CN116727814A - Welding process for bridge steel Q370qE ultra-thick plate - Google Patents
Welding process for bridge steel Q370qE ultra-thick plate Download PDFInfo
- Publication number
- CN116727814A CN116727814A CN202310744308.6A CN202310744308A CN116727814A CN 116727814 A CN116727814 A CN 116727814A CN 202310744308 A CN202310744308 A CN 202310744308A CN 116727814 A CN116727814 A CN 116727814A
- Authority
- CN
- China
- Prior art keywords
- welding
- q370qe
- weld
- steel
- arc
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K9/00—Arc welding or cutting
- B23K9/18—Submerged-arc welding
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K9/00—Arc welding or cutting
- B23K9/235—Preliminary treatment
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K9/00—Arc welding or cutting
- B23K9/32—Accessories
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Plasma & Fusion (AREA)
- Mechanical Engineering (AREA)
- Arc Welding In General (AREA)
Abstract
Description
技术领域Technical field
本发明涉及桥梁建筑技术领域,尤其涉及一种桥梁钢Q370qE超厚板焊接工艺。The invention relates to the technical field of bridge construction, and in particular to a welding process of bridge steel Q370qE ultra-thick plates.
背景技术Background technique
目前国内所采用的桥梁钢板厚最厚为120mm,板厚150mm的Q370qE桥梁钢板为首次使用;本工艺考虑到坡口形式、预热温度、定位焊、焊接方法、变形控制等措施,进行各种焊接试验、力学试验,确定焊接步骤与焊接工艺参数。At present, the thickest bridge steel plate used in China is 120mm, and the Q370qE bridge steel plate with a plate thickness of 150mm is used for the first time; this process takes into account the groove form, preheating temperature, positioning welding, welding method, deformation control and other measures to carry out various Welding test, mechanical test, determine welding steps and welding process parameters.
发明内容Contents of the invention
本发明要解决的技术问题是提供一种桥梁钢Q370qE超厚板焊接工艺,能够解决150mm的Q370qE钢板的焊接问题。The technical problem to be solved by this invention is to provide a bridge steel Q370qE ultra-thick plate welding process that can solve the welding problem of 150mm Q370qE steel plate.
为解决上述技术问题,本发明的技术方案为:一种桥梁钢Q370qE超厚板焊接工艺,该焊接工艺用于板厚150mm的Q370qE钢对接;其创新点在于:具体焊接工艺如下:In order to solve the above technical problems, the technical solution of the present invention is: a bridge steel Q370qE ultra-thick plate welding process, which is used for butt jointing of Q370qE steel with a plate thickness of 150mm; its innovation point is: the specific welding process is as follows:
将150mm的Q370qE钢的坡口采用铣床进行加工,焊接前对坡口处进行清理,并预加热到120-150℃;Use a milling machine to process the groove of 150mm Q370qE steel. Clean the groove before welding and preheat it to 120-150℃;
150mm的Q370qE钢定位焊与打底焊道异侧设置;The 150mm Q370qE steel positioning welding and bottoming welding beads are set on opposite sides;
150mm的Q370qE钢仰位焊采用焊条电弧焊;150mm Q370qE steel overhead welding uses electrode arc welding;
150mm的Q370qE钢正式焊缝采用气体保护焊与埋弧焊相结合的方式;The formal weld of 150mm Q370qE steel adopts a combination of gas shielded welding and submerged arc welding;
150mm的Q370qE钢焊后进行后热处理,将焊缝两侧进行加热至200-250℃,后热结束后将石棉铺在焊缝上,进行保温缓冷,焊接完成48h后进行超声波探伤。150mm Q370qE steel is subjected to post-heat treatment after welding. Both sides of the weld are heated to 200-250°C. After post-heating, asbestos is spread on the weld for thermal insulation and slow cooling. Ultrasonic flaw detection is performed 48 hours after the welding is completed.
进一步的,所述对接焊缝采用双面U型坡口,坡口角度30度,钝边3mm,根部圆弧段半径7mm。Furthermore, the butt weld adopts a double-sided U-shaped groove with a groove angle of 30 degrees, a blunt edge of 3mm, and a radius of the root arc segment of 7mm.
进一步的,预加热前将焊缝两侧20-30mm范围内的铁锈、油污、预涂底漆打磨干净,露出金属光泽。Furthermore, before preheating, polish away the rust, oil stains, and pre-coated primer within 20-30mm on both sides of the weld to reveal the metallic luster.
进一步的,所述预加热采用电加热方式,加热范围为焊缝两侧各100mm以及焊缝对称边100mm范围,保证应力均衡,防止定位焊开裂。Furthermore, the preheating adopts electric heating, and the heating range is 100mm on both sides of the weld and 100mm on the symmetrical side of the weld to ensure stress balance and prevent tack welding from cracking.
进一步的,在打底焊道背面进行定位焊接,采用J507Q焊条焊接,消除定位焊对打底焊道的影响,定位焊侧焊接前进行碳弧气刨,清除定位焊缝与未熔合区域。Further, tack welding is performed on the back side of the base weld bead, using J507Q electrode welding to eliminate the impact of tack welding on the base weld bead. Carbon arc gouging is performed before welding on the tack weld side to remove the tack weld seam and unfused area.
进一步的,打底焊道采用实心焊丝ER50-6平位焊接,打底焊道焊接一道,焊缝厚度控制在3-4mm;焊接电流为220-260A,电弧电压为26-30V。Furthermore, solid wire ER50-6 is used for flat position welding for the bottom welding pass, and the thickness of the welding seam is controlled at 3-4mm; the welding current is 220-260A, and the arc voltage is 26-30V.
进一步的,填充焊缝采用多层多道焊,焊接材料为埋弧焊丝H08Mn2E加埋弧焊剂SJ101q,焊接三层后翻身,进行碳弧气刨,清除未熔合区域,打磨匀顺后采用埋弧自动焊焊接,焊缝两面交替焊接,每焊接四层进行一次翻身,焊接时保证连续施焊,不应断弧;焊缝厚度控制在4-5mm,层间温度控制在80-200℃,焊接电流为600-700A,电弧电压为28-32V,焊接速度为20-26m/h。Furthermore, multi-layer and multi-pass welding is used to fill the weld. The welding material is submerged arc welding wire H08Mn2E plus submerged arc flux SJ101q. After welding three layers, turn it over and perform carbon arc gouging to remove the unfused area. After polishing it evenly, submerged arc is used. Automatic welding, both sides of the weld are alternately welded, turning over every four layers of welding, ensuring continuous welding, and the arc should not be interrupted; the thickness of the weld is controlled at 4-5mm, and the inter-layer temperature is controlled at 80-200°C. The current is 600-700A, the arc voltage is 28-32V, and the welding speed is 20-26m/h.
本发明的优点在于:The advantages of the present invention are:
1)本发明中定位焊采用J507Q焊条仰位焊接,与打底焊道异侧;打底焊道采用实心焊丝ER50-6焊接,预热温度80-120℃,焊接电流为220~260A,电弧电压为26-30V;填充层多层多道焊,采用埋弧焊丝H08Mn2E加SJ101q焊剂焊接,层间温度控制在80-200℃,焊接电流为600-700A,电弧电压为28-32V,焊接速度为20-26m/h;本发明进行各种焊接试验、机械性能试验,确定焊接步骤与焊接工艺参数,保证焊缝质量。1) In the present invention, the positioning welding uses J507Q electrode in the upward position, on the opposite side from the bottom welding bead; the bottom welding bead is welded with solid wire ER50-6, the preheating temperature is 80-120°C, the welding current is 220~260A, and the arc The voltage is 26-30V; the filling layer is multi-layer and multi-pass welding, using submerged arc welding wire H08Mn2E and SJ101q flux welding, the interlayer temperature is controlled at 80-200°C, the welding current is 600-700A, the arc voltage is 28-32V, the welding speed is 20-26m/h; the present invention conducts various welding tests and mechanical performance tests to determine the welding steps and welding process parameters to ensure the quality of the weld.
附图说明Description of drawings
下面结合附图和具体实施方式对本发明作进一步详细的说明。The present invention will be described in further detail below with reference to the accompanying drawings and specific embodiments.
图1为本发明的一种桥梁钢Q370qE超厚板焊接工艺的板材对接坡口形式图。Figure 1 is a diagram of the plate butt groove form of the bridge steel Q370qE ultra-thick plate welding process of the present invention.
图2为本发明的一种桥梁钢Q370qE超厚板焊接工艺的焊前预热示意图。Figure 2 is a schematic diagram of the pre-welding preheating process of the bridge steel Q370qE ultra-thick plate welding process of the present invention.
图3为本发明的一种桥梁钢Q370qE超厚板焊接工艺的定位焊示意图。Figure 3 is a schematic diagram of the positioning welding process of the bridge steel Q370qE ultra-thick plate welding process of the present invention.
图4为本发明的一种桥梁钢Q370qE超厚板焊接工艺的板材对接的焊缝布置图。Figure 4 is a welding seam layout diagram of the plate butt jointing process of the bridge steel Q370qE ultra-thick plate welding process of the present invention.
实施方式Implementation
为使本发明实施例的目的、技术方案和优点更加清楚,下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。通常在此处附图中描述和示出的本发明实施例的组件可以以各种不同的配置来布置和设计。In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments These are some embodiments of the present invention, rather than all embodiments. The components of the embodiments of the invention generally described and illustrated in the figures herein may be arranged and designed in a variety of different configurations.
因此,以下对在附图中提供的本发明的实施例的详细描述并非旨在限制要求保护的本发明的范围,而是仅仅表示本发明的选定实施例。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。Therefore, the following detailed description of the embodiments of the invention provided in the appended drawings is not intended to limit the scope of the claimed invention, but rather to represent selected embodiments of the invention. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without making creative efforts fall within the scope of protection of the present invention.
如图1至图4所示的一种桥梁钢Q370qE超厚板焊接工艺,该焊接工艺用于板厚150mm的Q370qE钢对接;具体焊接工艺如下:As shown in Figures 1 to 4, a bridge steel Q370qE ultra-thick plate welding process is used for the butt jointing of Q370qE steel with a plate thickness of 150mm; the specific welding process is as follows:
将150mm的Q370qE钢的坡口采用铣床进行加工,对接焊缝采用双面U型坡口,坡口角度30度,钝边3mm,根部圆弧段半径7mm;预加热前将焊缝两侧20-30mm范围内的铁锈、油污、预涂底漆打磨干净,露出金属光泽;预加热采用电加热方式,加热范围为焊缝两侧各100mm以及焊缝对称边100mm范围,保证应力均衡,防止定位焊开裂;并预加热到120-150℃。The groove of 150mm Q370qE steel is processed with a milling machine. The butt weld adopts a double-sided U-shaped groove with a groove angle of 30 degrees, a blunt edge of 3mm, and a radius of the root arc segment of 7mm. Before preheating, 20 - Rust, oil stains, and pre-coated primer within a 30mm range are polished to expose the metallic luster; preheating uses electric heating, and the heating range is 100mm on both sides of the weld and 100mm on the symmetrical side of the weld to ensure stress balance and prevent positioning Weld cracking; and preheat to 120-150℃.
150mm的Q370qE钢定位焊与打底焊道异侧设置;在打底焊道背面进行定位焊接,采用J507Q焊条焊接,消除定位焊对打底焊道的影响,定位焊侧焊接前进行碳弧气刨,清除定位焊缝与未熔合区域;打底焊道采用实心焊丝ER50-6平位焊接,打底焊道焊接一道,焊缝厚度控制在3-4mm;焊接电流为220-260A,电弧电压为26-30V。The 150mm Q370qE steel tack welding and the primer bead are set on opposite sides; tack welding is performed on the back of the primer bead, and J507Q electrode is used for welding to eliminate the impact of tack welding on the primer bead. Carbon arc gas is used before welding on the tack weld side. Plane and remove the positioning weld and unfused area; use solid wire ER50-6 for flat position welding for the bottom weld, and weld one bottom bead with the weld thickness controlled at 3-4mm; the welding current is 220-260A, and the arc voltage is 220-260A. is 26-30V.
150mm的Q370qE钢仰位焊采用焊条电弧焊;150mm Q370qE steel overhead welding uses electrode arc welding;
150mm的Q370qE钢正式焊缝采用气体保护焊与埋弧焊相结合的方式;填充焊缝采用多层多道焊,焊接材料为埋弧焊丝H08Mn2E加埋弧焊剂SJ101q,焊接三层后翻身,进行碳弧气刨,清除未熔合区域,打磨匀顺后采用埋弧自动焊焊接,焊缝两面交替焊接,每焊接四层进行一次翻身,焊接时保证连续施焊,不应断弧;焊缝厚度控制在4-5mm,层间温度控制在80-200℃,焊接电流为600-700A,电弧电压为28-32V,焊接速度为20-26m/h。The formal weld of the 150mm Q370qE steel uses a combination of gas shielded welding and submerged arc welding; the filling weld uses multi-layer multi-pass welding, and the welding material is submerged arc welding wire H08Mn2E plus submerged arc flux SJ101q. After welding three layers, turn over and proceed. Carbon arc gouging is used to remove unfused areas, and then submerged arc automatic welding is used after smooth polishing. Welding seams are alternately welded on both sides and turned over every four layers. During welding, continuous welding is ensured and the arc should not be interrupted; weld seam thickness Control it at 4-5mm, the interlayer temperature at 80-200℃, the welding current at 600-700A, the arc voltage at 28-32V, and the welding speed at 20-26m/h.
150mm的Q370qE钢焊后进行后热处理,将焊缝两侧进行加热至200-250℃,后热结束后将石棉铺在焊缝上,进行保温缓冷,焊接完成48h后进行超声波探伤。150mm Q370qE steel is subjected to post-heat treatment after welding. Both sides of the weld are heated to 200-250°C. After post-heating, asbestos is spread on the weld for thermal insulation and slow cooling. Ultrasonic flaw detection is performed 48 hours after the welding is completed.
本行业的技术人员应该了解,本发明不受上述实施例的限制,上述实施例和说明书中描述的只是说明本发明的原理,在不脱离本发明精神和范围的前提下,本发明还会有各种变化和改进,这些变化和改进都落入要求保护的本发明范围内。本发明要求保护范围由所附的权利要求书及其等效物界定。Those skilled in the industry should understand that the present invention is not limited by the above embodiments. The above embodiments and descriptions only illustrate the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention will also have other aspects. Various changes and modifications are possible, which fall within the scope of the claimed invention. The scope of protection of the present invention is defined by the appended claims and their equivalents.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310744308.6A CN116727814A (en) | 2023-06-25 | 2023-06-25 | Welding process for bridge steel Q370qE ultra-thick plate |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310744308.6A CN116727814A (en) | 2023-06-25 | 2023-06-25 | Welding process for bridge steel Q370qE ultra-thick plate |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116727814A true CN116727814A (en) | 2023-09-12 |
Family
ID=87907829
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310744308.6A Pending CN116727814A (en) | 2023-06-25 | 2023-06-25 | Welding process for bridge steel Q370qE ultra-thick plate |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116727814A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117324892A (en) * | 2023-09-14 | 2024-01-02 | 中铁山桥(南通)有限公司 | An efficient butt welding method for high-strength bridge steel Q500qD thick plates |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101491855A (en) * | 2008-05-16 | 2009-07-29 | 中冶天工上海十三冶建设有限公司 | T, L type heavy-plate joint fusion-penetration welding method |
| CN102744498A (en) * | 2012-07-05 | 2012-10-24 | 首钢总公司 | Method for welding specially-thick high-strength bridge steel plate |
| CN104384677A (en) * | 2014-11-05 | 2015-03-04 | 九冶建设有限公司 | Super-thick steel plate welding method |
| CN106001868A (en) * | 2016-05-18 | 2016-10-12 | 南京合信智能装备有限公司 | Full penetration welding method for simultaneously welding H-shaped steel with two guns |
| WO2022142286A1 (en) * | 2020-12-28 | 2022-07-07 | 中铁九桥工程有限公司 | Process method for one-sided welding and double-sided molding of alpine region q500qenh weathering steel |
| CN115889939A (en) * | 2022-12-20 | 2023-04-04 | 中铁山桥(南通)有限公司 | Welding process for stainless steel drainage tank of bridge |
-
2023
- 2023-06-25 CN CN202310744308.6A patent/CN116727814A/en active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101491855A (en) * | 2008-05-16 | 2009-07-29 | 中冶天工上海十三冶建设有限公司 | T, L type heavy-plate joint fusion-penetration welding method |
| CN102744498A (en) * | 2012-07-05 | 2012-10-24 | 首钢总公司 | Method for welding specially-thick high-strength bridge steel plate |
| CN104384677A (en) * | 2014-11-05 | 2015-03-04 | 九冶建设有限公司 | Super-thick steel plate welding method |
| CN106001868A (en) * | 2016-05-18 | 2016-10-12 | 南京合信智能装备有限公司 | Full penetration welding method for simultaneously welding H-shaped steel with two guns |
| WO2022142286A1 (en) * | 2020-12-28 | 2022-07-07 | 中铁九桥工程有限公司 | Process method for one-sided welding and double-sided molding of alpine region q500qenh weathering steel |
| CN115889939A (en) * | 2022-12-20 | 2023-04-04 | 中铁山桥(南通)有限公司 | Welding process for stainless steel drainage tank of bridge |
Non-Patent Citations (1)
| Title |
|---|
| 张成国;冯清川;朱沈来;焦燕星;: "欧标钢结构超厚板焊接工艺", 焊接技术, no. 05, 28 February 2015 (2015-02-28), pages 44 - 46 * |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117324892A (en) * | 2023-09-14 | 2024-01-02 | 中铁山桥(南通)有限公司 | An efficient butt welding method for high-strength bridge steel Q500qD thick plates |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101543926B (en) | Repair Welding Technology of Ductile Iron Roller | |
| CN100548562C (en) | Welding method for thick plate of 50+120mm | |
| CN113351966B (en) | Dissimilar steel welding method for low alloy steel and austenitic stainless steel | |
| CN101774063B (en) | Defect repair welding process of stainless steel composite board coating | |
| CN105665898B (en) | A kind of pearlitic heat resistant steel composite board Lincoln weld welding method | |
| WO2018176696A1 (en) | Vertical butt joint welding method for thick plates | |
| CN104384677A (en) | Super-thick steel plate welding method | |
| CN103464925B (en) | High-temperature heat-proof steel component welding repair method for power station | |
| CN104084749A (en) | Field welding repair method particularly suitable for bead weld layer defects on low alloy and carbon steel | |
| WO2018196280A1 (en) | Method for submerged arc welding at inclined position | |
| CN113927133A (en) | A welding method for improving fatigue performance of welded joints of marine risers | |
| CN113172361B (en) | Method and system for welding and repairing hub of wind generating set | |
| CN107984105A (en) | The welding procedure of wind power tower S355NL steel | |
| CN103934544A (en) | Method for preventing overlaying sealing surface from cracking | |
| CN113275711A (en) | Method for welding hydraulic support structural part by using welding wire with diameter of 1.4mm | |
| CN102091852A (en) | Method for welding copper nickel pipe | |
| CN114734125B (en) | A preheat-free welding method suitable for 500HB grade wear-resistant steel | |
| CN114273764B (en) | Butt joint girth weld welding method for high-strength steel plate steel pipe piles | |
| CN104625322B (en) | Large non-standard device thick-plate all-position welding method | |
| CN116727814A (en) | Welding process for bridge steel Q370qE ultra-thick plate | |
| CN113042876B (en) | Friction stir additive manufacturing method for presetting heterogeneous metal interlayer | |
| CN116275401A (en) | Large-caliber pipe dissimilar steel welding process applied to advanced ultra-supercritical boiler material | |
| CN117139794A (en) | Q500qe high-strength steel plate welding manufacturing process | |
| CN105252109A (en) | Weld crack repair welding method for 30 CrMnSiA welding structural part finished product | |
| CN116551129B (en) | Submerged arc welding process for marine ultra-thick plate jointed board |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |