CN116695684A - Steel sheet pile and steel sheet pile support secondary disease control construction method - Google Patents
Steel sheet pile and steel sheet pile support secondary disease control construction method Download PDFInfo
- Publication number
- CN116695684A CN116695684A CN202310817932.4A CN202310817932A CN116695684A CN 116695684 A CN116695684 A CN 116695684A CN 202310817932 A CN202310817932 A CN 202310817932A CN 116695684 A CN116695684 A CN 116695684A
- Authority
- CN
- China
- Prior art keywords
- steel sheet
- sand
- injection pipe
- sheet pile
- water
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/04—Prefabricated parts, e.g. composite sheet piles made of steel
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
- E02D17/08—Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
- E02D17/12—Back-filling of foundation trenches or ditches
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/12—Consolidating by placing solidifying or pore-filling substances in the soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/12—Consolidating by placing solidifying or pore-filling substances in the soil
- E02D3/123—Consolidating by placing solidifying or pore-filling substances in the soil and compacting the soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/16—Auxiliary devices rigidly or detachably arranged on sheet piles for facilitating assembly
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/18—Placing by vibrating
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D9/00—Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
- E02D9/02—Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof by withdrawing
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Engineering & Computer Science (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- Composite Materials (AREA)
- Chemical & Material Sciences (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
一种钢板桩及钢板桩支护次生病害防治施工方法,涉及采用钢板桩进行支护的深基坑施工领域,该钢板桩包括主体钢板以及设置在主体钢板内侧面的注砂管和注水管,注砂管和注水管均沿主体钢板的长度方向设置,主体钢板的内侧面并位于其下部设置有混合室,注砂管和注水管的下端均与混合室连通,混合室具有供水、砂混合后排出的出料口以及能够控制出料口打开或关闭的止逆组件。本发明可有效抑制拔桩后引起的地面沉降和位移现象,保证基坑周围的建(构)筑物、地下管线和其他市政设施的安全和正常使用,尤其能够解决较差地质条件下深沟槽开挖采用钢板桩支护引起的较大变形和不均匀沉降等次生病害。
A steel sheet pile and a construction method for preventing and controlling secondary diseases of the steel sheet pile support, relating to the field of deep foundation pit construction using steel sheet piles for support, the steel sheet pile includes a main steel plate and a sand injection pipe and a water injection pipe arranged on the inner surface of the main steel plate , the sand injection pipe and the water injection pipe are arranged along the length direction of the main steel plate, the inner surface of the main steel plate and its lower part are provided with a mixing chamber, the lower ends of the sand injection pipe and the water injection pipe are connected with the mixing chamber, and the mixing chamber has water supply, sand The discharge port after mixing and the non-return component that can control the opening or closing of the discharge port. The invention can effectively suppress the ground subsidence and displacement caused by pile pulling, ensure the safe and normal use of buildings (structures), underground pipelines and other municipal facilities around the foundation pit, and can especially solve the problem of deep trenches under poor geological conditions. Secondary damage such as large deformation and uneven settlement caused by steel sheet pile support for trench excavation.
Description
技术领域technical field
本发明涉及采用钢板桩进行支护的深基坑施工领域,具体的说是一种钢板桩及钢板桩支护次生病害防治施工方法。The invention relates to the field of deep foundation pit construction supported by steel sheet piles, in particular to a construction method for preventing and controlling secondary diseases of steel sheet piles and steel sheet piles.
背景技术Background technique
钢板桩作为一种基坑支护结构,因其可回收利用、环境污染小、施工效率高等特点而被广泛地应用到城市建设工程中。As a foundation pit support structure, steel sheet piles are widely used in urban construction projects because of their recyclability, low environmental pollution, and high construction efficiency.
在实际应用中的基坑回填后,则需拔除板桩,以便重复使用。目前拔桩后的土孔回填材料主要采用回灌砂子,当管道所处位置地质情况较差时,也可采用注入水泥砂浆。After the foundation pit is backfilled in practical applications, the sheet piles need to be pulled out for reuse. At present, the soil hole backfill material after the pile is pulled out mainly adopts refilling sand, and when the geological condition of the pipeline is poor, injecting cement mortar can also be used.
目前普遍存在由于钢拔桩的振动影响,以及钢拔桩带土过多引起地面沉降和位移,给周围结构和道路带来很大危害,并影响临近原有建筑物、构筑物或地下管线的安全。根据设计方案钢板桩拔除后留下的土孔采用灌砂处理,但往往因较差的地层因钢板桩的振动导致土孔已经堵塞或者坍塌,沙子根本无法回灌。周边道路在车辆荷载及振动下向沟槽滑移,造成路面沉降开裂。因此如何防治或降低钢板桩施工造成的病害是亟需解决的问题。At present, due to the vibration effect of steel pulling piles and the excessive soil of steel pulling piles, ground subsidence and displacement cause great harm to surrounding structures and roads, and affect the safety of adjacent original buildings, structures or underground pipelines. . According to the design plan, the soil holes left after the steel sheet piles are pulled out are treated with sand filling, but the soil holes are often blocked or collapsed due to the vibration of the steel sheet piles in poor ground, and the sand cannot be recharged at all. The surrounding roads slipped to the groove under the vehicle load and vibration, causing the road surface to settle and crack. Therefore, how to prevent or reduce the diseases caused by steel sheet pile construction is an urgent problem to be solved.
现有技术中,申请号为202210488499.X的中国发明专利,公开了一种可拆卸、拔桩过程可同步注浆的钢板桩及其使用方法,其包括主体钢板,主体钢板侧面焊接有用于注浆的注浆通道,在使用时,将注浆管沿注浆通道通至桩尖位置,启动拔桩设备,上拔一定高度后启动注浆泵,在浆体冲击作用下下盖板打开,主体钢板上升的同时能够及时填补拔桩产生的孔洞。In the prior art, the Chinese invention patent with the application number 202210488499.X discloses a detachable steel sheet pile that can be synchronously grouted during the pile pulling process and its use method. The grouting channel for grouting, when in use, pass the grouting pipe to the pile tip along the grouting channel, start the pile pulling equipment, start the grouting pump after pulling up to a certain height, and open the lower cover under the impact of the slurry, While the main steel plate rises, the holes generated by the pile pulling can be filled in time.
但是,由于拔桩过程产生的振动会造成拔桩后的孔洞被泥土填充,尤其是在淤泥质土的工况环境下,淤泥质土受到振动后液化流动,进而填充至钢板桩拔出后的孔洞内,孔洞内灌注的砂浆在初期没有强度,会发生流动,因此砂浆会受到下部液化后淤泥质土的挤压而上返,孔洞不易被填充密实;并且,在现有技术的这种注浆方法中,需要将浆料提前混合完成,并对混合好的浆料持续搅拌以防止其提前凝固,连续拔桩的过程持续时间较长,耗能较多,并且还会出现配置的浆料量与拔桩时的需求量不匹配,造成浆料浪费,或停工等待再次配料而影响生产效率。However, the vibration generated during the pile pulling process will cause the hole after the pile is pulled to be filled with soil, especially in the working condition of muddy soil. In the hole, the mortar poured in the hole has no strength at the initial stage and will flow, so the mortar will be squeezed by the muddy soil after the liquefaction of the lower part and go back up, and the hole is not easy to be filled and dense; In the slurry method, the slurry needs to be mixed in advance, and the mixed slurry should be continuously stirred to prevent it from solidifying in advance. The process of continuous pile extraction takes a long time, consumes more energy, and the configured slurry will also appear. The amount does not match the demand when pulling out piles, resulting in waste of slurry, or stopping work to wait for re-batching, which affects production efficiency.
发明内容Contents of the invention
本发明旨在提供一种钢板桩及钢板桩支护次生病害防治施工方法,以解决如何防治或降低钢板桩施工造成病害的问题。The present invention aims to provide a steel sheet pile and a steel sheet pile support secondary disease prevention construction method to solve the problem of how to prevent or reduce the disease caused by the steel sheet pile construction.
为了解决以上技术问题,本发明采用的具体方案为:一种钢板桩,包括主体钢板以及设置在主体钢板内侧面的注砂管和注水管,注砂管和注水管均沿主体钢板的长度方向设置,主体钢板的内侧面并位于其下部设置有混合室,注砂管和注水管的下端均与混合室连通,混合室具有供水、砂混合后排出的出料口以及能够控制出料口打开或关闭的止逆组件。In order to solve the above technical problems, the specific solution adopted by the present invention is: a steel sheet pile, including a main steel plate and a sand injection pipe and a water injection pipe arranged on the inner surface of the main steel plate, the sand injection pipe and the water injection pipe are all along the length direction of the main steel plate Setting, the inner surface of the main steel plate and the lower part are provided with a mixing chamber, the lower ends of the sand injection pipe and the water injection pipe are connected with the mixing chamber, the mixing chamber has a discharge port for water supply and sand mixing, and can control the opening of the discharge port Or closed non-return components.
作为上述技术方案的进一步优化,止逆组件包括挡板和能够控制挡板打开或关闭出料口的控制单元。As a further optimization of the above technical solution, the non-return assembly includes a baffle and a control unit capable of controlling the baffle to open or close the discharge port.
作为上述技术方案的进一步优化,挡板的上端转动连接在混合室的侧壁并位于出料口上方,控制单元包括转轴和设置在转轴上的档杆,转轴和档杆之间连接有扭簧,档杆在扭簧的扭力作用下能够将挡板封堵在出料口,且混合室内物料外排的冲击力能够克服扭簧的扭力并推动挡板外移,以打开出料口。As a further optimization of the above technical solution, the upper end of the baffle is rotatably connected to the side wall of the mixing chamber and located above the discharge port. The control unit includes a rotating shaft and a gear lever arranged on the rotating shaft. A torsion spring is connected between the rotating shaft and the gear lever. Under the torsion of the torsion spring, the gear rod can block the baffle at the discharge port, and the impact force of the material discharged from the mixing chamber can overcome the torsion of the torsion spring and push the baffle to move outward to open the discharge port.
作为上述技术方案的进一步优化,挡板的下端转动连接在混合室的侧壁并位于出料口下方,控制单元为连接在挡板内侧的拉绳,拉绳的末端由注砂管或注水管伸出后固定在主体钢板上。As a further optimization of the above technical solution, the lower end of the baffle is rotatably connected to the side wall of the mixing chamber and located below the discharge port. The control unit is a pull rope connected to the inside of the baffle, and the end of the pull rope is connected by a sand injection pipe or a water injection pipe. After stretching out, it is fixed on the main steel plate.
作为上述技术方案的进一步优化,混合室为上大下小的楔形。As a further optimization of the above technical solution, the mixing chamber is wedge-shaped with a large top and a small bottom.
作为上述技术方案的进一步优化,注砂管和注水管呈V形分布。As a further optimization of the above technical solution, the sand injection pipes and water injection pipes are distributed in a V shape.
作为上述技术方案的进一步优化,注砂管的进砂口和注水管的进水口均低于主体钢板的上边沿。As a further optimization of the above technical solution, the sand inlet of the sand injection pipe and the water inlet of the water injection pipe are both lower than the upper edge of the main steel plate.
作为上述技术方案的进一步优化,主体钢板的横截面为梯形,包括主钢板和相对设置在主钢板两侧的侧钢板,注砂管和注水管均设置在主钢板上。As a further optimization of the above technical solution, the cross-section of the main steel plate is trapezoidal, including the main steel plate and side steel plates oppositely arranged on both sides of the main steel plate, and the sand injection pipe and the water injection pipe are both arranged on the main steel plate.
一种基于上述钢板桩的钢板桩支护次生病害防治施工方法,包括以下步骤,A construction method for preventing and controlling secondary diseases of steel sheet pile support based on the above steel sheet piles, comprising the following steps,
S1:将钢板桩的注砂管和注水管分别连接干式喷砂机和上水泵;S1: Connect the sand injection pipe and water injection pipe of the steel sheet pile to the dry sandblasting machine and the water pump respectively;
S2:先向上提升钢板桩,再启动干式喷砂机和上水泵,砂、水进入混合室进行混和,混合后的砂水混合物经振动液化从而经下方的出料口喷出,并填充在拔出钢板桩后的孔洞内;S2: Lift the steel sheet pile up first, then start the dry sandblasting machine and the water pump, the sand and water enter the mixing chamber for mixing, and the mixed sand and water mixture is vibrated and liquefied to be sprayed out through the outlet below, and filled in In the hole after the steel sheet pile is pulled out;
S3:对钢板桩拔出后的孔洞顶部采用砂土压实。S3: Use sand to compact the top of the hole after the steel sheet pile is pulled out.
作为上述技术方案的进一步优化,步骤S2中,通过振动打桩机向上提升钢板桩20~40cm后,先打开干式喷砂机向注砂管内送风,保持风压0.1-0.2MPa并向注砂管内送砂,再按照水压比风压高0.1MPa,水砂比0.8:1进行喷射。As a further optimization of the above technical solution, in step S2, after the steel sheet pile is lifted up by 20-40cm by the vibrating pile driver, the dry sandblasting machine is first turned on to supply air to the sand injection pipe, and the air pressure is maintained at 0.1-0.2MPa to inject sand into the sand injection pipe. Send sand in the pipe, and then spray according to the water pressure is 0.1MPa higher than the wind pressure, and the water-sand ratio is 0.8:1.
与现有技术相比,本发明的有益效果如下:Compared with the prior art, the beneficial effects of the present invention are as follows:
本发明可有效抑制拔桩后引起的地面沉降和位移现象,保证基坑周围的建(构)筑物、地下管线和其他市政设施的安全和正常使用,尤其能够解决较差地质条件下深沟槽开挖采用钢板桩支护引起的较大变形和不均匀沉降等次生病害。The invention can effectively suppress the ground subsidence and displacement caused by pile pulling, ensure the safe and normal use of buildings (structures), underground pipelines and other municipal facilities around the foundation pit, and can especially solve the problem of deep trenches under poor geological conditions. Secondary damage such as large deformation and uneven settlement caused by steel sheet pile support for trench excavation.
本发明的施工方法主要是在拔桩过程中采取强冲砂措施实现病害防治,采用在钢板桩上增加注砂管和注水管,在正常拔桩的过程中,将砂料和水分别通过钢板桩上的注砂管和水管同时注入,借助振动打桩机拔桩时产生的强振动,结合砂石振动液化的原理,利用水震法和振冲法相结合,将水和砂混合后在打桩机拔桩产生的强振动作用下达到密实效果,从而保证拔桩后孔洞的密实,有效抑制侧向土压力的的释放,针对性解决拔桩后的孔洞引起沉降开裂问题。The construction method of the present invention mainly adopts strong sand washing measures to realize disease prevention and control during the pile pulling process, adopts adding sand injection pipes and water injection pipes on the steel sheet piles, and passes sand materials and water through the steel sheet piles during the normal pile pulling process. The sand injection pipe and the water pipe on the pile are injected at the same time, with the help of the strong vibration generated when the vibratory pile driver pulls out the pile, combined with the principle of sand and gravel vibration liquefaction, using the combination of water shock method and vibratory flushing method, water and sand are mixed and placed on the pile driver Under the action of strong vibration generated by pile pulling, the compaction effect can be achieved, so as to ensure the compactness of the holes after pile pulling, effectively inhibit the release of lateral earth pressure, and solve the problem of settlement and cracking caused by holes after pulling piles.
本发明中填充拔桩后孔洞的的原材料主要为分开存放的砂子和水,相较于加工后的砂浆在成本及现场存放上占据优势,砂子和水在使用过程中按需配比,也避免了砂浆配置量没有恰好满足施工需求而造成的资源浪费或影响拔桩作业的进度。In the present invention, the raw materials for filling the holes after pile extraction are mainly sand and water stored separately. Compared with the processed mortar, it has advantages in cost and on-site storage. The ratio of sand and water in the use process is also avoided. The waste of resources caused by the amount of mortar configuration not meeting the construction requirements or affecting the progress of pile pulling operations.
附图说明Description of drawings
图1为本发明的结构示意图;Fig. 1 is a structural representation of the present invention;
图2为控制单元为转轴和档杆时,挡板封堵出料口时的结构示意图;Fig. 2 is a structural schematic diagram when the baffle plate blocks the discharge port when the control unit is a rotating shaft and a gear lever;
图3为控制单元为转轴和档杆时,出料口打开时的结构示意图;Fig. 3 is a structural schematic diagram when the discharge port is opened when the control unit is a rotating shaft and a gear lever;
图4为控制单元为拉绳时,挡板封堵出料口时的结构示意图;Fig. 4 is a structural schematic diagram when the baffle plate blocks the discharge port when the control unit is a pull cord;
图5为控制单元为拉绳时,出料口打开时的结构示意图;Fig. 5 is a structural schematic diagram when the discharge port is opened when the control unit is a pull rope;
图6为注水管和注砂管低于主体钢板上边沿的结构示意图;Fig. 6 is a structural schematic diagram of the water injection pipe and the sand injection pipe being lower than the upper edge of the main steel plate;
图7为混合室为竖向管道时的结构示意图;Fig. 7 is the structural representation when mixing chamber is vertical pipeline;
图8为钢板桩在使用状态的结构示意图;Fig. 8 is a structural schematic diagram of a steel sheet pile in use;
附图标记:1、主体钢板,101、主钢板,102、侧钢板,2、注水管,3、注砂管,4、混合室,5、止逆组件,501、转动件,502、挡板,503、档杆,504、转轴,505、护板,507、拉绳,6、出料口,7、干式喷砂机,8、上水泵,9、振动打桩机。Reference signs: 1, main steel plate, 101, main steel plate, 102, side steel plate, 2, water injection pipe, 3, sand injection pipe, 4, mixing chamber, 5, non-return assembly, 501, rotating part, 502, baffle plate , 503, gear lever, 504, rotating shaft, 505, guard plate, 507, pull rope, 6, discharge port, 7, dry sandblasting machine, 8, upper water pump, 9, vibratory pile driver.
具体实施方式Detailed ways
下面结合附图及具体实施例对本发明的技术方案做进一步的详细阐述,本发明以下实施例中未详细记载和公开的部分,均应理解为本领域技术人员所知晓或应当知晓的现有技术。The technical solutions of the present invention will be further elaborated below in conjunction with the accompanying drawings and specific embodiments. The parts that are not described in detail and disclosed in the following embodiments of the present invention should be understood as prior art known or should be known to those skilled in the art .
如图1、图6所示,本发明公开了一种钢板桩,包括主体钢板1以及设置在主体钢板1内侧面的注砂管3和注水管2。As shown in FIG. 1 and FIG. 6 , the present invention discloses a steel sheet pile, which includes a main steel plate 1 and a sand injection pipe 3 and a water injection pipe 2 arranged on the inner surface of the main steel plate 1 .
主体钢板1的整体为长条形,横截面为梯形,包括主钢板101和相对设置在主钢板101两侧的侧钢板102。The main steel plate 1 is elongated overall, with a trapezoidal cross-section, including a main steel plate 101 and side steel plates 102 oppositely arranged on both sides of the main steel plate 101 .
注砂管3和注水管2均设置在主体钢板1的凹槽内,并固定在主钢板101上。注砂管3和注水管2沿主体钢板1的长度方向自上而下延伸,注砂管3和注水管2的下端均与混合室4连通,混合室4具有供水、砂混合后排出的出料口6以及能够控制出料口6打开或关闭的止逆组件5。The sand injection pipe 3 and the water injection pipe 2 are both arranged in the groove of the main steel plate 1 and fixed on the main steel plate 101 . The sand injection pipe 3 and the water injection pipe 2 extend from top to bottom along the length direction of the main steel plate 1, and the lower ends of the sand injection pipe 3 and the water injection pipe 2 are connected with the mixing chamber 4, which has an outlet for water supply and sand mixing. The feed port 6 and the non-return assembly 5 capable of controlling the opening or closing of the discharge port 6.
注砂管3和注水管2呈V形分布。注砂管3和注水管2的下端交汇于混合室4顶部的进料口,注砂管3内的砂料和注水管2内的水能够在进料口处碰撞混合,以提高水、砂的混合效果。The sand injection pipe 3 and the water injection pipe 2 are distributed in a V shape. The lower ends of the sand injection pipe 3 and the water injection pipe 2 meet at the feed inlet at the top of the mixing chamber 4, and the sand material in the sand injection pipe 3 and the water in the water injection pipe 2 can collide and mix at the feed inlet to increase the water and sand mixed effect.
混合室4的外形轮廓为上大下小的楔形。混合室4相背于主钢板101的一面为斜面,斜面上开设出料口6,从进料口到出料口6形成弧形的流道。水、砂共同经进料口流入流道内,再从出料口6排出。The profile of the mixing chamber 4 is wedge-shaped with a large top and a small bottom. The side of the mixing chamber 4 opposite to the main steel plate 101 is an inclined plane, on which an outlet 6 is set, and an arc-shaped flow path is formed from the inlet to the outlet 6 . Water and sand flow into the flow channel through the feed port together, and then are discharged from the discharge port 6.
此外,如图7所示,混合室4也可以设置为在注砂管3和注水管2下端的竖向管道,注砂管3和注水管2均交汇在竖向管道的进料口,竖向管道的下端设置有出料口,出料口处设置止逆组件5。In addition, as shown in Figure 7, the mixing chamber 4 can also be set as a vertical pipe at the lower end of the sand injection pipe 3 and the water injection pipe 2, and the sand injection pipe 3 and the water injection pipe 2 all meet at the feed port of the vertical pipe, and the vertical A discharge port is provided at the lower end of the pipeline, and a non-return assembly 5 is provided at the discharge port.
止逆组件5包括挡板502和能够控制挡板502打开或关闭出料口6的控制单元。The non-return assembly 5 includes a baffle 502 and a control unit capable of controlling the baffle 502 to open or close the discharge port 6 .
如图2、图3所示,挡板502的上端转动连接在混合室4的侧壁并位于出料口6上方,具体的,挡板502的上端通过转动件501转动连接在混合室4的侧壁外侧,该侧壁形成混合室4相背于主钢板101的斜面。转动件501为转轴、铰链或合页,以使挡板502能够绕转动件501转动,打开或封堵出料口6即可。本实施例中挡板502与混合室4之间通过合页连接,合页的具体安装方式为现有技术,在此不再赘述。As shown in Figure 2 and Figure 3, the upper end of the baffle plate 502 is rotatably connected to the side wall of the mixing chamber 4 and is located above the discharge port 6. Specifically, the upper end of the baffle plate 502 is rotatably connected to the side wall of the mixing chamber 4 through the rotating member 501. Outside the side wall, the side wall forms a slope of the mixing chamber 4 facing away from the main steel plate 101 . The rotating part 501 is a rotating shaft, a hinge or a hinge, so that the baffle plate 502 can rotate around the rotating part 501, and it is sufficient to open or block the discharge port 6 . In this embodiment, the baffle plate 502 is connected to the mixing chamber 4 through hinges, and the specific installation method of the hinges is the prior art, and will not be repeated here.
控制单元包括转轴504和设置在转轴504上的档杆503,转轴504和档杆503之间连接有扭簧(图中未示出),档杆503在扭簧的扭力作用下能够将挡板502封堵在出料口6,且混合室4内物料外排的冲击力能够克服扭簧的扭力并推动挡板502外移,以打开出料口6。具体的,混合室侧壁上设置有安装座,档杆503的下端开设有通孔,且转轴504穿过档杆的通孔支撑在安装座上,转轴504上套设有扭簧,扭簧的一端固定在档杆503上,另一端固定在混合室4的侧壁。在打桩过程中,扭簧的扭力带动档杆503上端压紧在挡板502上,通过挡板502将出料口6封堵,避免泥土从出料口6进入混合室4内造成混合室4、注砂管3或注水管2堵塞,在拔桩过程中,通过向注砂管3和注水管2通入相应的物料,物料外排的冲击力克服扭簧的扭力打开出料口6,以将物料填充至拔桩产生的孔洞内。The control unit includes a rotating shaft 504 and a gear lever 503 arranged on the rotating shaft 504. A torsion spring (not shown) is connected between the rotating shaft 504 and the gear lever 503. The gear lever 503 can move the baffle plate under the torsion of the torsion spring. 502 is blocked at the discharge port 6, and the impact force of the material discharged in the mixing chamber 4 can overcome the torsion force of the torsion spring and push the baffle plate 502 to move outward to open the discharge port 6. Specifically, a mounting seat is provided on the side wall of the mixing chamber, a through hole is provided at the lower end of the shift rod 503, and the rotating shaft 504 is supported on the mounting seat through the through hole of the shift rod, and a torsion spring is sleeved on the rotating shaft 504, and the torsion spring One end of it is fixed on the bar 503, and the other end is fixed on the side wall of the mixing chamber 4. During the piling process, the torsion force of the torsion spring drives the upper end of the gear rod 503 to be pressed against the baffle 502, and the discharge port 6 is blocked by the baffle 502 to prevent soil from entering the mixing chamber 4 from the discharge port 6 and causing the mixing chamber 4 1. The sand injection pipe 3 or the water injection pipe 2 is blocked. During the pile pulling process, by feeding the corresponding materials into the sand injection pipe 3 and the water injection pipe 2, the impact force of the materials discharged out overcomes the torsion force of the torsion spring to open the discharge port 6, To fill the material into the hole created by the pile pulling.
混合室4的侧壁上还是设有护板505,护板505位于转轴504的下方,护板505可以在打桩的过程中对转轴504和其上的扭簧、档杆503进行保护,减少土层对扭簧和转轴504的冲击。在使用过程中也可以将扭簧的一端固定在档杆503上,另一端固定在护板505上。Still be provided with guard plate 505 on the sidewall of mixing chamber 4, guard plate 505 is positioned at the below of rotating shaft 504, and guard plate 505 can protect rotating shaft 504 and the torsion spring on it, gear rod 503 in the process of pile driving, reduces soil The impact of the layer on the torsion spring and the rotating shaft 504. During use, one end of the torsion spring can also be fixed on the shift rod 503 , and the other end can be fixed on the guard plate 505 .
作为止逆组件5的另一种设置方式,如图4、图5所示,挡板502的下端转动连接在混合室4的侧壁并位于出料口6下方,控制单元为连接在挡板502内侧的拉绳507。具体的,挡板502的下端通过转动件501连接在混合室4的侧壁,转动件501为合页,可以理解的是,转动件501也可以为转轴或铰链。挡板502朝向出料口6的一侧为其内侧,在挡板502的内侧固定有拉绳507,拉绳507为钢丝绳。拉绳507的另一端从混合室4伸出后由注砂管3或注水管2伸出,并固定在主体钢板1上。主体钢板1的凹槽内设置有用于固定拉绳507的固定柱(图中未示出),固定柱靠近注砂管3和注水管2的上端设置,以避免固定柱在打桩过程中进入土层内。As another arrangement of the non-return assembly 5, as shown in Figure 4 and Figure 5, the lower end of the baffle 502 is rotatably connected to the side wall of the mixing chamber 4 and located below the discharge port 6, and the control unit is connected to the baffle 502 inside the stay cord 507. Specifically, the lower end of the baffle plate 502 is connected to the side wall of the mixing chamber 4 through a rotating member 501, which is a hinge. It can be understood that the rotating member 501 can also be a rotating shaft or a hinge. The side of the baffle plate 502 facing the discharge port 6 is its inner side, and a stay rope 507 is fixed on the inner side of the baffle plate 502, and the stay rope 507 is a steel wire rope. The other end of the stay rope 507 stretches out from the mixing chamber 4 and then stretches out from the sand injection pipe 3 or the water injection pipe 2 and is fixed on the main steel plate 1 . The groove of the main steel plate 1 is provided with a fixed column (not shown) for fixing the stay rope 507, and the fixed column is arranged near the upper end of the sand injection pipe 3 and the water injection pipe 2, so as to prevent the fixed column from entering the soil during piling. layer.
通过拉紧拉绳507可以使挡板502封堵出料口6,在拔桩时,松开拉绳507,混合室4内的物料冲击挡板502以打开出料口6,从而将物料填充在拔桩产生的孔洞内。By tightening the stay rope 507, the baffle plate 502 can block the discharge port 6. When the pile is pulled out, the stay cord 507 is loosened, and the material in the mixing chamber 4 impacts the baffle plate 502 to open the discharge port 6, thereby filling the material In the hole created by pulling the pile.
拉绳507的长度大于主体钢板1的长度,以使松开拉绳507后,拉绳507远离挡板502的一端依然能够绑定在固定柱上,避免拉绳507落入注砂管3或注水管2对后期的重复利用造成不便。The length of the stay cord 507 is greater than the length of the main steel plate 1, so that after the stay cord 507 is loosened, the end of the stay cord 507 away from the baffle plate 502 can still be bound to the fixed column, preventing the stay cord 507 from falling into the sand injection pipe 3 or The water injection pipe 2 is inconvenient for later reuse.
如图6所示,注砂管3的进砂口和注水管2的进水口均低于主体钢板1的上边沿。可以便于钢板打桩机的夹具夹持钢板桩。As shown in FIG. 6 , both the sand inlet of the sand injection pipe 3 and the water inlet of the water injection pipe 2 are lower than the upper edge of the main steel plate 1 . It is convenient for the clamp of the steel sheet pile driver to hold the steel sheet pile.
本发明还公开了一种钢板桩支护次生病害防治施工方法,包括以下步骤,The invention also discloses a construction method for preventing and controlling secondary diseases of steel sheet pile support, which includes the following steps:
S1:将钢板桩的注砂管3和注水管2分别连接干式喷砂机7和上水泵8;如图8所示为钢板桩连接干式喷砂机7和上水泵8后的示意图。S1: Connect the sand injection pipe 3 and the water injection pipe 2 of the steel sheet pile to the dry sand blasting machine 7 and the upper water pump 8 respectively;
S2:先向上提升钢板桩,再启动干式喷砂机7和上水泵8,砂、水进入混合室4进行混和,混合后的砂水混合物经振动液化从而经下方的出料口6喷出,并填充在拔出钢板桩后的孔洞内;S2: Lift the steel sheet pile upwards first, then start the dry sandblasting machine 7 and the water pump 8, sand and water enter the mixing chamber 4 for mixing, and the mixed sand and water mixture is vibrated and liquefied to be sprayed out through the lower outlet 6 , and fill in the hole after the steel sheet pile is pulled out;
通过振动打桩机9向上提升钢板桩20~40cm,先打开干式喷砂机7向注砂管3内送风,保持风压0.1-0.2MPa并向注砂管3内送砂,再按照水压比风压高0.1MPa,水砂比0.8:1进行喷射;根据土工试验,选定砂的堆积密度在1.36~1.60g/cm3范围,孔隙率在42%~47%之间,注水量应保证注入干砂处于饱和状态,确定水砂比(体积比)为0.8:1。Lift the steel sheet pile upwards by 20-40cm through the vibrating pile driver 9, first turn on the dry sandblasting machine 7 to supply air to the sand injection pipe 3, keep the wind pressure at 0.1-0.2MPa and send sand to the sand injection pipe 3, and then follow the water The pressure is 0.1MPa higher than the wind pressure, and the water-sand ratio is 0.8:1 for spraying; according to the geotechnical test, the bulk density of the selected sand is in the range of 1.36-1.60g/ cm3 , the porosity is between 42% and 47%, and the water injection volume It should be ensured that the injected dry sand is in a saturated state, and the water-sand ratio (volume ratio) is determined to be 0.8:1.
拔桩速度根据不同施工场地进行试验确定,一般控制在2cm/s~1.5cm/s,在此速度下能够确保砂和水能及时填充拔桩后的空隙,同时充分利用拔桩的震动效果使砂密实。The pile pulling speed is determined according to different construction sites, and is generally controlled at 2cm/s~1.5cm/s. At this speed, it can ensure that the sand and water can fill the gaps after pile pulling in time, and at the same time make full use of the vibration effect of pile pulling to make The sand is dense.
S3:对钢板桩拔出后的孔洞顶部采用砂土压实。S3: Use sand to compact the top of the hole after the steel sheet pile is pulled out.
本发明以珠海前山河综合整治二期工程为工程实例,通过对华宇路污水管道的钢板桩进行施工研究,钢板桩支护次生灾害防治施工技术可有效减少钢板桩拔桩后对周边地层的影响,减少对现有路面的破坏,施工完成后钢板桩拔除的空隙回填密实,大大降低了路面沉降的风险,施工效益显著,通过工程实践证明,该技术具有可操作性、实用性。The present invention takes the second-phase project of comprehensive improvement of Qianshan River in Zhuhai as an engineering example, and conducts construction research on the steel sheet piles of the Huayu Road sewage pipeline. The construction technology for the prevention and control of secondary disasters supported by steel sheet piles can effectively reduce the damage to the surrounding strata after the steel sheet piles are pulled out. After the construction is completed, the gaps removed by the steel sheet piles are backfilled densely, which greatly reduces the risk of road surface settlement, and the construction benefits are remarkable. The engineering practice has proved that this technology is operable and practical.
具体施工过程如下:The specific construction process is as follows:
施工工艺流程包括:施工准备→测量放线→施打灌砂型钢板桩→沟槽开挖、管道安装→沟槽回填施工→边灌砂边震动拔桩→施工完成。The construction process includes: construction preparation → measurement and setting out → application of sand-filled steel sheet piles → trench excavation, pipeline installation → trench backfilling construction → sand pouring and pile extraction → construction completion.
施工准备:Construction preparation:
(1)施工前对作业人员进行安全技术交底,明确作业程序、作业分工、作业中可能存在的危险因素及采取的防护措施等。(1) Disclose the safety technology of the operators before construction, and clarify the operating procedures, division of labor, possible risk factors and protective measures taken during the operation.
(2)在施工前对施工范围内的管线采用人工挖探槽和探底雷达结合的方式进行探测,查明施工区域内地下管线的埋设情况。(2) Before the construction, the pipelines in the construction area shall be detected by the combination of manual excavation trench and bottom-penetrating radar, and the buried conditions of underground pipelines in the construction area shall be found out.
(3)根据土孔的体积适量储备回填粗砂,确保喷射机运行正常。(3) Reserve an appropriate amount of backfill coarse sand according to the volume of the soil hole to ensure the normal operation of the jetting machine.
(4)在作业部位张贴危险告知牌,警示作业人员存在的危害因素,警告周围无关人员远离危险作业部位。(4) Post hazard notice boards on the operating site to warn the workers of the hazards and warn the surrounding unrelated personnel to stay away from the dangerous operating site.
(5)确定喷射水砂比(5) Determine the jet water-sand ratio
首先根据土工试验,确定砂的堆积密度在1.36~1.60g/cm3范围,孔隙率在42%~47%之间。注水量应保证注入干砂处于饱和状态,确定水砂比(体积比)为0.8:1。First, according to the geotechnical test, it is determined that the bulk density of the sand is in the range of 1.36-1.60g/ cm3 , and the porosity is between 42% and 47%. The amount of water injected should ensure that the injected dry sand is in a saturated state, and the water-sand ratio (volume ratio) is determined to be 0.8:1.
(6)正式施工前应进行试喷试验,确定拔桩速度,确保砂和水能及时填充拔桩后的空隙,同时充分利用拔桩的震动效果使砂密实。(6) Before the official construction, a trial spraying test should be carried out to determine the pile pulling speed, to ensure that the sand and water can fill the gaps after the pile pulling in time, and at the same time make full use of the vibration effect of the pile pulling to make the sand dense.
测量放线:Measuring and setting out:
(1)首先核定永久性控制点,建立坐标控制网,精度应符合要求。(1) Firstly, the permanent control points are verified, and the coordinate control network is established, and the accuracy should meet the requirements.
(2)严格按施工图及井位坐标先定出沟槽轴线,再根据图纸设计要求放出基槽的开挖线。(2) Determine the trench axis strictly according to the construction drawing and well position coordinates, and then release the excavation line of the foundation trench according to the drawing design requirements.
(3)施工中管沟纵断面的高程控制,采用基底设置高程控制桩,控制桩间距为10m,在桩上部标注高程。(3) For the elevation control of the vertical section of the pipe ditch during construction, the elevation control piles are set at the base, the distance between the control piles is 10m, and the elevation is marked on the top of the piles.
施打灌砂型钢板桩Casting sand-type steel sheet piles
(1)采用本发明的钢板桩,注砂管3和注水管2分别为φ4cm的钢管,出料口6的直径为5cm。在钢板桩上部,注砂管3和注水管2略低于主体钢板1上沿以便于钢板桩机夹具夹桩。两钢管呈V形布置,在钢板桩的底部两根管交叉在一起通入楔形槽内,楔形槽和钢板桩的下沿齐平。(1) Using the steel sheet pile of the present invention, the sand injection pipe 3 and the water injection pipe 2 are respectively φ4cm steel pipes, and the diameter of the discharge port 6 is 5cm. On the upper part of the steel sheet pile, the sand injection pipe 3 and the water injection pipe 2 are slightly lower than the upper edge of the steel sheet 1 of the main body so as to facilitate the clamping of the steel sheet pile machine. The two steel pipes are arranged in a V shape. At the bottom of the steel sheet pile, the two pipes intersect and pass into the wedge-shaped groove. The wedge-shaped groove is flush with the lower edge of the steel sheet pile.
(2)钢板桩打拔采用振动打桩机9施打。打桩前对钢板桩逐根检查,剔除连接锁口锈蚀、变形严重的普通板桩,并确保注砂管入口和注水管入口是否通畅,不合格的钢板桩待修整后方可使用。在钢板桩的锁口内涂油脂,以方便打入拔出。(2) The steel sheet pile is driven by a vibratory pile driver 9 . Before piling, inspect the steel sheet piles one by one, remove the ordinary sheet piles with corrosion and serious deformation at the connection lock, and ensure that the entrance of the sand injection pipe and the water injection pipe are unobstructed, and the unqualified steel sheet piles can be used after being repaired. Apply grease to the lock of the steel sheet pile to facilitate driving in and out.
(3)钢板桩施打采用屏风式逐根打入法施工。屏风式打入法不易使板桩发生屈曲、扭转、倾斜和墙面凹凸,打入精度高,易于实现封闭合拢。施工时,将10~20根钢板桩成排插入导架内,使它呈屏风状,然后再施打。通常将屏风墙两端的一组钢板桩打至设计标高或一定深度,并严格控制垂直度,用电焊固定在围檩上,然后在中间按顺序分1/3或1/2板桩高度打入。(3) The steel sheet piles are driven by the screen-type root-by-root driving method. The screen-type driving method is not easy to cause buckling, twisting, tilting and unevenness of the wall surface, and the driving precision is high, and it is easy to realize sealing and closing. During construction, insert 10 to 20 steel sheet piles into the guide frame in a row to make it screen-like, and then drive. Usually, a group of steel sheet piles at both ends of the screen wall are driven to the design elevation or a certain depth, and the verticality is strictly controlled. .
沟槽开挖trench excavation
(1)沟槽开挖采用后退法开挖,分台阶进行,在开挖过程中遵循“开槽支撑,先撑后挖,分层开挖,严禁超挖”的施工原则。开挖时由一台反铲挖掘机进行开挖,开挖时力求做到随挖随运,开挖过程中应与支撑相互配合,挖掘机挖土后必须及时支撑,防止槽壁失稳而导致沟槽坍塌。(1) The trench excavation adopts the step-back method and is divided into steps. During the excavation process, the construction principle of "grooving support, first supporting and then digging, layered excavation, and over-excavation is strictly prohibited" shall be followed. Excavation is carried out by a backhoe excavator. During the excavation, it strives to be excavated and transported. During the excavation process, it should cooperate with the support. The excavator must be supported in time after digging to prevent the wall from becoming unstable and causing the trench to collapse.
(2)挖掘机以及自卸汽车由专人指挥至指定地点就位施工,装土过程中,自卸汽车、挖掘机工作半径范围内严禁人员靠近。安排专人加强对自卸汽车的监管力度,严格把控,坚决杜绝自卸汽车超高、超载装运。(2) Excavators and dump trucks are directed by special personnel to the designated location for construction. During the soil loading process, personnel within the working radius of dump trucks and excavators are strictly prohibited from approaching. Arrange special personnel to strengthen the supervision of dump trucks, strictly control them, and resolutely put an end to super-high and overloaded dump trucks.
(3)管道安装采用人工配合吊车将管道吊至管沟内。吊装时,钢丝绳与铸铁管接触处用废旧橡胶垫隔以保护铸铁管和防腐层。管道安装采用自下游向上游进行下管,并控制管道的中线和高程。管道安装将插口顺水流方向,承口逆水流方向,由低点向高点依次安装,管道安装采用人工调整。(3) The pipeline is installed manually with a crane to hoist the pipeline into the trench. When hoisting, the contact between the steel wire rope and the cast iron pipe is separated by waste rubber pads to protect the cast iron pipe and the anti-corrosion layer. Pipeline installation is carried out from downstream to upstream, and the centerline and elevation of the pipeline are controlled. When installing the pipeline, install the socket along the direction of the water flow, and the socket against the direction of the water flow, and install them sequentially from the low point to the high point. The pipeline installation adopts manual adjustment.
沟槽回填施工Trench backfill construction
(1)管道在密闭性试验合格后,沟槽应及时进行回填,回填料采用石屑,回填分层夯实。(1) After the pipeline passes the airtightness test, the groove should be backfilled in time. The backfill should be stone chips, and the backfill should be compacted in layers.
(2)回填前应先将基底的建筑垃圾、积水、淤泥和杂物清理干净。管道基础顶至管顶0.5m范围内必须采用人工回填、夯实。管道两侧回填同时进行,两侧高差不得超过0.3m,并要注意管道腋角部位的夯实质量。(2) Before backfilling, the construction waste, accumulated water, silt and sundries on the base should be cleaned up. The range of 0.5m from the top of the pipeline foundation to the top of the pipeline must be backfilled and compacted manually. The backfilling on both sides of the pipeline shall be carried out at the same time, and the height difference between the two sides shall not exceed 0.3m, and attention shall be paid to the compaction quality of the axillary corners of the pipeline.
(3)管顶500mm以上部位回填时可采用机械从管道轴线两侧同时回填、夯实或碾压。(3) When backfilling the part above 500mm above the pipe top, mechanical backfilling, compaction or rolling can be used from both sides of the pipe axis at the same time.
边灌砂边振动拔桩Vibrating Pile Pulling While Filling Sand
(1)喷射砂料选用粗砂,砂料在运输、存放过程中应防止雨淋,保证砂料的干燥。装入喷射机前应过筛,防治大石块等杂物混入堵塞喷管。(1) Coarse sand is used for spraying sand, and the sand should be protected from rain during transportation and storage to ensure that the sand is dry. It should be sieved before loading into the injection machine to prevent debris such as large stones from mixing into the nozzle to block the nozzle.
(2)拔桩开始提升30cm后开始启动喷射砂料和注水。喷射开始时,应先送风,后开机注砂给料,保持风压0.1-0.2MPa,水压应比风压高0.1MPa左右,按照水砂比0.8:1进行喷射。喷射时向干式喷砂机供料应连续均匀,机械运转正常时,干式喷砂机内应保持足够的存料。喷射工作完毕或因故中断喷射时,将注砂管3内的积料清除干净。结束时应待注砂管3内砂料喷射完成后再关闭风。(2) After the pile pulling starts to lift 30cm, sand injection and water injection are started. At the beginning of spraying, the air should be supplied first, and then the machine should be turned on to inject sand and feed materials. Keep the wind pressure at 0.1-0.2MPa, the water pressure should be about 0.1MPa higher than the wind pressure, and spray according to the water-sand ratio of 0.8:1. The supply of material to the dry sandblasting machine should be continuous and even when spraying. When the machine is running normally, there should be enough stock in the dry sandblasting machine. When the spraying work is completed or the spraying is interrupted for some reason, the accumulated material in the sand injection pipe 3 should be cleaned up. When finished, the wind should be closed after the injection of the sand material in the sand injection pipe 3 is completed.
(3)喷射砂土时,灌水也应与其同时进行。槽内留下的干砂与水混合后在高压气流的作用下从出料口6排出,混合体快速填充在在钢板桩的孔洞内。(3) When spraying sandy soil, irrigation should also be carried out at the same time. The dry sand left in the tank is mixed with water and discharged from the discharge port 6 under the action of high-pressure airflow, and the mixture is quickly filled in the holes in the steel sheet pile.
(5)为了保证钢板桩的拔桩施工采用跳桩法拔除,完成一根桩的拔除后间隔一根进行拔除,跳桩法拔除可使砂土回填更加密实,并有效减少相邻钢板桩拔出的影响。(5) In order to ensure that the steel sheet piles are pulled out by the jumping pile method, one pile is pulled out at intervals after the pile is pulled out. The jumping pile method can make the sand backfill more compact and effectively reduce the pullout of adjacent steel sheet piles. out the impact.
(6)拔出的钢板桩需进行进砂管和进水管的清理,以便于周转使用。(6) The extracted steel sheet piles need to be cleaned for sand inlet pipes and water inlet pipes for easy turnover.
(7)对钢板桩拔除顶部的砂土进行再次压实。(7) Re-compact the sand on the top of the steel sheet pile.
施工注意事项Construction Notes
(1)钢板桩的打拔采用后退打拔法,避免重型钢板桩桩基对路基结构的影响。(1) The steel sheet piles are pulled out using the backward pulling method to avoid the impact of the heavy steel sheet pile foundation on the subgrade structure.
(2)挖机挖土时铺垫钢板增加受力面积,减少开挖过程对沟槽基础的扰动。(2) When the excavator excavates the soil, lay the steel plate to increase the force-bearing area and reduce the disturbance to the trench foundation during the excavation process.
(3)喷射过程中,如发生堵管、停风停电等故障时,应立即关闭水门,处理堵管时采用敲击法输通料管。(3) During the spraying process, if there is a failure such as pipe blockage, wind power failure, etc., the water gate should be closed immediately, and the material pipe should be conveyed by tapping method when dealing with pipe blockage.
(4)喷砂机进气口密封良好,防止漏风吹起粉尘,施工过程中因排气会沿着钢板桩的间隙排放,钢板桩间隙铺盖安全网防止砂土飞扬。(4) The air inlet of the sandblasting machine is well sealed to prevent dust from being blown by air leakage. During the construction process, the exhaust gas will be discharged along the gaps between the steel sheet piles, and the gaps between the steel sheet piles are covered with safety nets to prevent sand from flying.
本发明是采用在钢板桩上增加注砂管3和注水管2,在钢板桩底部合并至一起,并安装止逆组件5,防止钢板桩施打时泥土的涌入,沟槽回填施工完成后,在正常拔桩的过程中,通过本发明钢板桩上的注砂管3和注水管2将砂和水同时注入,将水和砂混合后利用振动效果进行液化,从而流入钢板桩留下的空隙,采用跳桩法进行拔出钢板桩施工,可以有效减少相邻钢板桩拔出的影响,本技术主要依靠在原本施工工艺上,结合砂石振动液化的原理,针对性解决拔桩后留空隙的问题。The present invention adopts the method of adding sand injection pipe 3 and water injection pipe 2 on the steel sheet pile, merging them together at the bottom of the steel sheet pile, and installing the anti-reverse assembly 5 to prevent the influx of soil when the steel sheet pile is driven. After the trench backfilling construction is completed , in the process of normal pile pulling, sand and water are simultaneously injected through the sand injection pipe 3 and water injection pipe 2 on the steel sheet pile of the present invention, and the water and sand are mixed and liquefied by vibration effect, thereby flowing into the leftover water of the steel sheet pile The gap, using the pile-jumping method to pull out the steel sheet pile construction, can effectively reduce the impact of the adjacent steel sheet pile pullout. void problem.
以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included in the scope of the present invention. within the scope of protection.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310817932.4A CN116695684A (en) | 2023-07-05 | 2023-07-05 | Steel sheet pile and steel sheet pile support secondary disease control construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310817932.4A CN116695684A (en) | 2023-07-05 | 2023-07-05 | Steel sheet pile and steel sheet pile support secondary disease control construction method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116695684A true CN116695684A (en) | 2023-09-05 |
Family
ID=87839147
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310817932.4A Pending CN116695684A (en) | 2023-07-05 | 2023-07-05 | Steel sheet pile and steel sheet pile support secondary disease control construction method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116695684A (en) |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102605787A (en) * | 2012-02-29 | 2012-07-25 | 赵兴山 | Device for inhibiting foundation soil from disturbing during removing of steel sheet piles and application method thereof |
| CN203625883U (en) * | 2013-09-18 | 2014-06-04 | 武汉市政工程设计研究院有限责任公司 | Steel sheet support pile with pipes for foundation pit construction |
| CN109695241A (en) * | 2018-11-16 | 2019-04-30 | 中冶天工集团有限公司 | The compound backfill method of road surface lower groove |
| CN220117213U (en) * | 2023-06-09 | 2023-12-01 | 中国水利水电第十一工程局有限公司 | Steel sheet pile structure for preventing road settlement |
-
2023
- 2023-07-05 CN CN202310817932.4A patent/CN116695684A/en active Pending
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102605787A (en) * | 2012-02-29 | 2012-07-25 | 赵兴山 | Device for inhibiting foundation soil from disturbing during removing of steel sheet piles and application method thereof |
| CN203625883U (en) * | 2013-09-18 | 2014-06-04 | 武汉市政工程设计研究院有限责任公司 | Steel sheet support pile with pipes for foundation pit construction |
| CN109695241A (en) * | 2018-11-16 | 2019-04-30 | 中冶天工集团有限公司 | The compound backfill method of road surface lower groove |
| CN220117213U (en) * | 2023-06-09 | 2023-12-01 | 中国水利水电第十一工程局有限公司 | Steel sheet pile structure for preventing road settlement |
Non-Patent Citations (3)
| Title |
|---|
| 富海鹰等: "《普通高等教育十一五国家级规划教材 土力学 第4版》", 31 October 2022, 中国铁道出版社, pages: 277 * |
| 李西彬;吴玲;: "钢板桩支护工程实践", 水利水电施工, no. 04, 31 December 2007 (2007-12-31) * |
| 王虎妹等: "《城市轨道交通路基工程》", 31 January 2018, 北京交通大学出版社, pages: 55 - 56 * |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN112554177B (en) | Construction method of ultra-long small-diameter cast-in-situ bored pile | |
| CN111236957B (en) | Mechanical pipe jacking construction process | |
| CN107859145A (en) | A kind of drainpipe is plugged into construction method under water | |
| CN106088099B (en) | A kind of subway foundation pit anchor cable processing method | |
| CN110778328B (en) | Loess tunnel entrance section construction method for passing through landslide body | |
| CN113174958A (en) | Construction method for foundation pit of adjacent road under poor ground condition | |
| CN114991165A (en) | Construction method for subway deep foundation pit adjacent to railway business line | |
| CN103321246A (en) | Construction Method of Foundation Pit Using Underground Diaphragm Wall | |
| CN111119277B (en) | Method for connecting water intake pipeline in river by crossing cofferdam | |
| CN112064751A (en) | Deep groove construction method for drainage pipeline | |
| CN113266392B (en) | A construction method of pipe jacking through existing anchor cable groups | |
| CN109812271B (en) | Construction method for shield-crossing limited box culvert | |
| CN101994314A (en) | Longhole rectangular terraced antiskid pile jump-preventing excavating construction | |
| CN113266362B (en) | A construction method of pipe jacking and cover excavation crossing existing dense anchor cable area | |
| CN109024621A (en) | The compound retaining wall supporting construction of embankment high slope tubular pole and its construction method | |
| CN113684785A (en) | Construction process of pile foundation wharf | |
| CN116695684A (en) | Steel sheet pile and steel sheet pile support secondary disease control construction method | |
| CN112854117B (en) | L-shaped wharf construction method | |
| CN117345944A (en) | Embedded installation process of large-diameter PCCP pipes on complex foundations | |
| CN114411751A (en) | A multi-layer underground passage construction component based on multi-support structure and its technology | |
| CN114542092A (en) | Construction Method of Shield Tunnel Receiving without Bottom Plate Structure | |
| CN109098205B (en) | Civil air defense underground passage and its construction method | |
| CN114753231B (en) | Frame beam lattice bridge structure crossing underground pipeline and construction method thereof | |
| CN114319372B (en) | Construction method of anchorage supporting structure | |
| CN114232638B (en) | Anchor supporting structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |