CN116837925A - A closed reclamation method for large pit tailings reservoirs - Google Patents
A closed reclamation method for large pit tailings reservoirs Download PDFInfo
- Publication number
- CN116837925A CN116837925A CN202310827284.0A CN202310827284A CN116837925A CN 116837925 A CN116837925 A CN 116837925A CN 202310827284 A CN202310827284 A CN 202310827284A CN 116837925 A CN116837925 A CN 116837925A
- Authority
- CN
- China
- Prior art keywords
- slurry
- pit
- tailings
- slurry discharge
- pipeline
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02F—DREDGING; SOIL-SHIFTING
- E02F5/00—Dredgers or soil-shifting machines for special purposes
- E02F5/22—Dredgers or soil-shifting machines for special purposes for making embankments; for back-filling
- E02F5/223—Dredgers or soil-shifting machines for special purposes for making embankments; for back-filling for back-filling
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Mechanical Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Underground Or Underwater Handling Of Building Materials (AREA)
Abstract
本发明公开了一种大型坑式尾矿库闭库复垦方法,采用的排浆回填装置(6)由一根排浆管道、若干浮沉筒组合构成,若干浮沉筒绑扎于排浆管道的两端并平稳地悬浮在坑式尾矿库内的水面上,排浆管道的下面设有排浆孔。在浆体拌合池(1)内加入设定量的回填土、水、植物种子进行搅拌,再通过浆体气泵(10),经泥浆输送管道(3)将拌合浆料输送至排浆回填装置(6)的排浆管道(8)中,经过排浆孔(11)排出,从而对需要回填的坑式尾矿库之上部尾矿坑口的某分区进行覆土。本发明应用于大型坑式尾矿库闭库复垦,在确保大型坑式尾矿库闭库过程和最终复垦后满足安全和环保要求的同时,实现造价低、施工简易且龄期短的覆土。
The invention discloses a closed reclamation method for a large pit-type tailings reservoir. The adopted slurry discharge and backfill device (6) is composed of a slurry discharge pipe and a number of floating and sinking tubes. The several floating and sinking tubes are tied to both sides of the slurry discharge pipe. The end of the tailings tank is stably suspended on the water surface in the pit tailings reservoir, and there is a slurry discharge hole below the slurry discharge pipe. Add the set amount of backfill soil, water, and plant seeds into the slurry mixing tank (1) for mixing, and then transport the mixed slurry to the slurry discharge through the slurry air pump (10) and the mud transportation pipe (3) The slurry discharge pipe (8) of the backfill device (6) is discharged through the slurry discharge hole (11), so that a certain section of the upper tailings pit entrance of the pit-type tailings reservoir that needs to be backfilled is covered with soil. The invention is applied to the closed reclamation of large-scale pit-type tailings reservoirs. It ensures that the closure process and final reclamation of large-scale pit-type tailings reservoirs meet safety and environmental protection requirements while achieving low cost, simple construction and short lifespan. Cover with soil.
Description
技术领域Technical field
本发明属于坑式尾矿库闭库复垦工程技术领域,尤其是涉及以库容大于1000万m3的大型露天采坑作为尾矿库的闭库复垦方法。The invention belongs to the technical field of pit-type tailings reservoir closed reservoir reclamation engineering, and in particular relates to a closed reservoir reclamation method using a large open-pit mining pit with a storage capacity of more than 10 million m3 as a tailings reservoir.
背景技术Background technique
尾矿库是矿山的三大控制性工程之一,是矿山企业的重要生产设施,主要用于贮存金属、非金属矿山经过矿石选别后排出的尾矿或其他工业废渣的场所,是维持矿山正常生产的必要设施之一。已运行到设计最终标高或不再进行排尾作业的尾矿库都应进行闭库处理,闭库的内容包括尾矿库滩面的整治。滩面整治是为了防止闭库后的尾矿库滩面风化,产生扬尘造成环境污染,主要工程是在尾矿库滩面进行覆土,并且种植植被。The tailings pond is one of the three major control projects of the mine. It is an important production facility of the mining enterprise. It is mainly used to store tailings or other industrial waste residues discharged from metal and non-metal mines after ore separation. It is a place to maintain the mine. One of the necessary facilities for normal production. Tailings ponds that have reached the final designed elevation or are no longer undergoing tailing discharge operations should be closed. The content of the closure includes the regulation of the beach surface of the tailings pond. The beach surface improvement is to prevent the tailings pond beach surface from weathering after closure, causing dust and environmental pollution. The main project is to cover the tailings pond beach surface with soil and plant vegetation.
尾矿库类型主要包括山谷型尾矿库、傍山型尾矿库、平地型尾矿库和截河型尾矿库四种。通常情况下,这些尾矿库在实行闭库滩面治理过程中会首先将库内积水排出,待滩面具备足够承载力后,采用施工车辆将周边土壤运至库内进行滩面覆土绿化。近年来,为实现对露天矿山封场后的综合治理,考虑到露天矿坑具有较大库容优势,并且无需人工筑坝,具有造价低、施工简易且龄期短等优势,因此利用露天矿坑作为尾矿的排放场所,可解决土地资源匮乏、实际利用率低等难题。There are four main types of tailings ponds: valley-type tailings ponds, mountain-side tailings ponds, flat-land tailings ponds and river-cut tailings ponds. Normally, when these tailings reservoirs implement closed reservoir beach surface management, the accumulated water in the reservoir will first be drained. After the beach surface has sufficient bearing capacity, construction vehicles will be used to transport the surrounding soil to the reservoir for beach surface covering and greening. . In recent years, in order to achieve comprehensive management of open-pit mines after closure, considering that open-pit mines have the advantage of large storage capacity, do not require manual dam construction, have low cost, simple construction, and short life, open-pit mines are used as tail mines. Mine discharge sites can solve problems such as lack of land resources and low actual utilization rate.
露天矿坑作为尾矿排放场所,其巨大凹陷空间的结构特点决定了坑式尾矿库区别于一般尾矿库,主要体现于坑式尾矿库内均无干滩,尾矿水可完全覆盖全部尾矿,因此,在坑式尾矿库停止排放尾矿后,若采用常规尾矿库闭库复垦方式(即将上覆水完全抽出,并待滩面固结具有承载力后采用车辆运送周边土壤进行覆土绿化)进行坑式尾矿库闭库复垦,会面临如下问题:(1)闭库周期长:车辆运输覆土需滩面具备一定承载力,坑式尾矿库滩面常年被水淹没,若需达到滩面承载力满足车辆行驶要求需进行排水固结,将库内水全部抽出后待库内滩面裸露自然风晒,该过程需要很长的年限。(2)覆土不均匀:车辆库内运输覆土易产生挤土效应,造成滩面覆土不均,凹凸不平。(3)环境污染严重:传统尾矿库闭库方式采用车辆运送周边土壤,因其工程量较大,运输车辆完成闭库工作势必产生大量尾气,对大气造成严重不利影响。(4)处置方式的安全性较低:露天矿坑坑内尾砂排水固结周期较长,固结效果不能得以保障,部分区域固结效果较弱时采用车辆运输覆土易产生车辆损毁、设备倾覆等问题。(5)施工组织管理困难:坑式尾矿库采用车辆覆土闭库复垦所需人员、工程车辆较多,现场施工组织管理比较困难。基于此,本发明提出了一种大型坑式尾矿库闭库复垦方法。As a tailings discharge site, open-pit mines have structural characteristics of a huge concave space that determines that pit-type tailings ponds are different from general tailings ponds. This is mainly reflected in the fact that there is no dry beach in the pit-type tailings ponds, and the tailings water can completely cover all tailings. Therefore, after the pit-type tailings reservoir stops discharging tailings, if the conventional tailings reservoir closed reclamation method is adopted (that is, the overlying water is completely pumped out, and the surrounding soil is transported by vehicle after the beach surface is consolidated and has bearing capacity) Covering soil and greening) for closed reclamation of pit tailings reservoirs will face the following problems: (1) Long closure period: vehicle transportation of covering soil requires a certain bearing capacity of the beach surface, and the beach surface of pit tailings ponds is flooded all year round. If it is necessary to achieve the beach surface bearing capacity to meet vehicle driving requirements, drainage consolidation is required. After all the water in the reservoir is pumped out, the beach surface in the reservoir is exposed to the natural wind. This process takes a long time. (2) Uneven soil covering: Transportation of covering soil in a vehicle garage can easily cause a soil squeezing effect, resulting in uneven and uneven covering of soil on the beach surface. (3) Serious environmental pollution: The traditional tailings reservoir closure method uses vehicles to transport surrounding soil. Due to the large amount of work, transport vehicles will inevitably produce a large amount of exhaust gas to complete the closure work, causing serious adverse effects on the atmosphere. (4) The safety of the disposal method is low: the tailings drainage and consolidation period in the open-pit mine is long, and the consolidation effect cannot be guaranteed. When the consolidation effect in some areas is weak, the use of vehicles to transport covering soil may easily cause vehicle damage, equipment overturning, etc. question. (5) Difficulties in construction organization and management: The use of vehicles to cover soil-covered closed reservoirs for reclamation requires a large number of personnel and engineering vehicles, making on-site construction organization and management difficult. Based on this, the present invention proposes a closed reclamation method for a large pit-type tailings reservoir.
发明内容Contents of the invention
本发明的目的就是针对现有技术存在的闭库周期长、覆土不均匀、容易造成环境污染、存在安全问题、施工组织困难等缺陷,而提供一种满足安全和环保要求、造价较低、施工简易且龄期短的大型坑式尾矿库闭库复垦方法。The purpose of this invention is to provide a method that meets safety and environmental protection requirements, has low cost and is easy to construct in order to solve the shortcomings of the existing technology such as long storage period, uneven soil covering, easy environmental pollution, safety problems, and difficulty in construction organization. A simple and short-term closed reclamation method for large-scale pit tailings reservoirs.
为实现本发明的上述目的,本发明一种大型坑式尾矿库闭库复垦方法采用以下技术方案实施:In order to achieve the above objects of the present invention, a large-scale pit-type tailings reservoir closed reclamation method of the present invention adopts the following technical solutions to implement:
1)根据需要回填的坑式尾矿库之上部尾矿坑口的大小、形状,划分为若干分区:一分区、二分区、三分区.....;1) According to the size and shape of the upper tailings pit mouth of the pit-type tailings reservoir that needs to be backfilled, it is divided into several zones: first zone, second zone, third zone...;
2)根据坑式尾矿库周边地理环境、交通运输、线路架设及距离尾矿坑远近,选择合适位置修建浆体拌合池、浆体堆放槽,浆体拌合池、和浆体堆放槽之间用管道连接,浆体堆放槽内配备有输送浆体的浆体气泵;浆体气泵的出口与铺向坑式尾矿库之上部尾矿坑口某分区的泥浆输送管道连接;2) Based on the geographical environment, transportation, line erection and distance from the tailings pit around the pit-type tailings reservoir, select a suitable location to build a slurry mixing tank, a slurry stacking tank, a slurry mixing tank, and a slurry stacking tank. The slurry stacking tank is equipped with a slurry air pump for transporting slurry; the outlet of the slurry air pump is connected to a mud transportation pipeline that is laid in a certain section of the upper tailings pit entrance above the pit-type tailings reservoir;
3)在需要回填的坑式尾矿库之上部尾矿坑口的某分区水面上横向布设排浆回填装置;3) Arrange a slurry discharge and backfill device horizontally on the water surface of a certain section of the upper tailings pit entrance of the pit-type tailings reservoir that needs to be backfilled;
所述的排浆回填装置由一根排浆管道、若干浮沉筒组合构成,若干浮沉筒绑扎于排浆管道的两端并平稳地悬浮在坑式尾矿库内的水面上;排浆管道的一端与泥浆输送管道的出口连接,排浆管道的另一端为盲管,排浆管道的下面设有排浆孔;The described slurry discharge and backfill device is composed of a slurry discharge pipe and a number of floating and sinking cylinders. The several floating and sinking cylinders are tied to both ends of the slurry discharging pipe and are smoothly suspended on the water surface in the pit tailings reservoir; the slurry discharging pipe is One end is connected to the outlet of the mud conveying pipe, the other end of the slurry discharge pipe is a blind pipe, and a slurry discharge hole is provided below the slurry discharge pipe;
4)在坑式尾矿库之上部尾矿坑口的侧边对应设有控制排浆回填装置移动的卷扬机/鼓风设备或远程控制器;卷扬机/鼓风设备安装有钢丝链索,每条钢丝链索与对应布设在排浆管道一端的浮沉筒可拆卸组装连接;4) On the side of the upper tailings pit entrance of the pit-type tailings reservoir, there is a winch/blower equipment or remote controller that controls the movement of the slurry discharge and backfill device; the winch/blower equipment is equipped with a steel wire chain, and each steel wire The chain cable is removably assembled and connected to the corresponding floating and sinking tube arranged at one end of the slurry discharge pipe;
当采用远程控制器时,在排浆回填装置上对应设置智能驱动机构,通过远程控制器控制排浆回填装置在坑式尾矿库内的水面上移动。When a remote controller is used, an intelligent driving mechanism is set on the slurry discharge and backfill device, and the remote controller controls the slurry discharge and backfill device to move on the water surface in the pit tailings reservoir.
5)在浆体拌合池内加入设定量的回填土、水、植物种子进行搅拌,制备出拌合浆料,再通过浆体堆放槽内配备的输送浆体的浆体气泵,经泥浆输送管道将拌合浆料输送至排浆回填装置的排浆管道中,经过排浆孔排出,卷扬机/鼓风设备控制排浆回填装置在某分区水面上反复匀速移动,从而对需要回填的坑式尾矿库之上部尾矿坑口的某分区进行原位覆土;5) Add a set amount of backfill soil, water, and plant seeds into the slurry mixing tank and stir to prepare a mixed slurry, which is then transported by the slurry through the slurry air pump equipped in the slurry stacking tank. The pipeline transports the mixed slurry to the slurry discharge pipe of the slurry discharge and backfill device, and discharges it through the slurry discharge hole. The winch/blower equipment controls the slurry discharge and backfill device to repeatedly move at a constant speed on the water surface of a certain zone, thereby filling the pits that need to be backfilled. A certain section of the upper tailings pit entrance above the tailings pond will be covered with soil in situ;
6)当某分区的覆土厚度满足复垦要求时,再将排浆回填装置移到下一个分区进行覆土,直至所有分区完成覆土。6) When the covering soil thickness of a certain partition meets the reclamation requirements, move the slurry discharge and backfill device to the next partition to cover the soil until all partitions are completed.
优选的,所述的泥浆输送管道与排浆管道通过插拔式一字二通接头固定连接。Preferably, the mud transport pipeline and the slurry discharge pipeline are fixedly connected through a plug-in two-way joint.
优选的,位于排浆管道两端的浮沉筒数量相同,并且位置相对,使得排浆管道平稳地悬浮在坑式尾矿库水面上。Preferably, the number of floats and sinks located at both ends of the slurry discharge pipe is the same and the positions are opposite, so that the slurry discharge pipe is smoothly suspended on the water surface of the pit tailings reservoir.
优选的,排浆孔的孔径为0.8cm-1.2cm,所述排浆孔等距间隔依次排列在排浆管道的下面。Preferably, the diameter of the slurry discharge holes is 0.8cm-1.2cm, and the slurry discharge holes are arranged at equidistant intervals below the slurry discharge pipe.
优选的,所述的拌合浆料的质量浓度为60-70%。Preferably, the mass concentration of the mixing slurry is 60-70%.
优选的,所述的覆土厚度为20cm-50cm。Preferably, the thickness of the covering soil is 20cm-50cm.
优选的,每一分区的宽度为6m-15m。Preferably, the width of each partition is 6m-15m.
优选的,所述浮沉筒采用高密度聚乙烯或聚酯合成材料制成。Preferably, the floating tube is made of high-density polyethylene or polyester synthetic material.
当排浆管道长度过大时,所述的排浆管道是由若干根长度较短的管道通过L型二通螺纹接头连接成一根整体。When the length of the slurry discharge pipe is too long, the slurry discharge pipe is composed of several shorter pipes connected into one whole body through an L-shaped two-way threaded joint.
进一步地,所述的覆土厚度为20cm-30cm;所述的拌合浆料的质量浓度为65-70%,其中植物种子在拌合浆料中的质量占比为1-5%;每一分区的宽度为6m-10m。Further, the thickness of the covering soil is 20cm-30cm; the mass concentration of the mixing slurry is 65-70%, in which the mass proportion of plant seeds in the mixing slurry is 1-5%; each The width of the partition is 6m-10m.
本发明一种大型坑式尾矿库闭库复垦方法采用以上技术方案后,具有下列积极效果:The closed reclamation method of a large pit-type tailings reservoir of the present invention has the following positive effects after adopting the above technical solution:
(1)本发明研制的排浆回填装置利用水的浮力使得排浆管道浮于坑式尾矿库水面上,采用卷扬机/鼓风设备辅助钢丝链索收放,实现控制排浆回填装置在水面上反复匀速移动,通过泥浆输送管道将拌合胶结浆体输送至排浆管道中,并通过排浆管道内设有的若干排浆孔排出,进行覆土,有效避免了现有技术中车辆覆土过程产生的挤土效应,覆土均匀,滩面平整,覆土效果较好。(1) The slurry discharge and backfill device developed by the present invention uses the buoyancy of water to make the slurry discharge pipe float on the water surface of the pit tailings reservoir, and uses a winch/blower equipment to assist the retraction and release of the steel wire chain to achieve control of the slurry discharge and backfill device on the water surface. It moves at a constant speed repeatedly, and the mixed cementing slurry is transported to the slurry discharge pipe through the slurry conveying pipe, and is discharged through a number of slurry discharge holes provided in the slurry discharge pipe for soil covering, which effectively avoids the vehicle soil covering process in the existing technology. The resulting soil squeezing effect results in even soil covering, smooth beach surface, and better soil covering effect.
(2)本发明采用原位覆土方式直接在水面上对尾矿坑滩面进行覆土,省去了前期尾矿排水固结时间,极大地缩短了闭库复垦作业龄期,降低了大量人力及车辆的投入,具有造价成本低,项目工程组织管理简单等优势。(2) The present invention uses the in-situ soil covering method to cover the tailings pit beach surface with soil directly on the water surface, which saves the early tailings drainage and consolidation time, greatly shortens the period of closed reservoir reclamation operation, and reduces a lot of manpower and time. The investment in vehicles has the advantages of low cost and simple project organization and management.
(3)本发明通过卷扬机/鼓风设备、钢丝链索带动排浆回填装置进行覆土,闭库复垦全过程更加绿色、低碳,该过程更加环保。(3) The present invention drives the slurry discharge and backfilling device through the winch/blowing equipment and steel wire chain cables to cover the soil. The whole process of closed reservoir reclamation is greener, lower-carbon, and more environmentally friendly.
(4)本发明省去了运输车辆在坑内覆土的过程,有效避免坑内车辆损毁、设备倾覆等事故发生。(4) The present invention eliminates the need for transportation vehicles to cover the pit with soil, and effectively avoids accidents such as vehicle damage and equipment overturning in the pit.
(5)本发明全过程在湿式环境下进行,有效避免了扬尘的产生,保护环境;本发明应用于大型坑式尾矿库闭库复垦,在确保大型坑式尾矿库闭库过程和最终复垦后满足安全和环保要求的同时,实现造价低、施工简易且龄期短的覆土。(5) The entire process of the present invention is carried out in a wet environment, effectively avoiding the generation of dust and protecting the environment; the present invention is applied to closed reclamation of large-scale pit-type tailings reservoirs, ensuring the closure process of large-scale pit-type tailings reservoirs and After the final reclamation, it not only meets safety and environmental protection requirements, but also achieves low-cost, simple construction and short-term covering soil.
附图说明Description of the drawings
图1为本发明一种大型坑式尾矿库闭库复垦方法的设计的系统布置结构示意图;Figure 1 is a schematic diagram of the system layout and structure of the design of a large-scale pit-type tailings reservoir closed reclamation method according to the present invention;
图2为本发明方法采用的排浆回填装置的结构示意图;Figure 2 is a schematic structural diagram of the slurry discharge and backfill device used in the method of the present invention;
图3为图2中A-A的剖视图;Figure 3 is a cross-sectional view of A-A in Figure 2;
图4为本发明方法采用的插拔式一字二通接头的的结构示意图。Figure 4 is a schematic structural diagram of a plug-in two-way connector used in the method of the present invention.
附图标记为:1-浆体拌合池;2-浆体堆放槽;3-泥浆输送管道;4-钢丝链索;5-卷扬机/鼓风设备;6-排浆回填装置;7-浮沉筒;8-排浆管道;9-插拔式一字二通接头;10-浆体气泵;11-排浆孔;12-L型二通螺纹接头。The reference numbers are: 1-slurry mixing tank; 2-slurry stacking tank; 3-slurry transportation pipeline; 4-wire chain; 5-winch/blast equipment; 6-slurry discharge and backfill device; 7-floating and sinking cylinder; 8-slurry discharge pipe; 9-plug-in one-way two-way joint; 10-slurry air pump; 11-slurry discharge hole; 12-L-type two-way threaded joint.
具体实施方式Detailed ways
为进一步描述本发明,下面结合附图对本发明一种大型坑式尾矿库闭库复垦方法作进一步详细描述。显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。In order to further describe the present invention, a closed reclamation method for a large pit-type tailings reservoir of the present invention will be described in further detail below with reference to the accompanying drawings. Obviously, the described embodiments are only some of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts fall within the scope of protection of the present invention.
由图1所示的本发明一种大型坑式尾矿库闭库复垦方法的设计的系统布置结构示意图并结合图2、图3看出,本发明一种大型坑式尾矿库闭库复垦方法,采用以下技术方案实施:From the schematic system layout structure diagram of the design of a large-scale pit-type tailings closed storage reclamation method of the present invention shown in Figure 1 and combined with Figures 2 and 3, it can be seen that a large-scale pit-type tailings closed storage tank of the present invention Reclamation methods are implemented using the following technical solutions:
1)根据需要回填的坑式尾矿库之上部尾矿坑口的大小、形状,划分为若干分区:一分区、二分区、三分区.....,每一分区的宽度为6m-10m。1) According to the size and shape of the upper tailings pit mouth of the pit-type tailings reservoir that needs to be backfilled, it is divided into several zones: first zone, second zone, third zone..., the width of each zone is 6m-10m.
2)根据坑式尾矿库周边地理环境、交通运输、线路架设及距离尾矿坑远近,选择合适位置修建浆体拌合池1和浆体堆放槽2,浆体拌合池1和浆体堆放槽2用管道连接,浆体堆放槽2内配备有输送浆体的浆体气泵10;浆体气泵10的出口与铺向坑式尾矿库之上部尾矿坑口某分区的泥浆输送管道3连接。2) Based on the geographical environment, transportation, line erection and distance from the tailings pit around the pit tailings reservoir, select the appropriate location to build the slurry mixing tank 1 and slurry stacking tank 2, slurry mixing tank 1 and slurry stacking tank Tank 2 is connected with a pipeline, and the slurry stacking tank 2 is equipped with a slurry air pump 10 for transporting slurry; the outlet of the slurry air pump 10 is connected to the mud transportation pipeline 3 that is laid in a certain section of the upper tailings pit entrance of the pit-type tailings reservoir. .
3)在需要回填的坑式尾矿库之上部尾矿坑口的某分区水面上横向布设排浆回填装置6。3) Arrange the slurry discharge and backfill device 6 horizontally on the water surface of a certain section of the upper tailings pit entrance of the pit-type tailings reservoir that needs to be backfilled.
所述的排浆回填装置6由一根排浆管道8、若干浮沉筒7组合构成,浮沉筒7采用HMWHDPE(高分子聚乙烯)等环保材料制成,有利于提高沉降筒7的使用寿命,并减少环境污染。若干浮沉筒7绑扎于排浆管道8的两端,若干沉降筒7通过钢筋骨架与排浆管道8固接,位于排浆管道8两端的浮沉筒7数量相同,并且位置相对,使得排浆管道8利用水的浮力平稳地悬浮在坑式尾矿库水面上。排浆管道8的一端与泥浆输送管道3的出口通过插拔式一字二通接头9固定连接,排浆管道8的另一端为盲管,排浆管道8的下面设有距间隔依次排列排浆孔11,使得拌合浆料均匀排出,提高覆土均匀性;排浆孔11的孔径为0.8cm-1.2cm。The described slurry discharge and backfill device 6 is composed of a slurry discharge pipe 8 and several floating and sinking tubes 7. The floating and sinking tubes 7 are made of environmentally friendly materials such as HMWHDPE (high molecular polyethylene), which is beneficial to increasing the service life of the settling tubes 7. and reduce environmental pollution. A number of floating and sinking drums 7 are tied to both ends of the slurry discharge pipe 8. Several settling drums 7 are fixedly connected to the slurry discharge pipe 8 through steel frames. The number of floating and sinking drums 7 located at both ends of the slurry discharge pipe 8 is the same and their positions are opposite, so that the slurry discharge pipes 8. Use the buoyancy of water to float smoothly on the water surface of the pit tailings reservoir. One end of the slurry discharge pipe 8 is fixedly connected to the outlet of the mud conveying pipe 3 through a plug-in one-way two-way joint 9. The other end of the slurry discharge pipe 8 is a blind pipe. The bottom of the slurry discharge pipe 8 is arranged at intervals and arranged in sequence. The slurry hole 11 enables the mixing slurry to be discharged evenly and improves the uniformity of the covering soil; the diameter of the slurry discharge hole 11 is 0.8cm-1.2cm.
4)在坑式尾矿库之上部尾矿坑口的侧边对应设有控制排浆回填装置6移动的卷扬机/鼓风设备5或远程控制器;卷扬机/鼓风设备5安装有钢丝链索4,每条钢丝链索4与对应布设在排浆管道8一端的浮沉筒7组装连接;如此设置,通过位于两侧的四个卷扬机/鼓风设备5辅助钢丝链索4收放,实现控制排浆回填装置在水面上反复匀速移动。钢丝链索4为金属制品,质量较轻,便于与卷扬机/鼓风设备5配合,且强度较高,可有效带动排浆回填装置移动,可提高覆土效率。4) On the side of the upper tailings pit mouth of the pit-type tailings reservoir, there is correspondingly provided a winch/blower equipment 5 or a remote controller that controls the movement of the slurry discharge and backfill device 6; the winch/blower equipment 5 is equipped with a steel wire chain 4 , each steel wire chain cable 4 is assembled and connected with the corresponding floating drum 7 arranged at one end of the slurry discharge pipe 8; with this arrangement, the four winches/blower equipment 5 located on both sides assist in the retraction and unfolding of the steel wire chain cable 4 to achieve controlled discharge. The slurry backfill device moves repeatedly and uniformly on the water surface. The steel wire chain rope 4 is made of metal, is light in weight, is easy to cooperate with the winch/blower equipment 5, and has high strength, which can effectively drive the movement of the slurry discharge and backfill device and improve the soil covering efficiency.
5)在浆体拌合池1内加入设定量的回填土、水、植物种子进行搅拌,制备出拌合浆料,再通过浆体堆放槽2内配备的输送浆体的浆体气泵10,经泥浆输送管道3将拌合浆料输送至排浆回填装置6的排浆管道8中,经过排浆孔11排出,从而对需要回填的坑式尾矿库之上部尾矿坑口的某分区进行覆土。覆土厚度为20cm-30cm,拌合浆料的质量浓度控制66-69%。5) Add a set amount of backfill soil, water, and plant seeds into the slurry mixing tank 1 and stir to prepare a mixed slurry, which is then transported through the slurry air pump 10 equipped in the slurry stacking tank 2 , the mixed slurry is transported to the slurry discharge pipe 8 of the slurry discharge and backfill device 6 through the mud transport pipe 3, and is discharged through the slurry discharge hole 11, thereby filling a certain section of the upper tailings pit entrance of the pit-type tailings reservoir that needs to be backfilled. Cover with soil. The thickness of the covering soil is 20cm-30cm, and the mass concentration of the mixing slurry is controlled at 66-69%.
6)当某分区的覆土厚度满足复垦要求时,再将排浆回填装置(6)移到下一个分区进行覆土,直至所有分区完成覆土。6) When the thickness of the covering soil in a certain partition meets the reclamation requirements, move the slurry discharge and backfill device (6) to the next partition to cover the soil until all partitions are completed.
由图4所示本发明方法采用的插拔式一字二通接头的的结构示意图并结合图1看出,当排浆管道8长度过大时,所述的排浆管道8是由若干根长度较短的管道通过L型二通螺纹接头12连接成一根整体。From the schematic structural diagram of the plug-in two-way joint used in the method of the present invention shown in Figure 4 and combined with Figure 1, it can be seen that when the length of the slurry discharge pipe 8 is too large, the slurry discharge pipe 8 is composed of several The shorter pipes are connected into a whole body through the L-shaped two-way threaded joint 12.
本发明方法闭库复垦全过程更加绿色、低碳,该过程更加环保,有效避免了现有技术中车辆覆土过程产生的挤土效应,覆土均匀,滩面平整,覆土效果更好;本发明采用原位覆土方式直接在水面上对尾矿坑滩面进行覆土,省去了前期尾矿排水固结时间,极大缩短了闭库复垦作业龄期,减少了大量人力及车辆的资金投入,具有造价成本低,项目工程组织管理简单等优势;省去了运输车辆在坑内覆土的过程,有效避免坑内车辆损毁、设备倾覆等事故发生;本发明全过程在湿式环境下进行,有效避免了扬尘的产生,保护环境;本发明应用于大型坑式尾矿库闭库复垦,在确保大型坑式尾矿库闭库过程和最终复垦后满足安全和环保要求的同时,实现造价低、施工简易且龄期短的覆土。The whole closed reservoir reclamation process of the method of the present invention is greener, lower-carbon, more environmentally friendly, and effectively avoids the soil squeezing effect caused by the vehicle soil covering process in the prior art. The soil covering is even, the beach surface is flat, and the soil covering effect is better; The in-situ soil covering method is used to cover the tailings pit beach surface with soil directly on the water surface, which saves the early tailings drainage and consolidation time, greatly shortens the period of closed reservoir reclamation operations, and reduces a large amount of manpower and vehicle capital investment. It has the advantages of low cost and simple project organization and management; it eliminates the need for transportation vehicles to cover the pit with soil, effectively avoiding accidents such as vehicle damage and equipment overturning in the pit; the entire process of the present invention is carried out in a wet environment, effectively avoiding dust production and environmental protection; the present invention is applied to the closed reclamation of large-scale pit-type tailings reservoirs to ensure that the closure process and final reclamation of large-scale pit-type tailings reservoirs meet safety and environmental protection requirements while achieving low cost and low construction costs. Simple and short-term soil covering.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310827284.0A CN116837925A (en) | 2023-07-07 | 2023-07-07 | A closed reclamation method for large pit tailings reservoirs |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310827284.0A CN116837925A (en) | 2023-07-07 | 2023-07-07 | A closed reclamation method for large pit tailings reservoirs |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116837925A true CN116837925A (en) | 2023-10-03 |
Family
ID=88168587
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310827284.0A Pending CN116837925A (en) | 2023-07-07 | 2023-07-07 | A closed reclamation method for large pit tailings reservoirs |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116837925A (en) |
Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2611075C1 (en) * | 2015-12-29 | 2017-02-21 | Федеральное государственное бюджетное образовательное учреждение высшего образования "Северо-Осетинский государственный университет имени Коста Левановича Хетагурова" (СОГУ) | Method of tailing dump in mountain trenches recultivation |
| CN217608300U (en) * | 2022-06-09 | 2022-10-21 | 中钢集团马鞍山矿山研究总院股份有限公司 | Middle-size and small-size hole formula tailing storehouse closed warehouse reclamation device |
-
2023
- 2023-07-07 CN CN202310827284.0A patent/CN116837925A/en active Pending
Patent Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2611075C1 (en) * | 2015-12-29 | 2017-02-21 | Федеральное государственное бюджетное образовательное учреждение высшего образования "Северо-Осетинский государственный университет имени Коста Левановича Хетагурова" (СОГУ) | Method of tailing dump in mountain trenches recultivation |
| CN217608300U (en) * | 2022-06-09 | 2022-10-21 | 中钢集团马鞍山矿山研究总院股份有限公司 | Middle-size and small-size hole formula tailing storehouse closed warehouse reclamation device |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US12077459B2 (en) | Device and method for mud solidification based on electro-osmosis well points cooperating with well-points dewatering | |
| CN110056390B (en) | Disposal method of full tailings consolidation disposal system for underground abandoned roadway | |
| CN220306960U (en) | Pumped storage-gravity energy storage-photovoltaic-wind power system utilizing waste coal mine | |
| CN209323523U (en) | A deep shaft concrete pouring device | |
| CN217470721U (en) | Device for closed-warehouse reclamation of large pit-type tailing warehouse | |
| CN217608300U (en) | Middle-size and small-size hole formula tailing storehouse closed warehouse reclamation device | |
| CN103232149B (en) | An in-situ rapid dehydration system for sediment in an environmentally friendly dredging yard | |
| CN101570822B (en) | Hydraulic method for constructing mine pile | |
| CN105780809B (en) | A kind of multi-functional sinking equipment and its construction method | |
| CN116837925A (en) | A closed reclamation method for large pit tailings reservoirs | |
| CN114846964B (en) | Method for reclamation of closed tailings pond of large pit type | |
| CN115637989A (en) | Tunnel inclined shaft herringbone hole entering construction method | |
| CN110777813A (en) | Modular cyclone grading dam-building system and implementation method for tailings pond | |
| CN109931075A (en) | The hole arragement construction in steep inclined shaft tunnel | |
| CN220815739U (en) | Slurry backfilling system for closed-reservoir reclamation of large pit type tailing pond | |
| CN109944288B (en) | Underground coal mine sump dredging robot and dredging method | |
| CN114830882B (en) | Middle and small pit type tailing pond closed-pond reclamation device and method | |
| CN110529118B (en) | Method for treating abandoned open-pit basin of mine by long-distance pipeline conveying mortar | |
| CN210033451U (en) | Layout structure of the tunnel entrance of steep slope inclined shaft tunnel | |
| CN107419800A (en) | Deep layer tunnel internal desilting system | |
| CN112012788A (en) | Tailing filling system based on mine slope and steep slope terrain and construction method | |
| CN211735347U (en) | Mud solidification treatment device for electroosmosis well point and well point dewatering | |
| CN209838476U (en) | Efficient upward layered filling dehydration system | |
| CN223203059U (en) | Mine ecological restoration filling body percolate effective collection guide and drainage system | |
| CN116586424A (en) | Ecological restoration method for small pit type storage yard |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |