin and the water that flows out by weep pipe.
5, be easy to realize monitoring to side slope or barricade
In work progress, can in side slope, play special boring, so that extensometer is embedded in the layer of concrete of boring and gabion interlayer.Like this, can help to judge the stability of side slope or barricade by the deformation measurement data that obtains.Also can obtain load that barricade bears and monitored data such as inner stress or strain thereof by being embedded in sensor in the reinforced concrete floor or in the screed.

Claims (8)

1、一种用于边坡加固的层状网式钢筋石笼挡墙,包括成排成层地堆砌成台阶状的钢筋石笼,其特征在于:1. A layered net-type reinforced gabion retaining wall for slope reinforcement, including rows of reinforced gabions stacked in layers to form steps, characterized in that: 在钢筋石笼层间浇注有混凝土层,所述钢筋石笼框架的竖向钢筋长于笼体的高度,其末端插入所述钢筋石笼层间的混凝土层内部;A concrete layer is poured between the reinforced gabion layers, the vertical reinforcement of the reinforced gabion frame is longer than the height of the cage body, and its end is inserted into the concrete layer between the reinforced gabion layers; 在钢筋石笼侧面空隙间浇注有砂浆层;以及A layer of mortar is poured between the side spaces of the steel gabion; and 还包括有排水系统。Also includes a drainage system. 2、如权利要求1所述的用于边坡加固的层状网式钢筋石笼挡墙,其特征在于:所述钢筋石笼框架的竖向钢筋两端为弯勾状。2. The layered mesh reinforced gabion retaining wall for slope reinforcement according to claim 1, characterized in that: the two ends of the vertical reinforcement of the reinforced gabion frame are hook-shaped. 3、如权利要求1所述的用于边坡加固的层状网式钢筋石笼挡墙,其特征在于:所述混凝土层由钢筋网和混凝土浇注而成。3. The layered mesh reinforced gabion retaining wall for slope reinforcement according to claim 1, wherein the concrete layer is formed by pouring steel mesh and concrete. 4、如权利要求1所述的用于边坡加固的层状网式钢筋石笼挡墙,其特征在于:所述的排水系统包括:4. The layered mesh reinforced gabion retaining wall for slope reinforcement according to claim 1, wherein the drainage system includes: 所述的钢筋石笼侧面下方有沿边坡倾向方向的纵向排水管;There are longitudinal drainage pipes along the inclined direction of the slope under the sides of the reinforced gabion; 在每层所述钢筋石笼侧面设有沿边坡走向方向连通两相邻钢筋石笼的横向排水管;以及On the side of the steel gabion on each floor, there is a horizontal drainage pipe connecting two adjacent steel gabions along the direction of the slope; and 在边坡内设有与所述钢筋石笼内部的碎石相通的排水孔。Drainage holes communicating with the crushed stone inside the reinforced gabion are provided in the slope. 5、如权利要求1所述的用于边坡加固的层状网式钢筋石笼挡墙,其特征在于:在所述钢筋石笼挡墙各台阶上设有沿边坡走向方向的集水槽,并设置滴水管。5. The layered net-type reinforced gabion retaining wall for slope reinforcement according to claim 1, characterized in that: each step of the reinforced gabion retaining wall is provided with a water collection tank along the direction of the slope, And set the dripper. 6、如权利要求1所述的用于边坡加固的层状网式钢筋石笼挡墙,其特征在于:在所述钢筋石笼挡墙各台阶上还设有用于栽种植物的土槽。6. The layered mesh reinforced gabion retaining wall for slope reinforcement according to claim 1, characterized in that: soil grooves for planting plants are also provided on each step of the reinforced gabion retaining wall. 7、如权利要求1所述的用于边坡加固的层状网式钢筋石笼挡墙,其特征在于:在所述混凝土层内埋设有监测边坡变形的伸长计。7. The layered mesh reinforced gabion retaining wall for slope reinforcement according to claim 1, characterized in that: an extensometer for monitoring slope deformation is embedded in the concrete layer. 8、如权利要求1所述的用于边坡加固的层状网式钢筋石笼挡墙,其特征在于:在所述混凝土层或所述砂浆层埋设有监测挡墙负荷的传感器。8. The layered mesh reinforced gabion retaining wall for slope reinforcement according to claim 1, characterized in that a sensor for monitoring the load of the retaining wall is embedded in the concrete layer or the mortar layer.
CN 02159704 2002-12-30 2002-12-30 Layered Mesh Reinforced Gabion Retaining Wall for Slope Reinforcement Expired - Fee Related CN1198990C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 02159704 CN1198990C (en) 2002-12-30 2002-12-30 Layered Mesh Reinforced Gabion Retaining Wall for Slope Reinforcement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 02159704 CN1198990C (en) 2002-12-30 2002-12-30 Layered Mesh Reinforced Gabion Retaining Wall for Slope Reinforcement

Publications (2)

Publication Number Publication Date
CN1512011A CN1512011A (en) 2004-07-14
CN1198990C true CN1198990C (en) 2005-04-27

Family

ID=34237601

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 02159704 Expired - Fee Related CN1198990C (en) 2002-12-30 2002-12-30 Layered Mesh Reinforced Gabion Retaining Wall for Slope Reinforcement

Country Status (1)

Country Link
CN (1) CN1198990C (en)

Families Citing this family (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101412605B (en) * 2008-11-21 2011-11-16 中冶宝钢技术服务有限公司 Steel slag movable retaining wall and manufacturing method thereof
CN101984192B (en) * 2009-12-25 2015-02-18 北京群祥兴科技有限公司 Ecological engineering method of flexible strong structure
CN101967830A (en) * 2010-09-21 2011-02-09 张宇顺 An ecological net cage and a slope retaining wall using the ecological net cage
CN102296580A (en) * 2011-04-21 2011-12-28 长沙理工大学 Slope shallow drainage system
CN104328766A (en) * 2014-10-31 2015-02-04 杭州市市政工程集团有限公司 Ecological stone cage net box retaining wall and construction method
CN104358203B (en) * 2014-11-14 2016-08-24 铁道第三勘察设计院集团有限公司 The reinforced concrete floor formula gabion side's of abandoning lateral drainage groove structure
CN108157077A (en) * 2015-03-11 2018-06-15 泉州泉港润美环保科技有限公司 A kind of modification method in hillside forest land
CN105544563B (en) * 2015-12-16 2018-01-12 大连久鼎祥瑞特种工程技术研究院有限公司 Large-scale loose ground, stone body slope protection structure
CN105484199B (en) * 2015-12-28 2017-09-22 陈桂腾 A kind of dam configuration and its construction method
CN105569071B (en) * 2015-12-29 2017-07-28 吉林省银河水利水电新技术设计有限公司 A kind of slip casting under water of cement-based material or mud jacking block ground mass foundation construction
CN106337394A (en) * 2016-09-22 2017-01-18 水利部中国科学院水工程生态研究所 River bank ecological restoration device and method suitable for mountain river characteristics
CN106759397A (en) * 2017-01-06 2017-05-31 苏州工业园区园林绿化工程有限公司 Ecological lattice guest method to set up
CN107313445B (en) * 2017-05-23 2019-05-17 西北矿冶研究院 Composite retaining wall structure of refuse dump
CN107354954A (en) * 2017-07-27 2017-11-17 中钢集团马鞍山矿山研究院有限公司 A kind of Gravity Retaining Wall administered for slope and land slide
CN107975138A (en) * 2017-12-29 2018-05-01 内蒙古蒙草生态环境(集团)股份有限公司 A kind of gabion structure and preparation method thereof
CN108374388B (en) * 2018-04-03 2020-05-15 江西翔博建设工程有限公司 A kind of retaining wall for hydraulic engineering
CN110438857B (en) * 2019-07-12 2023-12-05 中交一公局第四工程有限公司 A kind of reinforced cage stalagmite pile and its construction technology in mountainous and hilly areas
CN110438943A (en) * 2019-07-31 2019-11-12 江河水利水电咨询中心 A kind of sandy soil fill construction method
CN112144940A (en) * 2020-09-28 2020-12-29 中国电建集团贵阳勘测设计研究院有限公司 Steel reinforcement gabion bin wall structure suitable for backfilling foundation and construction method
CN112609731A (en) * 2020-12-31 2021-04-06 四川省交通勘察设计研究院有限公司 Flexible permeable cutting retaining wall and construction method
CN113250240A (en) * 2021-05-24 2021-08-13 中国电建集团贵阳勘测设计研究院有限公司 Combined side slope protection structure and process of layered net type gabion and concrete
CN113463801B (en) * 2021-07-27 2025-01-21 上海通正铝结构建设科技有限公司 Gabion curtain wall structure and its construction method
CN113863340A (en) * 2021-10-13 2021-12-31 中电建十一局工程有限公司 Cofferdam construction method under complex terrain condition

Also Published As

Publication number Publication date
CN1512011A (en) 2004-07-14

Similar Documents

Publication Publication Date Title
CN1198990C (en) Layered Mesh Reinforced Gabion Retaining Wall for Slope Reinforcement
CN111549799A (en) Comprehensive control system applied to gravel soil slope
CN101899839A (en) A kind of prestressed cantilever opposite tension retaining wall with reinforcement
CN110886327A (en) Basement structure decompression and anti-floating system based on slope area and its construction method
CN111676989A (en) A kind of expansive soil road cutting side slope reinforcement structure and construction method
CN113250240A (en) Combined side slope protection structure and process of layered net type gabion and concrete
CN112431213B (en) Semi-rigid support ecological comprehensive treatment structure of artificial slope and its construction method
CN208280161U (en) The compound retaining wall structure of antifouling type reinforcement pervious concrete
CN113585296A (en) Ecological comprehensive treatment structure for assembled flexible support of artificial slope and construction method thereof
CN108691317A (en) The compound retaining wall of antifouling type reinforcement pervious concrete and its construction method
CN112832288A (en) Anti-floating structure of sloping field building basement and construction method thereof
CN210482362U (en) Assembled rigid and flexible combined elastic anti-seismic reinforced earth retaining wall
CN111622240A (en) Trapezoidal toe-added drainage slide-resistant pile and construction method thereof
CN205296209U (en) Prestressed anchorage cable assembled stake siding wall protective structure
CN212294705U (en) Inflation dirt road moat slope reinforced structure
CN210216318U (en) Ecological river course side slope protective structure
CN208933976U (en) A plant-type ecological concrete slope protection
CN214783977U (en) Compound foundation pit supporting structure of full miscellaneous filled earth stratum
CN111851407A (en) A kind of construction method of gabion retaining wall
CN217419689U (en) Soil body high slope outer buttress formula barricade anchor rope reinforced structure
CN206667263U (en) A kind of foundation pit supporting construction
CN211773946U (en) Basement structure decompression anti system of floating based on slope area
CN208701738U (en) A kind of solid reinforcement combination of rigidity and flexibility ecology retaining wall
CN209384261U (en) A kind of anti-deformation cracking retaining wall structure
CN209066483U (en) A prefabricated ecological retaining wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: China Railway Construction Engineering Bureau No.16 Group Corp., Ltd.

Assignor: Institute of Geology and Geophysics, Chinese Academy of Sciences

Contract fulfillment period: 2009.4.28 to 2014.4.30 contract change

Contract record no.: 2009990000478

Denomination of invention: Layered net type steel bar stone cage barricade for reinforcing slope

Granted publication date: 20050427

License type: Exclusive license

Record date: 2009.5.13

LIC Patent licence contract for exploitation submitted for record

Free format text: EXCLUSIVE LICENSE; TIME LIMIT OF IMPLEMENTING CONTACT: 2009.4.28 TO 2014.4.30; CHANGE OF CONTRACT

Name of requester: CHINA RAILWAY 16 BUREAU GROUP CO., LTD.

Effective date: 20090513

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20050427

Termination date: 20111230