CN116397700A - 一种冲孔长桩卡锤后埋锤施工处理方法 - Google Patents
一种冲孔长桩卡锤后埋锤施工处理方法 Download PDFInfo
- Publication number
- CN116397700A CN116397700A CN202310056633.3A CN202310056633A CN116397700A CN 116397700 A CN116397700 A CN 116397700A CN 202310056633 A CN202310056633 A CN 202310056633A CN 116397700 A CN116397700 A CN 116397700A
- Authority
- CN
- China
- Prior art keywords
- hammer
- pile
- pile foundation
- construction
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D33/00—Testing foundations or foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D13/00—Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
- E02D13/08—Removing obstacles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/04—Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/06—Placing concrete under water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
一种冲孔长桩卡锤后埋锤施工处理方法,施工处理步骤为:(1)确认桩基设计承载力特征值及安全系数,复核并研判,通过桩基后注浆是否能满足桩基承载力要求;(2)当通过桩基后注浆满足桩基承载力要求时,放弃打捞原冲锤,对原桩进行回填片石;(3)采用新冲锤重新组织冲孔施工,当冲锤冲到旧冲锤顶部,无法继续往下冲时停止冲孔,进行泥浆循环清孔;(4)安装钢筋笼,进行二次清孔;(5)泥浆比重、含砂率、桩底沉渣均满足设计要求后,灌水下混凝土;(6)混凝土达到设计强度后,对混凝土进行钻压浆孔;(7)采用水泥浆或玻璃水对桩底进行高压注浆。本处理方法是当卡锤时,在不改变桩位的前提下,继续施工,不延误工期,减少施工成本。
Description
技术领域
本发明涉及基础施工的技术领域,具体是一种冲孔长桩卡锤后埋锤施工处理方法。
背景技术
在桥梁桩基冲孔施工中,若钻进过程中遇到斜岩、孤石、夹层、溶洞等地质情况,控制不好冲程时,极易引起卡锤事故。目前对卡锤的常用处理有两种方法:一是采用不同角度尝试斜拉冲锤,若钢丝绳被拉断,还需派潜水员潜到桩底,绑扎钢丝绳,存在很大的安全隐患;二是放弃打捞冲锤,回填土,变更桩位,重新冲孔。以上处理工期比较长,成本比较高,安全隐患大。由于埋锤事故发生在地表深处,“看不见,摸不着”,使事故处理十分困难,很多施工单位因缺乏处理经验,虽费尽心思,想法设法试图打捞,但还是以失败告终。
若锤头无法取出,丢失一个桩锤不仅仅是损失桩锤的成本,还常常造成该桩位报废,需要补桩,延误工期,给建设单位造成工期与投资的双重损失。
发明内容
本发明的目的是提供一种冲孔长桩卡锤后埋锤施工处理方法,该冲孔长桩卡锤后埋锤施工处理方法是在无法将锤头取出时,在不改变桩位的前提下,继续施工,不延误工期,减少施工成本。
为了实现本发明的目的,所采取的技术方案为:
一种冲孔长桩卡锤后埋锤施工处理方法,其特征在于:施工处理包括以下步骤:
(1)根据设计规范,确认桩基设计承载力特征值及安全系数,复核并研判,通过桩基后注浆是否能满足桩基承载力要求。桩基承载力极限值为:,由于卡锤原因,导致桩长未能按原设计施工。根据桩基后注浆加固的原理,通过βs、βp的修正,以达到满足桩基承载力;
(2)当通过桩基后注浆满足桩基承载力要求时,放弃打捞原冲锤,对原桩进行回填片石,要求片石粒径小于15cm,回填高于卡锤位置3m以上。
(3)采用新冲锤重新组织冲孔施工,当冲锤冲到旧冲锤顶部,无法继续往下冲时停止冲孔,使片石填充压紧桩基底部,避免下沉,然后进行泥浆循环清孔。
(4)清孔满足施工要求后,安装钢筋笼,再进行二次清孔。
(5)泥浆比重、含砂率、桩底沉渣均满足设计要求后,灌水下混凝土。
(6)混凝土达到设计强度后,对混凝土进行钻孔,要求钻孔深度大于混凝土长度。
(7)采用水泥浆或玻璃水对桩底进行高压注浆,当高压注浆并养护达到要求后即完成施工处理。
进一步优选的:所述的对混凝土进行钻孔,是从混凝土桩基的顶部从上往下钻三个压浆孔,三个压浆孔以混凝土桩基的中心均布设置。
本冲孔长桩卡锤后埋锤施工处理方法是在施工过程中出现卡锤,无法将锤头取出时,确认桩基设计承载力特征值及安全系数,复核并研判,通过桩基后注浆是否能满足桩基承载力要求,当通过桩基后注浆满足桩基承载力要求时,放弃打捞原冲锤,对原桩进行回填片石,要求片石粒径小于15cm,回填高于卡锤位置3m以上,采用新冲锤重新组织冲孔施工,当冲锤冲到旧冲锤顶部,无法继续往下冲时停止冲孔,进行泥浆循环清孔,清孔满足施工要求后,安装钢筋笼,再进行二次清孔,泥浆比重、含砂率、桩底沉渣均满足设计要求后,灌水下混凝土,混凝土达到设计强度后,对混凝土进行钻孔高压注浆,以达到满足桩基承载力的目的,实现了在不改变桩位的前提下,继续施工,不延误工期,减少施工成本,也避免了打捞卡锤时出现安全事故。
附图说明
图1是本冲孔长桩卡锤后埋锤施工处理后桩基混凝的结构示意图;
图2是压浆孔的布置示意图;
图3是卡锤时桩基的示意图;
图4是桩基回填片石的示意图;
图中的序号对应的名称为:
1、原冲锤,2、钢丝绳,3、钢护筒,4、片石,5、混凝土,6、注浆体,7、压浆孔。
具体实施方式
为了使本申请的技术方案和优点更加清楚,下面结合实施例,对本技术方案进行清楚、完整地描述。
实施例1
采用以下步骤,完成冲孔长桩卡锤后埋锤施工处理:
(1)根据设计规范,确认桩基设计承载力特征值及安全系数,复核并研判,通过桩基后注浆是否能满足桩基承载力要求。
(2)当通过桩基后注浆满足桩基承载力要求时,与原冲锤1连接的钢丝绳2拉断后,放弃打捞原冲锤1,对原桩进行回填片石4,要求片石4粒径小于15cm,回填高于卡锤位置3m以上。
(3)采用新冲锤重新组织冲孔施工,当冲锤冲到旧冲锤顶部,无法继续往下冲时停止冲孔,进行泥浆循环清孔。
(4)清孔满足施工要求后,在钢护筒3中间安装钢筋笼,再进行二次清孔。
(5)泥浆比重、含砂率、桩底沉渣均满足设计要求后,灌水下混凝土5。
(6)混凝土达到设计强度后,对混凝土进行钻孔,要求钻孔深度大于混凝土长度。所述的对混凝土进行钻孔,是从混凝土桩基的顶部从上往下钻三个压浆孔7,三个压浆孔以混凝土桩基的中心均布设置。
(7)采用水泥浆或玻璃水对桩底进行高压注浆,使注浆体6注满混凝土桩基的底部,当高压注浆并养护达到要求后即完成施工处理。
施工应用案例
某桥梁 5号桩基类型为摩擦桩,设计桩长为37m,桩径为Φ2.2m,原设计桩顶高程为520.5m,桩底高程为483.5m。在冲孔到标高为481.5m位置发生卡钻,测得此时孔净深为34m。卡钻位置的地层为强风化粉砂岩。项目采用歪拉斜吊法,沿事故钻头的吊绳方位反方向挪动钻机以偏移一定距离,使钻头吊绳呈斜拉状态,固定钻机后开动卷扬机反复起吊钻头,持续一段时间(10-20min)后再挪动钻机到另一方向,如此往复至拉动事故钻头,但使用此方法没能取出钻头,在多次尝试后,钻头钢丝绳断裂,地面打桩机与孔底钻头失去联系。经项目研讨,采用本申请的冲孔长桩卡锤后埋锤施工处理方法,放弃旧冲锤,对原桩回填片石,采用新冲锤继续冲孔到旧锤顶部后,停止冲孔,进行泥浆循环清孔、灌注水下混凝土,待达到强度后,进行混凝土钻心、后注浆,提高桩基单桩承载力特征值,满足施工及设计要求。
上述说明并非是对本申请的限制,本申请也并不限于上述实例,本技术领域的普通技术人员,在本申请的实质范围内,作出的变化、改型、添加或替换,都应属于本申请的保护范围。
Claims (2)
1.一种冲孔长桩卡锤后埋锤施工处理方法,其特征在于:施工处理包括以下步骤:
(1)根据设计规范,确认桩基设计承载力特征值及安全系数,复核并研判,通过桩基后注浆是否能满足桩基承载力要求;
(2)当通过桩基后注浆满足桩基承载力要求时,放弃打捞原冲锤,对原桩进行回填片石,要求片石粒径小于15cm,回填高于卡锤位置3m以上;
(3)采用新冲锤重新组织冲孔施工,当冲锤冲到旧冲锤顶部,无法继续往下冲时停止冲孔,进行泥浆循环清孔;
(4)清孔满足施工要求后,安装钢筋笼,再进行二次清孔;
(5)泥浆比重、含砂率、桩底沉渣均满足设计要求后,灌水下混凝土;
(6)混凝土达到设计强度后,对混凝土进行钻孔,要求钻孔深度大于混凝土长度;
(7)采用水泥浆或玻璃水对桩底进行高压注浆,当高压注浆并养护达到要求后即完成施工处理。
2.根据权利要求1所述的冲孔长桩卡锤后埋锤施工处理方法,其特征在于:所述的对混凝土进行钻孔,是从混凝土桩基的顶部从上往下钻三个压浆孔,三个压浆孔以混凝土桩基的中心均布设置。
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310056633.3A CN116397700B (zh) | 2023-01-16 | 2023-01-16 | 一种冲孔长桩卡锤后埋锤施工处理方法 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310056633.3A CN116397700B (zh) | 2023-01-16 | 2023-01-16 | 一种冲孔长桩卡锤后埋锤施工处理方法 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN116397700A true CN116397700A (zh) | 2023-07-07 |
| CN116397700B CN116397700B (zh) | 2025-06-03 |
Family
ID=87016670
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310056633.3A Active CN116397700B (zh) | 2023-01-16 | 2023-01-16 | 一种冲孔长桩卡锤后埋锤施工处理方法 |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116397700B (zh) |
Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4624327A (en) * | 1984-10-16 | 1986-11-25 | Flowdril Corporation | Method for combined jet and mechanical drilling |
| CN102409978A (zh) * | 2011-10-26 | 2012-04-11 | 中冶集团武汉勘察研究院有限公司 | 复杂地层灌注桩施工采用多级合金超前牙轮钻头回旋钻进成孔工法 |
| CN105862862A (zh) * | 2016-04-06 | 2016-08-17 | 广东省建筑工程机械施工有限公司 | 一种大直径桩埋锤打捞方法 |
| CN107938676A (zh) * | 2017-11-21 | 2018-04-20 | 重庆建工市政交通工程有限责任公司 | 一种穿越全填充型溶洞的桩基施工方法 |
| US20180340312A1 (en) * | 2017-05-25 | 2018-11-29 | Powerchina Huadong Engineering Corporation Limited | Offshore non-driven-in large-diameter monopile foundation structure and constryction method |
| AU2020101426A4 (en) * | 2020-06-17 | 2020-08-20 | Hebei Research Institute of Construction & Geotechnical Investigation Co., Ltd. | Anti-Deviation Rotary Drilling Tool for Karst Stratum and Drilling Method Thereof |
| WO2021082767A1 (zh) * | 2019-10-31 | 2021-05-06 | 国家电网有限公司 | 一种基于增强纤维和偏高岭土的加压灌注桩的施工方法 |
| CN114837209A (zh) * | 2022-05-19 | 2022-08-02 | 中铁三局集团第二工程有限公司 | 岩溶发育地区深厚砂层大直径桩基施工方法 |
-
2023
- 2023-01-16 CN CN202310056633.3A patent/CN116397700B/zh active Active
Patent Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4624327A (en) * | 1984-10-16 | 1986-11-25 | Flowdril Corporation | Method for combined jet and mechanical drilling |
| US4624327B1 (zh) * | 1984-10-16 | 1990-08-21 | Flowdril Corp | |
| CN102409978A (zh) * | 2011-10-26 | 2012-04-11 | 中冶集团武汉勘察研究院有限公司 | 复杂地层灌注桩施工采用多级合金超前牙轮钻头回旋钻进成孔工法 |
| CN105862862A (zh) * | 2016-04-06 | 2016-08-17 | 广东省建筑工程机械施工有限公司 | 一种大直径桩埋锤打捞方法 |
| US20180340312A1 (en) * | 2017-05-25 | 2018-11-29 | Powerchina Huadong Engineering Corporation Limited | Offshore non-driven-in large-diameter monopile foundation structure and constryction method |
| CN107938676A (zh) * | 2017-11-21 | 2018-04-20 | 重庆建工市政交通工程有限责任公司 | 一种穿越全填充型溶洞的桩基施工方法 |
| WO2021082767A1 (zh) * | 2019-10-31 | 2021-05-06 | 国家电网有限公司 | 一种基于增强纤维和偏高岭土的加压灌注桩的施工方法 |
| AU2020101426A4 (en) * | 2020-06-17 | 2020-08-20 | Hebei Research Institute of Construction & Geotechnical Investigation Co., Ltd. | Anti-Deviation Rotary Drilling Tool for Karst Stratum and Drilling Method Thereof |
| CN114837209A (zh) * | 2022-05-19 | 2022-08-02 | 中铁三局集团第二工程有限公司 | 岩溶发育地区深厚砂层大直径桩基施工方法 |
Non-Patent Citations (2)
| Title |
|---|
| 梅华国: "冲孔灌注桩施工中埋锤或卡锤事故的处理措施", 电力建设, no. 03, 20 March 2004 (2004-03-20), pages 39 - 40 * |
| 骆宏勋;: "不良地质条件下深水大直径桩基综合施工技术", 公路工程, no. 03, 20 June 2011 (2011-06-20), pages 131 - 136 * |
Also Published As
| Publication number | Publication date |
|---|---|
| CN116397700B (zh) | 2025-06-03 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106988302B (zh) | 一种大倾角坚硬岩层旋挖桩施工工法 | |
| CN110735432B (zh) | 盾构过侵限隧道范围内桩基清除及参数控制方法 | |
| CN101812843A (zh) | 中心灌注后压浆桩施工方法及其使用的灌注器和注浆器 | |
| CN115341533B (zh) | 一种易塌地层灌注桩钻孔施工方法 | |
| CN103993598A (zh) | 一种引孔植入布袋碎石注浆桩及施工方法 | |
| CN114517472A (zh) | 一种载体桩的施工方法 | |
| CN108775036A (zh) | 一种更换灌注桩的施工方法 | |
| CN103485344A (zh) | 一种拔除建筑工程桩基的方法 | |
| CN101691760B (zh) | 一种锚杆联合掏挖复合基础及其施工方法 | |
| CN105862862B (zh) | 一种大直径桩埋锤打捞方法 | |
| CN115538422A (zh) | 串珠式溶洞与厚砂砾覆盖层连通的钻孔灌注桩施工工法 | |
| CN109208594B (zh) | 钢护筒下沉遇孤石的处理方法、钢护筒结构及钻孔桩 | |
| CN106948347A (zh) | 拔桩方法及拔桩系统 | |
| CN111287177A (zh) | 密实卵石层地区大直径超长冲孔灌注桩施工方法 | |
| CN106968252B (zh) | 拔桩回灌方法及拔桩回灌系统 | |
| CN116397700A (zh) | 一种冲孔长桩卡锤后埋锤施工处理方法 | |
| CN203808055U (zh) | 螺纹旋后插筋挤密灌注桩 | |
| CN204326068U (zh) | 可回收外钢护筒的水中钻孔桩基础施工系统 | |
| CN218622226U (zh) | 一种组合式吊打锤击沉管灌注桩施工系统 | |
| CN111926821A (zh) | 一种新型护坡桩的施工工法 | |
| JP7630362B2 (ja) | ケーソン工法 | |
| CN111519617A (zh) | 一种全套管液压锤击挤土灌注桩装置及其施工方法 | |
| CN206902712U (zh) | 拔桩回灌系统 | |
| CN116804324A (zh) | 一种基于素砼桩的软土地基加固方法 | |
| CN207004431U (zh) | 软土地基激振打井装置 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |