[go: up one dir, main page]

CN117026720A - Pavement subbase layer construction method based on precast beam field concrete panel - Google Patents

Pavement subbase layer construction method based on precast beam field concrete panel Download PDF

Info

Publication number
CN117026720A
CN117026720A CN202311185266.3A CN202311185266A CN117026720A CN 117026720 A CN117026720 A CN 117026720A CN 202311185266 A CN202311185266 A CN 202311185266A CN 117026720 A CN117026720 A CN 117026720A
Authority
CN
China
Prior art keywords
concrete panel
beam field
precast beam
pavement
pedestal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311185266.3A
Other languages
Chinese (zh)
Inventor
周胜利
余威
周斌
浣启超
彭程
曾美容
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Road and Bridge Construction Group Co Ltd
Original Assignee
Hunan Road and Bridge Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Road and Bridge Construction Group Co Ltd filed Critical Hunan Road and Bridge Construction Group Co Ltd
Priority to CN202311185266.3A priority Critical patent/CN117026720A/en
Publication of CN117026720A publication Critical patent/CN117026720A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/32Coherent pavings made in situ made of road-metal and binders of courses of different kind made in situ
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/02Arrangement or construction of joints; Methods of making joints; Packing for joints
    • E01C11/04Arrangement or construction of joints; Methods of making joints; Packing for joints for cement concrete paving
    • E01C11/10Packing of plastic or elastic materials, e.g. wood, resin
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The application provides a pavement subbase layer construction method based on a precast beam field concrete panel, which comprises the following steps: s1, paving a gravel cushion layer on a road base layer in a beam field construction stage, pouring a concrete panel on the gravel cushion layer, and setting a fracture joint and an expansion joint; s2, after prefabrication of the small box girder is completed, breaking the pedestal and the track pedestal, and reserving a concrete panel; s3, checking the concrete panel, further cleaning the broken joint and the expansion joint on the concrete panel, removing scraps in the cut, filling the water stop strip in the broken joint, embedding the filling material in the expansion joint, and finishing waterproof treatment; s4, paving a water-stable subbase layer on the concrete panel. The application can save materials and manpower in the road construction process, reduce construction noise and dust, improve the bearing capacity and the service life of the road surface structure, and reduce the later maintenance cost.

Description

一种基于预制梁场混凝土面板的路面底基层垫层施工方法A construction method of pavement subbase cushion based on prefabricated beam field concrete panels

技术领域Technical field

本发明涉及公路施工技术领域,具体涉及一种基于预制梁场混凝土面板的路面底基层垫层施工方法。The invention relates to the technical field of highway construction, and in particular to a pavement subbase cushion construction method based on prefabricated beam field concrete panels.

背景技术Background technique

公路路面结构一般由上至下分为沥青混凝土面层、水稳底基层和路基层。其中,水稳底基层是连接路基和沥青混凝土面层的重要组成部分,起着隔水和传递荷载的作用。水稳底基层一般采用水泥稳定碎石、沥青稳定碎石等材料,其施工质量直接影响路面的承载力和使用寿命。The highway pavement structure is generally divided from top to bottom into asphalt concrete surface layer, water stable base layer and road base layer. Among them, the water-stabilized subbase is an important component connecting the roadbed and asphalt concrete surface layer, playing the role of water isolation and load transmission. The water-stabilized base layer generally uses cement-stabilized gravel, asphalt-stabilized gravel and other materials. Its construction quality directly affects the bearing capacity and service life of the pavement.

在高速公路建设过程中,通常需要在预定位置建设预制梁场,用于生产预应力混凝土箱梁等桥梁构件。预制梁场一般采用混凝土硬化处理,形成坚固平整的混凝土面板,以承受箱梁等构件的重量和运输车辆的荷载。预制梁场使用完毕后,需要对混凝土面板进行拆除和处理,以便恢复原有的路基结构。这种传统的施工工艺不仅增加了施工难度和费用,而且造成了混凝土材料的浪费和污染。During highway construction, it is usually necessary to build a precast beam field at a predetermined location for the production of bridge components such as prestressed concrete box girders. Prefabricated beam fields generally adopt concrete hardening treatment to form a strong and flat concrete panel to withstand the weight of components such as box beams and the load of transportation vehicles. After the precast beam field is used, the concrete panels need to be removed and processed to restore the original roadbed structure. This traditional construction technology not only increases the difficulty and cost of construction, but also causes waste and pollution of concrete materials.

因此,如何有效利用预制梁场不破除的混凝土面板,提高其再利用率和资源节约性,是目前本领域技术人员亟需解决的技术问题。Therefore, how to effectively utilize the concrete panels that are not broken in the precast beam field and improve their reuse rate and resource conservation is a technical problem that technicians in the field urgently need to solve.

发明内容Contents of the invention

有鉴于此,本发明提供了一种基于预制梁场混凝土面板的路面底基层垫层施工方法,用以至少解决现有技术中施工难度大和浪费严重的问题。In view of this, the present invention provides a pavement subbase cushion construction method based on precast beam field concrete panels to at least solve the problems of high construction difficulty and serious waste in the prior art.

为了实现上述目的,本发明采用如下技术方案:In order to achieve the above objects, the present invention adopts the following technical solutions:

一种基于预制梁场混凝土面板的路面底基层垫层施工方法,包括以下步骤:A pavement subbase cushion construction method based on precast beam field concrete panels includes the following steps:

S1.在梁场建设阶段,在路基层上铺设碎石垫层,在碎石垫层上浇筑混凝土面板,并设置断缝和伸缩缝;S1. In the construction stage of the beam yard, a gravel cushion is laid on the roadbed, a concrete panel is poured on the gravel cushion, and fracture joints and expansion joints are set;

S2.在小箱梁预制完成后,对台座及轨道台座进行破除,保留所述混凝土面板;S2. After the prefabrication of the small box beams is completed, remove the pedestal and track pedestal, and retain the concrete panel;

S3.对所述混凝土面板进行检查,并进一步对所述混凝土面板上的断缝和伸缩缝进行清理,去除切口内的碎屑,在所述断缝内填充止水带,所述伸缩缝内嵌入填充材料,并完成防水处理;S3. Inspect the concrete panel, and further clean the broken joints and expansion joints on the concrete panel, remove debris in the cuts, fill waterstops in the broken joints, and fill the expansion joints with Embed filling material and complete waterproofing treatment;

S4.在所述混凝土面板上摊铺水稳底基层。S4. Spread a water-stabilized base layer on the concrete panel.

优选的,所述碎石垫层的厚度为5cm,所述混凝土面板的厚度为25cm。Preferably, the thickness of the gravel cushion is 5 cm, and the thickness of the concrete panel is 25 cm.

优选的,在S1中,所述混凝土面板顶面标高按精加工顶面标高控制,对于填方段,根据梁场使用时的梁板重量及重车行走重量对标高设置预抬值。Preferably, in S1, the top elevation of the concrete panel is controlled according to the finishing top elevation. For the fill section, a pre-lift value is set for the elevation based on the weight of the beam plate and the weight of the heavy truck when used in the beam yard.

优选的,在S1中,浇筑混凝土面板过程中,所述台座与所要浇筑的所述混凝土面板之间先预埋有钢筋。Preferably, in S1, during the process of pouring the concrete panel, steel bars are pre-embedded between the base and the concrete panel to be poured.

优选的,在S1中,浇筑所述台座时,在进行整体硬化过程中,于所述台座两端区域范围内布置钢筋。Preferably, in S1, when the pedestal is poured, steel bars are arranged within the two end areas of the pedestal during the overall hardening process.

优选的,前期轨道扩大基础施工时,将顶面高程设置为低于混凝土面板顶面高程。Preferably, during the early stage of track expansion foundation construction, the top elevation is set lower than the top elevation of the concrete panel.

优选的,断缝和伸缩缝的位置和尺寸按照混凝土面板的长度和宽度进行分块划分。Preferably, the locations and sizes of fracture joints and expansion joints are divided into blocks according to the length and width of the concrete panel.

优选的,S3中对所述混凝土面板进行检查的检查项目包括弯沉、底板脱空、裂缝、空鼓、蜂窝、标高和平整度,当发现缺陷或偏差,进行修补或更换。Preferably, the inspection items for inspecting the concrete panel in S3 include deflection, bottom plate hollowing, cracks, hollows, honeycombs, elevation and flatness. When defects or deviations are found, they are repaired or replaced.

优选的,S3中的所述防水处理包括在伸缩缝内嵌入填充材料,并涂刷防水材料;其中所述填充材料包括聚氨酯泡沫条;所述防水材料包括密封胶。Preferably, the waterproofing treatment in S3 includes embedding filling material in the expansion joint and applying waterproof material; wherein the filling material includes polyurethane foam strips; and the waterproofing material includes sealant.

优选的,S4的具体内容包括:Preferably, the specific contents of S4 include:

确定摊铺厚度,并设置摊铺厚度控制点;Determine the paving thickness and set the paving thickness control points;

将水稳料均匀地摊铺在所述混凝土面板上,并调整摊铺宽度和坡度;Spread the water-stabilizing material evenly on the concrete panel, and adjust the paving width and slope;

对水稳料进行压实,并检测其密实度是否符合规范要求。Compact the water-stabilized material and check whether its compactness meets the specification requirements.

经由上述的技术方案可知,与现有技术相比,本发明公开提供了一种基于预制梁场混凝土面板的路面底基层垫层施工方法,具有以下有益效果:It can be seen from the above technical solutions that compared with the existing technology, the present invention provides a pavement subbase cushion construction method based on prefabricated beam field concrete panels, which has the following beneficial effects:

(1)利用预制梁场不破除的混凝土面板作为路面底基层垫层,避免了对混凝土面板的拆除和处理,节约了材料和人力,减少了施工噪音和粉尘;(1) Use the concrete panels that cannot be broken in the prefabricated beam field as the pavement base layer, avoiding the dismantling and processing of the concrete panels, saving materials and manpower, and reducing construction noise and dust;

(2)混凝土面板具有高强度、耐久性好、防水性强等优点,能够有效提高路面结构的承载力和使用寿命,降低后期维护费用;(2) Concrete panels have the advantages of high strength, good durability, and strong waterproofness, which can effectively improve the bearing capacity and service life of the pavement structure and reduce subsequent maintenance costs;

(3)混凝土面板采用板块化施工,设置合理的断缝和伸缩缝,防止热胀冷缩引起的裂缝和变形,保证路面平整度和稳定性;(3) The concrete panel adopts modular construction and sets reasonable fracture joints and expansion joints to prevent cracks and deformation caused by thermal expansion and contraction, and ensure the smoothness and stability of the road surface;

(4)该方法简化了路面底基层的施工流程,缩短了施工周期,提高了施工效率。(4) This method simplifies the construction process of the pavement subbase, shortens the construction period, and improves construction efficiency.

附图说明Description of the drawings

为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to explain the embodiments of the present invention or the technical solutions in the prior art more clearly, the drawings needed to be used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings in the following description are only These are some embodiments of the present invention. For those of ordinary skill in the art, other drawings can be obtained based on these drawings without exerting creative efforts.

图1为本发明提供的一种基于预制梁场混凝土面板的路面底基层垫层施工方法的流程示意图。Figure 1 is a schematic flow chart of a pavement subbase cushion construction method based on precast beam field concrete panels provided by the present invention.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, of the embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts fall within the scope of protection of the present invention.

本发明提供了一种基于预制梁场混凝土面板的路面底基层垫层施工方法,如图1所示,包括以下步骤:The invention provides a pavement subbase cushion construction method based on prefabricated beam field concrete panels. As shown in Figure 1, it includes the following steps:

S1.在梁场建设阶段,在路基层上铺设碎石垫层,在碎石垫层上浇筑混凝土面板,并设置断缝和伸缩缝;S1. In the construction stage of the beam yard, a gravel cushion is laid on the roadbed, a concrete panel is poured on the gravel cushion, and fracture joints and expansion joints are set;

S2.在小箱梁预制完成后,对台座及轨道台座进行破除,保留混凝土面板;S2. After the prefabrication of the small box beams is completed, remove the pedestal and track pedestal and retain the concrete panel;

S3.对混凝土面板进行检查,并进一步对混凝土面板上的断缝和伸缩缝进行清理,去除切口内的碎屑,在断缝内填充止水带,伸缩缝内嵌入填充材料,并完成防水处理;S3. Inspect the concrete panel, and further clean the fractures and expansion joints on the concrete panel, remove debris in the cuts, fill the fractures with waterstops, embed filling materials in the expansion joints, and complete the waterproofing treatment ;

S4.在混凝土面板上摊铺水稳底基层。S4. Pave the water-stabilized base layer on the concrete panel.

在本实施例中,梁场长587m,宽31m,总面积18197平米。采用炮除的方式对台座及轨道台座进行破除,炮除时应注意控制爆破量和爆破方向,防止对混凝土面板造成损坏。In this embodiment, the beam field is 587m long, 31m wide, and has a total area of 18,197 square meters. The pedestal and track pedestal are demolished by blasting. When blasting, attention should be paid to controlling the blasting volume and blasting direction to prevent damage to the concrete panel.

需要说明的是:断缝和伸缩缝的设置是为了防止混凝土面板因温度变化而产生裂缝和变形,影响路面结构的稳定性和平整度。It should be noted that the setting of fracture joints and expansion joints is to prevent cracks and deformation of the concrete panel due to temperature changes, which will affect the stability and smoothness of the pavement structure.

为了进一步实施上述技术方案,碎石垫层的厚度为5cm,混凝土面板的厚度为25cm。In order to further implement the above technical solution, the thickness of the gravel cushion is 5cm and the thickness of the concrete panel is 25cm.

需要说明的是:It should be noted:

高速公路上路床厚度30cm,碎石垫层5cm、混凝土面板25cm,能提高面板承载能力及调整地基的不均匀沉降。The thickness of the road bed on the highway is 30cm, the gravel cushion is 5cm, and the concrete panel is 25cm, which can improve the load-bearing capacity of the panel and adjust the uneven settlement of the foundation.

为了进一步实施上述技术方案,在S1中,混凝土面板顶面标高按精加工顶面标高控制,对于填方段,根据梁场使用时的梁板重量及重车行走重量对标高设置预抬值。In order to further implement the above technical solution, in S1, the top elevation of the concrete panel is controlled according to the finishing top elevation. For the fill section, the pre-lift value is set for the elevation according to the weight of the beam plate and the weight of the heavy truck when used in the beam field.

实际应用时,精加工顶面标高控制:标高为设计值,根据桥规规定的断面测量办法控制即可;梁板重量和重车行走重量对标高设置预抬值:为施工经验所得,仅在梁场设置在填方区域考虑预抬值,每填筑1m高度,需增加预抬值0.006m。梁场若设置在挖方区域,由于地基十分稳定,基本不会发生沉降,因此不考虑预抬值。In actual application, the elevation of the finishing top surface is controlled: the elevation is the design value, which can be controlled according to the cross-sectional measurement method stipulated in the bridge regulations; the weight of the beam plate and the weight of the heavy vehicle travel set a pre-lift value for the elevation: it is obtained from construction experience and is only used when When setting up the beam field in the fill area, the pre-lift value should be taken into consideration. For every 1m of filling height, the pre-lift value needs to be increased by 0.006m. If the beam field is set up in the excavation area, since the foundation is very stable, settlement will basically not occur, so the pre-lift value is not considered.

为了进一步实施上述技术方案,在S1中,浇筑混凝土面板过程中,所述台座与所要浇筑的所述混凝土面板之间先预埋有钢筋。In order to further implement the above technical solution, in S1, during the process of pouring the concrete panel, steel bars are pre-embedded between the base and the concrete panel to be poured.

需要说明的是:考虑后期台座及轨道台座破除时不影响混凝土面板整体性,前期进行场地硬化时为先整体浇筑混凝土,在台座与混凝土面板之间预埋钢筋,以增强连接强度。It should be noted that considering that the integrity of the concrete panel will not be affected when the pedestal and track pedestal are removed in the later stage, concrete is poured as a whole during site hardening in the early stage, and steel bars are pre-embedded between the pedestal and the concrete panel to enhance the connection strength.

为了进一步实施上述技术方案,在S1中,浇筑台座时,在进行整体硬化过程中,于台座两端区域范围内布置钢筋。In order to further implement the above technical solution, in S1, when the pedestal is poured, steel bars are arranged within the two end areas of the pedestal during the overall hardening process.

需要说明的是:浇筑台座时,考虑后续张拉工艺,梁体起拱对台座两端造成的压力较大,为提高台座两端的承载能力,于台座两端区域范围内布置钢筋。It should be noted that when pouring the pedestal, considering the subsequent tensioning process, the arching of the beam body will cause greater pressure on both ends of the pedestal. In order to improve the load-bearing capacity of both ends of the pedestal, steel bars are arranged within the area at both ends of the pedestal.

为了进一步实施上述技术方案,前期轨道扩大基础施工时,将顶面高程设置为低于混凝土面板顶面高程。In order to further implement the above technical solution, during the initial construction of the track expansion foundation, the top elevation was set lower than the top elevation of the concrete panel.

需要说明的是:轨道扩大基础即梁场龙门吊轨道扩大基础,位置沿梁场长度方向纵向布置,与梁场面板混凝土浇筑同时施工;龙门吊轨道扩大基础为龙门吊布置的关键工序,是梁场进行产梁运作的必要条件。It should be noted that the track expansion foundation is the beam yard gantry crane track expansion foundation, which is arranged longitudinally along the length of the beam yard and is constructed at the same time as the concrete pouring of the beam yard panel; the gantry crane track expansion foundation is a key process for the gantry crane layout and is the key to the production of the beam yard. Necessary conditions for beam operation.

将顶面高程设置为低于混凝土面板顶面高程是考虑后续轨道台座破除时扩大基础顶板不高于精加工顶面标高。Setting the top elevation lower than the top elevation of the concrete panel is to consider that the expanded foundation roof will not be higher than the finishing top elevation when the track pedestal is subsequently broken.

为了进一步实施上述技术方案,断缝和伸缩缝的位置和尺寸按照混凝土面板的长度和宽度进行分块划分。In order to further implement the above technical solution, the positions and sizes of fracture joints and expansion joints are divided into blocks according to the length and width of the concrete panel.

一般实施过程中纵向断缝位置根据梁场区域进行划分,其中梁场区域包括梁场边缘液压模板摆放区域、梁场预制台座摆放区域和梁场预制台座摆放区域,横向伸缩缝根据梁场内排水沟的布置;在本实施例中,将混凝土面板纵向分块为2.5+10.5+4+10.5+2.5m,其中,2.5m指梁场边缘液压模板摆放区域,实际距离梁场边线2.5m;10.5m指梁场预制台座摆放区域,实际距离梁场边线13m;4m指梁场中间行车道区域,实际距离梁场边线17m;横向在横向水沟位置断开,断开距离40m。断缝和伸缩缝的宽度均为2cm,深度为10cm。During the general implementation process, the longitudinal fracture positions are divided according to the beam field area. The beam field area includes the hydraulic formwork placement area at the edge of the beam field, the beam field prefabricated pedestal placement area, and the beam field prefabricated pedestal placement area. The horizontal expansion joints are divided according to the beam field area. Arrangement of drainage ditches in the site; in this embodiment, the concrete panel is longitudinally divided into 2.5+10.5+4+10.5+2.5m, where 2.5m refers to the area where the hydraulic formwork is placed at the edge of the beam field, and the actual distance from the edge of the beam field 2.5m; 10.5m refers to the area where the prefabricated pedestal is placed in the beam yard, and is actually 13m away from the sideline of the beam yard; 4m refers to the middle lane area of the beam yard, which is actually 17m away from the sideline of the beam yard; it is disconnected laterally at the horizontal ditch position, and the disconnection distance is 40m . The width of the break joint and the expansion joint are both 2cm and the depth is 10cm.

为了进一步实施上述技术方案,S3中对混凝土面板进行检查的检查项目包括弯沉、底板脱空、裂缝、空鼓、蜂窝、标高和平整度,当发现缺陷或偏差,进行修补或更换。In order to further implement the above technical solution, the inspection items of concrete panels in S3 include deflection, bottom plate hollowing, cracks, hollows, honeycombs, elevation and flatness. When defects or deviations are found, they will be repaired or replaced.

在本实施例中,根据湖南省交通规划勘察设计院有限公司验收指标要求,K7+890~K8+477段预制场混凝土面板弯沉要求:≤45(0.01mm)。标高要求:±5cm,对高于路床顶面设计标高5cm的混凝土面板进行铣创处理,对低于路床顶面设计标高的路段采用水稳材料调平至路床顶标高(在路面水稳底基层施工时进行调平)。In this embodiment, according to the acceptance index requirements of Hunan Provincial Transportation Planning, Survey and Design Institute Co., Ltd., the deflection requirements of the concrete panels in the precast yard in the K7+890~K8+477 section are: ≤45 (0.01mm). Elevation requirements: ±5cm. Concrete panels 5cm higher than the design elevation of the top of the road bed shall be milled. Road sections lower than the design elevation of the top of the road bed shall be leveled with water-stabilizing materials to the elevation of the top of the road bed (in the water level of the road surface). Leveling should be carried out during construction to stabilize the base layer).

为了进一步实施上述技术方案,S3中的防水处理包括在伸缩缝内嵌入填充材料,并涂刷防水材料;其中填充材料包括聚氨酯泡沫条;防水材料包括密封胶。In order to further implement the above technical solution, the waterproofing treatment in S3 includes embedding filling material in the expansion joint and applying waterproof material; the filling material includes polyurethane foam strips; the waterproofing material includes sealant.

在本实施例中,断缝和伸缩缝的宽度均为2cm,深度为10cm。止水带为橡胶止水带,聚氨酯泡沫条为柔性泡沫条,密封胶为聚氨酯密封胶。填充时应保证填充材料的均匀性和紧密性,防止渗水和松动。In this embodiment, the width of the break seam and the expansion joint are both 2cm and the depth is 10cm. The waterstop is a rubber waterstop, the polyurethane foam strip is a flexible foam strip, and the sealant is polyurethane sealant. When filling, the uniformity and tightness of the filling material should be ensured to prevent water seepage and looseness.

为了进一步实施上述技术方案,S4的具体内容包括:In order to further implement the above technical solutions, the specific contents of S4 include:

确定摊铺厚度,并设置摊铺厚度控制点;Determine the paving thickness and set the paving thickness control points;

将水稳料均匀地摊铺在混凝土面板上,并调整摊铺宽度和坡度;Spread the water-stabilizing material evenly on the concrete panel, and adjust the paving width and slope;

对水稳料进行压实,并检测其密实度是否符合规范要求。Compact the water-stabilized material and check whether its compactness meets the specification requirements.

在具体实施过程中,水稳底基层的厚度设置为20cm,其中包括4%的水泥稳定碎石,抗压强度为3~5Mpa;During the specific implementation process, the thickness of the water-stabilized base was set to 20cm, including 4% cement-stabilized gravel, with a compressive strength of 3-5Mpa;

水稳料采用专用摊铺机进行摊铺,并使用传感器自动控制摊铺厚度和横坡。摊铺速度应保持恒定,控制在1.0~3.0m/min之间。The water-stabilized material is paved using a special paver, and sensors are used to automatically control the paving thickness and cross slope. The paving speed should be kept constant and controlled between 1.0 and 3.0m/min.

摊铺后,对水稳料进行碾压。碾压顺序为:先用静压式压路机初压2遍,再用振动式压路机复压4遍,最后用胶轮式或双钢轮式压路机光碾2遍。碾压速度根据不同类型的压路机和不同阶段的碾压而适当调整,一般在1.5~2.5km/h之间。碾压时,边碾压边检测密实度和平整度,并及时处理不合格处。After paving, the water-stabilized material is rolled. The rolling sequence is: first use a static pressure roller for 2 passes, then use a vibratory roller for 4 passes, and finally use a rubber wheel or double steel wheel roller for 2 passes. The rolling speed is appropriately adjusted according to different types of road rollers and different stages of rolling, generally between 1.5 and 2.5km/h. When rolling, check the compactness and flatness while rolling, and deal with unqualified parts in time.

水稳料施工完成后,及时进行养生保护。养生保护应在水泥终凝后开始,并封闭交通不少于7天。养生期间应保持表面湿润,采用洒水或覆盖土工布等方法进行养生。养生期间严禁重车交通行驶。After the construction of water stabilizing materials is completed, health care and protection should be carried out in time. Health protection should start after the cement is finally set, and traffic should be closed for no less than 7 days. During the curing period, the surface should be kept moist, and methods such as sprinkling water or covering with geotextile should be used for curing. Heavy vehicle traffic is strictly prohibited during the health care period.

以上实施例仅用以说明本申请的技术方案,而非对其限制;尽管参照前述实施例对本申请进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本申请各实施例技术方案的精神和范围,均应包含在本申请的保护范围之内。The above embodiments are only used to illustrate the technical solutions of the present application, but are not intended to limit them. Although the present application has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that they can still modify the technical solutions described in the foregoing embodiments. Modifications are made to the recorded technical solutions, or equivalent substitutions are made to some of the technical features; these modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the spirit and scope of the technical solutions of the embodiments of this application, and shall be included in this application. within the scope of protection.

Claims (10)

1. The pavement subbase layer construction method based on the precast beam field concrete panel is characterized by comprising the following steps of:
s1, paving a gravel cushion layer on a road base layer in a beam field construction stage, pouring a concrete panel on the gravel cushion layer, and setting a fracture joint and an expansion joint;
s2, after prefabrication of the small box girder is completed, breaking the pedestal and the track pedestal, and reserving the concrete panel;
s3, checking the concrete panel, further cleaning a broken joint and an expansion joint on the concrete panel, removing scraps in the cut, filling a water stop strip in the broken joint, embedding a filling material in the expansion joint, and finishing waterproof treatment;
s4, paving a water-stable subbase layer on the concrete panel.
2. The method for constructing the pavement subbase layer based on the precast beam field concrete panel according to claim 1, wherein the thickness of the crushed stone subbase layer is 5cm, and the thickness of the concrete panel is 25cm.
3. The construction method of the pavement subbase layer based on the precast beam field concrete panel according to claim 1, wherein in S1, the elevation of the top surface of the concrete panel is controlled according to the elevation of the finish top surface, and for the filling section, a pre-lifting value is set according to the weight of the beam slab and the walking weight of the heavy truck when the beam field is used.
4. The construction method of the pavement subbase layer based on the precast beam field concrete panel according to claim 1, wherein in the step S1, steel bars are pre-buried between the pedestal and the concrete panel to be poured in the process of pouring the concrete panel.
5. The method for constructing a pavement underlayment layer based on precast beam field concrete panels according to claim 1, wherein in S1, steel bars are arranged in the range of the two end regions of the pedestal in the process of integral hardening when the pedestal is poured.
6. The method for constructing a pavement subbase layer based on a precast beam field concrete panel according to claim 1, wherein the top surface elevation is set to be lower than the top surface elevation of the concrete panel in the preliminary track expansion foundation construction.
7. The method for constructing a pavement subbase layer based on a precast beam field concrete panel according to claim 1, wherein the positions and the sizes of the break joints and the expansion joints are divided into blocks according to the length and the width of the concrete panel.
8. The method for constructing a pavement underlayment layer based on precast beam farm concrete panels according to claim 1, wherein the inspection items for inspecting the concrete panels in S3 include deflection, floor run-out, cracks, hollows, honeycomb, elevation and flatness, and repair or replacement is performed when defects or deviations are found.
9. The construction method of a pavement subbase layer based on a precast beam field concrete panel according to claim 1, wherein the waterproofing treatment in S3 comprises embedding a filler material in an expansion joint and brushing a waterproofing material; wherein the filler material comprises polyurethane foam strips; the waterproof material comprises a sealant.
10. The pavement subbase layer construction method based on the precast beam field concrete panel according to claim 1, wherein the specific content of S4 comprises:
determining a paving thickness, and setting a paving thickness control point;
uniformly spreading the water stabilizing material on the concrete panel, and adjusting spreading width and gradient;
compacting the water stable material and detecting whether the compactness meets the specification requirement.
CN202311185266.3A 2023-09-13 2023-09-13 Pavement subbase layer construction method based on precast beam field concrete panel Pending CN117026720A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311185266.3A CN117026720A (en) 2023-09-13 2023-09-13 Pavement subbase layer construction method based on precast beam field concrete panel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311185266.3A CN117026720A (en) 2023-09-13 2023-09-13 Pavement subbase layer construction method based on precast beam field concrete panel

Publications (1)

Publication Number Publication Date
CN117026720A true CN117026720A (en) 2023-11-10

Family

ID=88628379

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311185266.3A Pending CN117026720A (en) 2023-09-13 2023-09-13 Pavement subbase layer construction method based on precast beam field concrete panel

Country Status (1)

Country Link
CN (1) CN117026720A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104831598A (en) * 2015-04-21 2015-08-12 成军 Construction method for reconstruction of old cement pavement into asphalt concrete pavement
CN108193572A (en) * 2017-12-31 2018-06-22 中交第公路工程局有限公司 A kind of method recycled to precast beam precasting yard hardened layer
CN113089410A (en) * 2021-06-04 2021-07-09 四川公路桥梁建设集团有限公司 Asphalt pavement structure for permanent structure conversion of highway precast beam field pavement

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104831598A (en) * 2015-04-21 2015-08-12 成军 Construction method for reconstruction of old cement pavement into asphalt concrete pavement
CN108193572A (en) * 2017-12-31 2018-06-22 中交第公路工程局有限公司 A kind of method recycled to precast beam precasting yard hardened layer
CN113089410A (en) * 2021-06-04 2021-07-09 四川公路桥梁建设集团有限公司 Asphalt pavement structure for permanent structure conversion of highway precast beam field pavement

Similar Documents

Publication Publication Date Title
CN111764216A (en) A kind of prefabricated concrete road slab construction method and application
CN108193572A (en) A kind of method recycled to precast beam precasting yard hardened layer
CN111962350A (en) Geocell Reinforced Cement Concrete Pavement Structure and Surface Slab Thickness Calculation Method
CN207267954U (en) A Prefabricated Prestressed Construction Waste Recycled Aggregate Road
CN104452510B (en) Immediate construction method of rural road
CN114439267A (en) Road structure transformed from super-huge independent underground garage and construction method thereof
CN117758549A (en) Construction process of ballastless track of urban railway
KR100687211B1 (en) Road Pavement Using Precast Concrete Panels
CN205329462U (en) Structure is handled to cement concrete pavement seam of wrong platform of prevention inter -plate
CN215104290U (en) Prefabricated plate type ballastless track structure
CN113005908B (en) Installation method of overline overbridge
CN116876294B (en) A construction method for asphalt replaceable pavement for large aircraft testing
CN204662193U (en) Oblique prestressing force cement concrete-bituminous concrete composite pavement
CN117026720A (en) Pavement subbase layer construction method based on precast beam field concrete panel
CN216712592U (en) Novel roadbed applying foamed light soil
CN112982070A (en) Cement pavement slab staggering treatment structure and construction method
CN218466236U (en) A trackless transport roadway surface structure suitable for underground coal mines
CN113106790A (en) Prefabricated plate type ballastless track structure
CN112095394A (en) Composite pavement with excellent drainage function and construction method thereof
CN216999144U (en) Pavement structure suitable for uneven settlement disease of soft foundation road section bituminous pavement
CN218322165U (en) Steel construction combination beam type temporary pavement
CN116791447B (en) A construction method for a concrete replaceable pavement for large aircraft testing
CN221142520U (en) Cover plate auxiliary road culvert structure
CN116145739B (en) Vibration reduction structure of wood formwork of bottom plate without dismantling and construction method of vibration reduction structure
CN116837684B (en) A method for laying composite pavement structures

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination