[go: up one dir, main page]

CN117966722A - Anchor pile and pile forming process for sea construction ship - Google Patents

Anchor pile and pile forming process for sea construction ship Download PDF

Info

Publication number
CN117966722A
CN117966722A CN202410082988.4A CN202410082988A CN117966722A CN 117966722 A CN117966722 A CN 117966722A CN 202410082988 A CN202410082988 A CN 202410082988A CN 117966722 A CN117966722 A CN 117966722A
Authority
CN
China
Prior art keywords
pile
anchor
anchor pile
cable
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202410082988.4A
Other languages
Chinese (zh)
Inventor
杨建标
王万里
花长俊
杨跃
万友
武小强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Provincial Institute Of Hydrogeology And Engineering Geology
Original Assignee
Jiangsu Provincial Institute Of Hydrogeology And Engineering Geology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Provincial Institute Of Hydrogeology And Engineering Geology filed Critical Jiangsu Provincial Institute Of Hydrogeology And Engineering Geology
Priority to CN202410082988.4A priority Critical patent/CN117966722A/en
Publication of CN117966722A publication Critical patent/CN117966722A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/54Piles with prefabricated supports or anchoring parts; Anchoring piles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B21/00Tying-up; Shifting, towing, or pushing equipment; Anchoring
    • B63B21/50Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals
    • E02D5/285Prefabricated piles made of steel or other metals tubular, e.g. prefabricated from sheet pile elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/48Piles varying in construction along their length, i.e. along the body between head and shoe, e.g. made of different materials along their length
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/72Pile shoes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving
    • E02D7/06Power-driven drivers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving
    • E02D7/06Power-driven drivers
    • E02D7/14Components for drivers inasmuch as not specially for a specific driver construction

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses an anchor pile of a sea construction ship and a pile forming process, wherein the anchor pile comprises a pile body, the bottom end of the pile body is connected with a pile tip, the top end of the pile body is connected with a loop bar, and a reserved groove a is formed in the loop bar; two lug seats are connected above the pile body, and two counterforce retaining plates are connected below the pile body; the heavy hammer comprises a hammer body, the top end of the hammer body is connected with a joint, and the outer wall of the hammer body is connected with a counterweight rod; the guide rod penetrates into the hammer body through the guide hole, and the top end of the guide rod is connected with a piston; the bottom end of the guide rod is connected with a sleeve pipe matched with the sleeve rod, and a reserved groove b is arranged on the sleeve pipe; the two ends of the recovery cable are respectively connected to the two retaining plates after penetrating through the reserved groove a and the reserved groove b, then extending into the pile body and penetrating out of the reserved hole; two ends of the mooring rope are respectively connected to the two ear seats. The anchor pile type ship exploration device effectively solves the problem that an exploration ship cannot be fixed by adopting an anchor pile mode, and has the advantages of low cost, strong operability, wider application range, recyclability and the like.

Description

Sea area construction ship anchoring pile and pile forming process
Technical Field
The invention relates to the technical field of marine exploration, in particular to an anchor pile of a sea construction ship and a pile forming process.
Background
In general, the stability of an offshore survey construction vessel is a prerequisite for offshore drilling construction operations, while the stability of the construction vessel is affected by weather, tides, storms, waves, underwater formations and the subsea environment within the construction sea.
The anchoring of construction vessels in most sea areas is achieved by means of vessel anchors. In most sea areas, the anchor can be anchored in various modes as long as the anchor holding power allows. However, in special sea areas (such as the side convolution area of the inland river entering the sea), the tide is complex, the wind wave is large, the water is rapid, the underwater suspended garbage is thick, the main garbage is plastic products, knitting, chemical fiber old clothes and the like, the anchor teeth of the grab anchor cannot completely enter the seabed substrate soil layer, the anchor can be moved along with the increasing amount of garbage wound on the anchor teeth, the fixing time of a construction platform cannot ensure a drilling operation period, and the gravity anchor is also. If larger and heavier anchor operation areas are adopted, enough anchor lifting ships and lifting equipment cannot be provided, such as the second-generation wharf extension project of the Francisco of the Seria, the weight of the anchors is increased for a plurality of times during the early investigation, one operation drilling hole cannot be completed by increasing the number of the anchors, and the drilling operation and the construction period are seriously affected.
Therefore, in the case where the conventional anchor fixing method is not applicable, it is necessary to search for a method of fixing a construction vessel in a specific sea area.
Disclosure of Invention
The invention aims to provide an anchor pile of a sea construction ship and a pile forming process, which effectively solve the problem that an exploration ship cannot be fixed by adopting an anchor pile mode, and have the advantages of low cost, strong operability, wider application range, recycling and the like, so as to solve the problems in the prior art.
In order to achieve the above purpose, the present invention provides the following technical solutions:
An anchor pile of a sea construction ship comprises an anchor pile, a heavy hammer, a recovery cable and a mooring cable;
The anchor pile comprises a pile body, wherein the pile body is of a hollow steel pipe structure, the bottom end of the pile body is connected with a spike-shaped pile tip, the top end of the pile body is connected with a sleeve rod, and a reserved groove a is formed in the sleeve rod; two lug seats are connected above the pile body, two counterforce retaining plates are connected below the pile body, and two preformed holes are formed in the pile body above the counterforce retaining plates;
the heavy hammer comprises a hammer body which is of a hollow steel pipe structure, the top end of the hammer body is connected with a joint, and the outer wall of the hammer body is connected with a counterweight rod; the bottom of the hammer body is provided with a guide hole, a guide rod penetrates into the hammer body through the guide hole, and the top end of the guide rod is connected with a piston; the bottom end of the guide rod is connected with a sleeve pipe matched with the sleeve rod, and a reserved groove b is arranged on the sleeve pipe;
the two ends of the recovery cable are respectively connected to the two retaining plates after penetrating through the reserved groove a and the reserved groove b, then extending into the pile body and penetrating out of the reserved hole;
Two ends of the mooring rope are respectively connected to the two ear seats.
The invention further adopts the scheme that the counterforce baffle is symmetrically arranged on the outer wall of the pile body, the bottom end of the counterforce baffle is connected with the pile body through a steel loose-leaf, the outer side of the pile body is connected with a triangular wedge body for limiting the counterforce baffle, and the upper end of the counterforce baffle and the axis of the pile body rotate up and down within the range of 0-60 degrees.
According to the invention, the top end of the counter-force baffle is connected with the pull lugs, and two ends of the recovery cable are respectively connected to the two pull lugs.
The invention further adopts the scheme that the counterweight rods are solid steel pipes, and each counterweight rod is provided with three groups which are arranged up and down at equal intervals, and each group is provided with four counterweight rods.
According to the invention, each group of four weight rods are distributed in an annular array along the axis of the hammer body.
According to the invention, the number of the pistons is two, the pistons are arranged up and down, the steel pistons are in sliding fit with the inner wall of the guide hole, and the bottom end of the hammer body is connected with a baffle for preventing the pistons from falling off.
The invention further adopts the scheme that the hammer bodies at the upper end and the lower end of the counterweight rod are provided with drainage grooves.
According to a further scheme, the recovery cable and the mooring cable are both steel wire ropes.
A pile forming process, which uses the sea construction ship anchoring pile, comprises the following steps:
s1: before piling, a recovery cable and a mooring cable are installed, and the recovery cable and the mooring cable are required to be marked so as to be convenient for operators to distinguish; two ends of the recovery cable penetrate through the top ends of the anchor piles and are respectively fixedly connected to the two pull lugs after penetrating out of the two reserved holes; two ends of the mooring rope are fixedly connected to the two ear seats.
S2: and closing the counterforce baffle on the anchor pile, and wrapping the counterforce baffle on the outer wall of the anchor pile by using an adhesive tape to prevent the counterforce baffle from opening when the anchor pile is launched.
S3: the construction ship is driven to a preset anchor position by utilizing a GPS positioning system, after the construction ship is temporarily fixed, a sleeve rod at the top end of an anchor pile is inserted into a sleeve pipe at the bottom end of a heavy hammer, and is wrapped by an adhesive tape to prevent the anchor pile from falling off from the bottom end of the heavy hammer, and a reserved groove a is flush with a reserved groove b during connection and is used for a recovery cable to pass through, and the recovery cable is tied on a buoy and thrown into the sea; the joint at the top end of the heavy hammer is in threaded fit with a 42mm drill rod, and the anchor pile and the heavy hammer are sequentially lowered by a drilling machine, and the drill rod is 3m above a platform.
S4: and continuously dragging the heavy hammer up and down by using a winch of the drilling machine to knock the anchor pile, and driving the anchor pile into the soil until the whole pile body is completely immersed into the seabed soil layer.
S5: after the anchor pile is formed, the drilling machine recovers the drill rod, the sleeve at the bottom end of the heavy hammer is separated from the sleeve rod at the top end of the anchor pile, and the heavy hammer is recovered; the mooring rope and the construction ship anchor winch are connected through a steel wire rope, the anchor winch is utilized to drag the anchor pile, a soil retaining plate on the anchor pile is automatically opened under the action of external force, and a counterforce system is formed by the anchor pile and the pile body, so that enough counterforce is provided for a mooring rope of the construction ship; and after the towing anchor pile is finished, connecting the mooring rope with the buoy where the retrieving rope is positioned.
S6: and piling the anchor piles in the other three directions in turn in the same manner.
S7: the construction ship is connected with the front anchor pile, the rear anchor pile, the left anchor pile and the right anchor pile, the lengths of the four azimuth cables are adjusted through the front anchor machine, the rear anchor machine, the left anchor machine and the right anchor machine on the ship, the construction ship is moved to a construction hole site, the four azimuth cables are respectively connected with the four mooring cables, and the construction can be started after the cables are tightly twisted and fixed.
S8: after the drilling construction is finished, the mooring ropes in four directions are unwound from the mooring ropes; and (3) driving the construction ship to the upper part of the anchor pile, connecting a recovery cable by using a reamed anchor machine, pulling the anchor pile upwards to recover, closing the retaining plate under the action of the recovery cable, reducing the reaction action of the anchor pile, and pulling out the anchor pile under the dragging of the reamed anchor machine to recover smoothly.
The invention has the beneficial effects that:
The anchor pile and the piling process of the sea construction ship effectively solve the problem that an exploration ship cannot be fixed by adopting an anchor pile mode, have the advantages of low cost, strong operability, recycling and the like, have wider application range, have obvious superiority in the sea areas with more soil, soft clay and seabed garbage and river and lake water areas of similar environments, have the maximum water depth of 40m, are particularly suitable for continuous slow anchor water area walking of a traditional anchor operation platform, especially for pier investigation construction, and can continuously operate four piles to form multiple holes.
Drawings
Fig. 1 is a front cross-sectional view of an anchor pile of the present invention.
Fig. 2 is a partial view of fig. 1.
Fig. 3 is a side view of the anchor pile of the present invention.
Fig. 4 is a top view of the soil guard plate of the present invention.
FIG. 5 is a front sectional view of the weight according to the present invention.
FIG. 6 is a side view of the weight according to the present invention.
Fig. 7 is a schematic view of the working state of the anchor pile according to the present invention.
In the figure: 1-anchor pile, 101-pile body, 102-pile tip, 103-loop bar, 104-reserved groove a, 105-ear seat, 106-counter force retaining plate, 107-reserved hole, 108-steel loose-leaf, 109-triangular wedge, 110-pull lug, 2-heavy hammer, 201-hammer body, 202-joint, 203-counterweight rod, 204-guide hole, 205-guide rod, 206-piston, 207-sleeve, 208-reserved groove b, 209-baffle, 210-drainage groove, 3-recovery cable and 4-mooring cable.
Detailed Description
The invention is further elucidated below in connection with the drawings and the specific embodiments.
Example 1: as shown in fig. 1 to 7, an anchor pile for a marine construction ship comprises an anchor pile 1, a weight 2, a recovery cable 3 and a mooring cable 4.
The total length of the anchor pile 1 is 3400mm, the anchor pile comprises a pile body 101, the pile body 101 is of a hollow thick-wall steel pipe structure with the diameter of 110mm, the bottom end of the pile body 101 is connected with a spike-shaped pile tip 102, the top end of the pile body 101 is connected with a sleeve rod 103 with the length of 200mm and the diameter of 70mm, and a reserved groove a104 is formed in the sleeve rod 103; two lugs 105 are connected to 1/3 of the position below the top end of the pile body 101, two ends of the mooring rope 4 are respectively connected to the two lugs 105, two reaction soil retaining plates 106 with the width of 90mm are connected to the position, which is 101650mm, of the pile body above the pile tip 102, and two reserved holes 107 are formed in the pile body 101 above the reaction soil retaining plates 106.
The counter-force baffle 209 sets up at pile body 101 outer wall symmetry, and counter-force baffle 209 bottom passes through steel loose-leaf 108 with pile body 101 to be connected, and the pile body 101 outside is connected with the triangle wedge 109 that is used for spacing counter-force baffle 209, and counter-force baffle 209 upper end and pile body 101 axis are at 0 ~ 60 within range rotation from top to bottom.
The top end of the reaction force baffle 209 is connected with the pull lugs 110, and both ends of the recovery cable 3 are respectively connected to the two pull lugs 110.
The heavy hammer 2 comprises a hammer body 201, wherein the hammer body 201 is a hollow thick-wall steel pipe with the diameter of 146mm and the length of 4000mm, the top end of the hammer body 201 is connected with a joint 202, and the outer wall of the hammer body 201 is connected with a counterweight rod 203; the bottom of the hammer body 201 is provided with a guide hole 204, a guide rod 205 penetrates into the hammer body 201 through the guide hole 204, and the top end of the guide rod 205 is connected with a piston 206; the bottom end of the guide rod 205 is connected with a sleeve 207 with the diameter of 75mm and the length of 220mm which is matched with the loop bar 103, and a reserved groove b208 is arranged on the sleeve 207.
The recovery cable 3 passes through the reserved groove a104 and the reserved groove b208, then stretches into the pile body 101 and passes out of the reserved hole 107, and two ends of the recovery cable 3 are respectively connected to the two retaining plates.
The weight rods 203 are solid steel pipes with the diameter of 60mm and the length of 800mm, the weight rods 203 are three groups which are arranged at equal intervals up and down, four weight rods 203 are arranged in an annular array along the axis of the hammer body 201, and the hammer body 201 at the upper end and the lower end of the weight rods 203 is provided with 40 multiplied by 350mm drainage grooves 210.
The number of the pistons 206 is two, the diameter of the pistons 206 is 135mm, the distance between the pistons 206 is 250mm, the steel pistons 206 are in sliding fit with the inner wall of the guide holes 204, and the bottom end of the hammer body 201 is connected with a baffle 209 for preventing the pistons 206 from falling off.
Both the recovery cable 3 and the mooring cable 4 are steel wires of 28 mm.
A pile forming process, which uses the sea construction ship anchoring pile, comprises the following steps:
S1: before piling, the recovery cable 3 and the mooring cable 4 are installed, and the recovery cable 3 and the mooring cable 4 need to be marked so as to be convenient for operators to distinguish; two ends of the recovery cable 3 penetrate through the top end of the anchor pile 1 and respectively penetrate out of the two reserved holes 107, and then the two ends of the recovery cable 3 are respectively fixedly connected to the two pull lugs 110; the two ends of the mooring rope 4 are fixedly connected to the two lugs 105.
S2: the counterforce baffle 209 on the anchor pile 1 is closed, and the counterforce baffle is wrapped on the outer wall of the anchor pile 1 by using adhesive tape to prevent the anchor pile from opening when the anchor pile is launched.
S3: the construction ship is driven to a preset anchor position by a GPS positioning system, after the construction ship is temporarily fixed, a sleeve rod 103 at the top end of an anchor pile 1 is inserted into a sleeve 207 at the bottom end of a heavy hammer 2, and is wrapped by an adhesive tape to prevent the anchor pile 1 from falling off from the bottom end of the heavy hammer 2, and a reserved groove a104 is flush with a reserved groove b208 when the construction ship is connected, so that a recovery cable 3 passes through, and a buoy on the recovery cable 3 is thrown into the sea; the joint 202 at the top end of the heavy hammer 2 is in threaded fit with a 42mm drill rod, the anchor pile 1 and the heavy hammer 2 are sequentially lowered by a drilling machine, and the drill rod is 3m above a platform.
S4: the windlass of the drilling machine is utilized to continuously drag the heavy hammer 2 up and down back and forth to strike the anchor pile 1, and the anchor pile 1 is driven into the soil until the whole pile body 101 is completely immersed into the seabed layer.
S5: after the anchor pile 1 is formed, the drilling machine recovers the drill rod, the sleeve 207 at the bottom end of the heavy hammer 2 is separated from the sleeve rod 103 at the top end of the anchor pile 1, and the heavy hammer 2 is recovered; the mooring rope 4 and the construction ship anchor winch are connected through a steel wire rope, the anchor winch is utilized to drag the anchor pile 1, a soil retaining plate on the anchor pile 1 is automatically opened under the action of external force, and a counterforce system is formed by the soil retaining plate and the pile body 101, so that enough counterforce is provided for a mooring rope of the construction ship; after the end of the tie-back anchor pile 1, the mooring line 4 is connected with the buoy where the recovery line 3 is located.
S6: the anchor piles 1 of the other three orientations are piled in turn in the same manner as described above.
S7: the construction ship is connected with the front anchor pile 1, the rear anchor pile 1, the left anchor pile 1 and the right anchor pile 1, the lengths of the four cables in the directions are adjusted through the front anchor winch, the rear anchor winch, the left anchor winch and the right anchor winch on the ship, the construction ship is moved to a construction hole site, the cables in the directions are respectively connected with the four mooring cables 4, and the construction can be started after the cables are tightly twisted and fixed.
S8: after the drilling construction is finished, the mooring ropes in four directions are unwound from the mooring ropes 4; and (3) driving the construction ship to the upper part of the anchor pile 1, connecting the anchor pile 1 with a reaping cable 3 by using a reaping machine, pulling the anchor pile 1 upwards to carry out drawing back, closing the retaining plate under the action of the reaping cable 3, reducing the counterforce of the anchor pile 1, and pulling out the anchor pile 1 under the dragging of the reaping machine to carry out smooth recovery.
In the embodiment, the anchor pile 1 effectively solves the problem that the engineering survey ship cannot be fixed in the second-generation wharf extension of the Francisco of the Seildon, and ensures the smooth completion of projects. The anchor pile 1 technology has the advantages of low cost, strong operability, wide application range, recycling and the like, and particularly has obvious advantages in the sea area with complex submarine environment and thick underwater suspended garbage, especially in the exploration construction of wharfs, and four piles can be continuously operated and are porous.
The tonnage of a construction ship used in the second-generation wharf extension project of the friendship in the second republic of sorgo is about 200 tons, the construction area is located in a near-shore area of the east coast of the atlantic ocean, the maximum water depth is 32m, the four anchor piles 1 are adopted to fix the ship, the construction ship can be firmly fixed, the anchor running condition does not occur in the construction process of nearly 3 months, the reliability of the anchor piles 1 is verified, and the counterforce provided by the anchor piles 1 is also indicated to meet the anchoring requirement of the large-tonnage ship.
The recovery cable 3 and the mooring cable 4 are both made of 28mm steel wire ropes, and because the strength of the mooring cable 4 and the counterforce provided by the anchor piles 1 are relatively large, the distances between anchor positions are relatively wide, and after the four anchor piles 1 are piled, six exploration points in the surrounding area of the anchor piles 1 can be positioned and fixed only by adjusting the relative lengths of four ropes in the front, back, left and right directions on the construction ship, so that the anchoring positioning time is greatly saved, and the construction cost is effectively saved.
The foregoing embodiments are merely illustrative of the technical concept and features of the present invention, and are intended to enable those skilled in the art to understand the present invention and to implement the same, not to limit the scope of the present invention. All equivalent changes or modifications made according to the spirit of the present invention should be included in the scope of the present invention.

Claims (9)

1.一种海域施工船锚固桩,其特征在于:包括锚桩(1)、重锤(2)、回收缆(3)及系泊缆(4);1. An anchor pile for a marine construction vessel, characterized in that it comprises an anchor pile (1), a weight (2), a recovery cable (3) and a mooring cable (4); 所述锚桩(1)包括桩身(101),桩身(101)为空心钢管结构,桩身(101)的底端连接有尖刺状的桩尖(102),桩身(101)顶端连接有套杆(103),套杆(103)上设有预留槽a(104);所述桩身(101)上方连接有两个耳座(105),桩身(101)下方连接有两个反力挡土板(106),反力挡土板(106)上方的桩身(101)上设有两个预留孔(107);The anchor pile (1) comprises a pile body (101), the pile body (101) is a hollow steel pipe structure, the bottom end of the pile body (101) is connected to a spike-shaped pile tip (102), the top end of the pile body (101) is connected to a sleeve rod (103), and the sleeve rod (103) is provided with a reserved groove a (104); two ear seats (105) are connected to the top of the pile body (101), two reaction retaining plates (106) are connected to the bottom of the pile body (101), and two reserved holes (107) are provided on the pile body (101) above the reaction retaining plates (106); 所述重锤(2)包括锤身(201),锤身(201)为空心钢管结构,锤身(201)的顶端连接有接头(202),锤身(201)的外壁连接有配重杆(203);所述锤身(201)底部设有导向孔(204),导杆(205)通过导向孔(204)穿入锤身(201)内部,导杆(205)顶端连接有活塞(206);所述导杆(205)的底端连接有与套杆(103)适配的套管(207),套管(207)上设有预留槽b(208);The heavy hammer (2) comprises a hammer body (201), the hammer body (201) is a hollow steel pipe structure, the top end of the hammer body (201) is connected to a joint (202), and the outer wall of the hammer body (201) is connected to a counterweight rod (203); a guide hole (204) is provided at the bottom of the hammer body (201), a guide rod (205) penetrates into the inside of the hammer body (201) through the guide hole (204), and a piston (206) is connected to the top end of the guide rod (205); a sleeve (207) adapted to the sleeve rod (103) is connected to the bottom end of the guide rod (205), and a reserved groove b (208) is provided on the sleeve (207); 所述回收缆(3)穿过预留槽a(104)、预留槽b(208)后伸入桩身(101)内并从预留孔(107)穿出后,回收缆(3)的两端分别连接于两个挡土板上;The recovery cable (3) passes through the reserved groove a (104) and the reserved groove b (208), extends into the pile body (101), and passes through the reserved hole (107), and then the two ends of the recovery cable (3) are respectively connected to the two retaining plates; 所述系泊缆(4)的两端分别连接于两个耳座(105)上。Both ends of the mooring cable (4) are respectively connected to two ear seats (105). 2.如权利要求1所述的一种海域施工船锚固桩,其特征在于:所述反力挡板(209)在桩身(101)外壁对称设置,反力挡板(209)底端与桩身(101)通过钢质活页(108)连接,桩身(101)外侧连接有用于限位反力挡板(209)的三角楔体(109),反力挡板(209)上端与桩身(101)轴线在0°~60°范围内上下转动。2. An anchor pile for a sea construction ship as described in claim 1, characterized in that: the reaction baffle (209) is symmetrically arranged on the outer wall of the pile body (101), the bottom end of the reaction baffle (209) is connected to the pile body (101) through a steel hinge (108), and a triangular wedge (109) for limiting the reaction baffle (209) is connected to the outer side of the pile body (101), and the upper end of the reaction baffle (209) rotates up and down within the range of 0° to 60° with the axis of the pile body (101). 3.如权利要求2所述的一种海域施工船锚固桩,其特征在于:所述反力挡板(209)的顶端连接有拉耳(110),回收缆(3)的两端分别连接于两个拉耳(110)上。3. An anchor pile for a marine construction vessel as claimed in claim 2, characterized in that: a pull ear (110) is connected to the top of the reaction baffle (209), and both ends of the recovery cable (3) are respectively connected to the two pull ears (110). 4.如权利要求1所述的一种海域施工船锚固桩,其特征在于:所述配重杆(203)为实心钢管,配重杆(203)为上下等距设置的三组,每组共有四根。4. An anchor pile for a marine construction vessel as claimed in claim 1, characterized in that: the counterweight rod (203) is a solid steel pipe, and the counterweight rods (203) are arranged in three groups equidistantly up and down, with four rods in each group. 5.如权利要求4所述的一种海域施工船锚固桩,其特征在于:所述配重杆(203)每组四根沿锤身(201)轴线呈环形阵列排布。5. An anchor pile for a marine construction vessel as claimed in claim 4, characterized in that: each group of four counterweight rods (203) are arranged in a circular array along the axis of the hammer body (201). 6.如权利要求4所述的一种海域施工船锚固桩,其特征在于:所述活塞(206)为上下设置的两个,钢质活塞(206)滑动配合于导向孔(204)内壁,且锤身(201)底端连接有防止活塞(206)脱落的挡板(209)。6. An anchor pile for a marine construction ship as described in claim 4, characterized in that: the piston (206) is provided in two pieces up and down, the steel piston (206) is slidably fitted in the inner wall of the guide hole (204), and the bottom end of the hammer body (201) is connected with a baffle (209) to prevent the piston (206) from falling off. 7.如权利要求6所述的一种海域施工船锚固桩,其特征在于:所述配重杆(203)上下两端的锤身(201)上开设有排水槽(210)。7. An anchor pile for a marine construction vessel as claimed in claim 6, characterized in that drainage grooves (210) are provided on the hammer body (201) at the upper and lower ends of the counterweight rod (203). 8.如权利要求1所述的一种海域施工船锚固桩,其特征在于:所述回收缆(3)与系泊缆(4)均为钢丝绳。8. An anchor pile for a marine construction vessel according to claim 1, characterized in that the recovery cable (3) and the mooring cable (4) are both steel wire ropes. 9.一种成桩工艺,使用如权利要求1-8中任一项所述的海域施工船锚固桩,其特征在于包括如下步骤:9. A pile-forming process, using a marine construction vessel as claimed in any one of claims 1 to 8 to anchor piles, characterized in that it comprises the following steps: S1:成桩前先安装回收缆(3)与系泊缆(4),回收缆(3)与系泊缆(4)需要做上标记以便于作业人员区分;回收缆(3)的两端从锚桩(1)顶端穿入,并分别从两个预留孔(107)穿出后,回收缆(3)的两端分别固接于两个拉耳(110)上;系泊缆(4)的两端固接于两个耳座(105)上;S1: Before pile construction, the recovery cable (3) and the mooring cable (4) are installed. The recovery cable (3) and the mooring cable (4) need to be marked so that the operators can distinguish them. The two ends of the recovery cable (3) are inserted from the top of the anchor pile (1) and respectively pass through the two reserved holes (107). The two ends of the recovery cable (3) are respectively fixed to the two pulling ears (110); the two ends of the mooring cable (4) are fixed to the two ear seats (105); S2:将锚桩(1)上的反力挡板(209)合上,用胶带裹缠于锚桩(1)外壁防止下水时张开;S2: Close the reaction baffle (209) on the anchor pile (1) and wrap it around the outer wall of the anchor pile (1) with tape to prevent it from opening when launching; S3:利用GPS定位系统将施工船开至预置锚位处,暂时固定后,将锚桩(1)顶端的套杆(103)插入重锤(2)底端的套管(207),并用胶带裹缠防止锚桩(1)从重锤(2)底端脱落,连接时预留槽a(104)与预留槽b(208)平齐,用于回收缆(3)穿过,回收缆(3)绳系上浮标抛入海中;重锤(2)顶端的接头(202)螺纹配合于42mm钻杆,利用钻机依次将锚桩(1)及重锤(2)下放,钻杆至平台以上3m左右;S3: Use the GPS positioning system to drive the construction vessel to the preset anchor position. After temporarily fixing it, insert the sleeve rod (103) at the top of the anchor pile (1) into the sleeve (207) at the bottom of the weight (2), and wrap it with tape to prevent the anchor pile (1) from falling off from the bottom of the weight (2). When connected, the reserved groove a (104) is flush with the reserved groove b (208) for the recovery cable (3) to pass through. The recovery cable (3) is tied to the buoy and thrown into the sea; the joint (202) at the top of the weight (2) is threaded to fit the 42 mm drill rod, and the anchor pile (1) and the weight (2) are lowered in turn by using a drilling rig, and the drill rod is about 3 m above the platform; S4:利用钻机的卷扬机连续上下来回拖动重锤(2)敲击锚桩(1),将锚桩(1)打入土中,直至整个桩身(101)全部没入海底土层中;S4: using the winch of the drilling rig to continuously drag the heavy hammer (2) up and down to strike the anchor pile (1), thereby driving the anchor pile (1) into the soil until the entire pile body (101) is completely submerged in the seabed soil layer; S5:锚桩(1)成桩后,钻机将钻杆回收,重锤(2)底端的套管(207)与锚桩(1)顶端的套杆(103)脱离,将重锤(2)回收;将系泊缆(4)和施工船绞锚机通过钢丝绳连接,利用绞锚机回拖锚桩(1),锚桩(1)上的挡土板在外力作用下自动张开,和桩身(101)一起构成反力系统,为施工船的缆绳提供足够反力;回拖锚桩(1)结束后,将系泊缆(4)与回收缆(3)所在的浮标连接;S5: After the anchor pile (1) is formed, the drilling rig recovers the drill rod, the casing (207) at the bottom end of the weight (2) is separated from the casing rod (103) at the top end of the anchor pile (1), and the weight (2) is recovered; the mooring cable (4) and the anchor winch of the construction ship are connected by a steel wire rope, and the anchor pile (1) is towed back by the anchor winch. The retaining plate on the anchor pile (1) is automatically opened under the action of external force, and together with the pile body (101), a reaction force system is formed to provide sufficient reaction force for the cable of the construction ship; after the anchor pile (1) is towed back, the mooring cable (4) is connected to the buoy where the recovery cable (3) is located; S6:采用上述同样的方式依次将另外三个方位的锚桩(1)成桩;S6: Using the same method as above, the anchor piles (1) at the other three positions are piled one by one; S7:将施工船与前、后、左、右四个锚桩(1)连接好,通过船上前、后、左、右四台绞锚机调整四个方位缆绳的长度,将施工船移至施工孔位处,四个方位的缆绳分别与四个系泊缆(4)连接,并将缆绳绞紧固定后就可以开始施工;S7: Connect the construction ship to the front, rear, left and right anchor piles (1), adjust the lengths of the cables in the four directions by using the front, rear, left and right anchor winches on the ship, move the construction ship to the construction hole location, connect the cables in the four directions to the four mooring cables (4) respectively, and start construction after the cables are tightened and fixed; S8:钻探施工结束后,四个方位的缆绳从系泊缆(4)上解开;将施工船行驶至锚桩(1)上方,用绞锚机连接回收缆(3),将锚桩(1)向上拉动回拖,挡土板在回收缆(3)作用下闭合,锚桩(1)反力作用变小,锚桩(1)在绞锚机的拖动下被拔出,顺利回收。S8: After the drilling construction is completed, the cables in the four directions are untied from the mooring cable (4); the construction vessel is moved to the top of the anchor pile (1), and the recovery cable (3) is connected with the windlass to pull the anchor pile (1) upward and backhaul. The retaining plate is closed under the action of the recovery cable (3), and the reaction force of the anchor pile (1) becomes smaller. The anchor pile (1) is pulled out under the drag of the windlass and recovered smoothly.
CN202410082988.4A 2024-01-19 2024-01-19 Anchor pile and pile forming process for sea construction ship Pending CN117966722A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202410082988.4A CN117966722A (en) 2024-01-19 2024-01-19 Anchor pile and pile forming process for sea construction ship

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202410082988.4A CN117966722A (en) 2024-01-19 2024-01-19 Anchor pile and pile forming process for sea construction ship

Publications (1)

Publication Number Publication Date
CN117966722A true CN117966722A (en) 2024-05-03

Family

ID=90860911

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202410082988.4A Pending CN117966722A (en) 2024-01-19 2024-01-19 Anchor pile and pile forming process for sea construction ship

Country Status (1)

Country Link
CN (1) CN117966722A (en)

Similar Documents

Publication Publication Date Title
US6009825A (en) Recoverable system for mooring mobile offshore drilling units
CN109969341B (en) Grouting screw anchor capable of opening multi-layer side walls and installation method thereof
EP0972114B1 (en) Position penetrated anchor system and its use
US20120263540A1 (en) Subsea cable installation unit
Wang et al. Latest progress in deepwater installation technologies
US4048945A (en) Removable anchor having retrievable ballast
KR20230112665A (en) Anchor Systems and Methods
CN113928477A (en) Gravity injection type deepwater anchor and construction method
NO812498L (en) TEMPORA EXTENSION FOR TENSION PLATFORM.
CN116093836B (en) A method for passing a multi-ship abutting submarine cable protection tube through an embankment in a 360-degree rotating flow field
CN114889747B (en) A method for implementing a multi-purpose floating anchoring device
CN1060550C (en) Barge-supported skid-type beach sea trenching device
CN117966722A (en) Anchor pile and pile forming process for sea construction ship
CN218771207U (en) Vertical ground anchor that bores of fixed seabed optical cable
CN113964736A (en) Submarine cable long-distance intertidal zone landing construction process
CN111021401A (en) Extensible grouting type anchoring foundation and construction method thereof
CN214690075U (en) Waterborne ship drilling platform for engineering investigation
CN113585343B (en) A cable-stayed floating tunnel with cable flow piers and its construction method
CN111764418B (en) Steel cofferdam positioning system in deep water
CN210529503U (en) A positioning device for a suspension bridge beam-carrying ship
CN116620478A (en) Simple three-cable positioning method for self-propelled cutter suction dredger
JP2000355960A (en) Intake method for deep ocean water
CN221775977U (en) Triangular floating platform anchor mooring structure
CN218317228U (en) Construction equipment suitable for underwater equipment is buried underground
CN216185836U (en) Gravity injection type deepwater anchor

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Country or region after: China

Address after: 223003 Jiangsu Province Huai'an City Tianjin Road 108 Haizhou District

Applicant after: Jiangsu Hydrogeological and Engineering Geological Survey Institute Co., Ltd.

Address before: 223003 Jiangsu Province Huai'an City Tianjin Road 108 Haizhou District

Applicant before: Jiangsu Provincial Institute of Hydrogeology and Engineering Geology

Country or region before: China