[go: up one dir, main page]

CN116316779A - Configuration method and device of flexible power transformer - Google Patents

Configuration method and device of flexible power transformer Download PDF

Info

Publication number
CN116316779A
CN116316779A CN202310271987.XA CN202310271987A CN116316779A CN 116316779 A CN116316779 A CN 116316779A CN 202310271987 A CN202310271987 A CN 202310271987A CN 116316779 A CN116316779 A CN 116316779A
Authority
CN
China
Prior art keywords
new energy
flexible power
power transformer
station
short
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310271987.XA
Other languages
Chinese (zh)
Inventor
刘瑛琳
谢欢
赵天骐
李奇
王泽森
赵志宇
李善颖
夏雪
辛光明
曹天植
张思琪
陈瑞
黄天啸
刘苗
李�雨
林一凡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
North China Electric Power Research Institute Co Ltd
State Grid Corp of China SGCC
Original Assignee
North China Electric Power Research Institute Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by North China Electric Power Research Institute Co Ltd, State Grid Corp of China SGCC filed Critical North China Electric Power Research Institute Co Ltd
Priority to CN202310271987.XA priority Critical patent/CN116316779A/en
Publication of CN116316779A publication Critical patent/CN116316779A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for AC mains or AC distribution networks
    • H02J3/36Arrangements for transfer of electric power between AC networks via a high-tension DC link
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for AC mains or AC distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/381Dispersed generators
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for AC mains or AC distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/46Controlling of the sharing of output between the generators, converters, or transformers
    • H02J3/466Scheduling the operation of the generators, e.g. connecting or disconnecting generators to meet a given demand
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2300/00Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
    • H02J2300/20The dispersed energy generation being of renewable origin
    • H02J2300/22The renewable source being solar energy
    • H02J2300/24The renewable source being solar energy of photovoltaic origin
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2300/00Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
    • H02J2300/20The dispersed energy generation being of renewable origin
    • H02J2300/28The renewable source being wind energy
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2300/00Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
    • H02J2300/40Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation wherein a plurality of decentralised, dispersed or local energy generation technologies are operated simultaneously

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a configuration method and a device of a flexible power transformer, and relates to the technical field of power systems, wherein the method comprises the following steps: after determining that the power system is suitable for configuring a flexible power transformer according to the collected power system data, calculating the short-circuit ratio of each new energy multi-station; for each new energy station with the new energy multi-station short-circuit ratio not greater than a first preset threshold value: sequentially accessing the flexible power transformers according to the sequence from small to large of the flexible power transformers, recalculating the short-circuit ratio of the new energy multi-station, and determining configuration parameters of the new energy multi-station accessing the flexible power transformers when the recalculated short-circuit ratio of the new energy multi-station is larger than a first preset threshold value; and screening the configuration parameters of the flexible power transformer accessed to each new energy station by utilizing the overcurrent threshold and the withstand voltage threshold to obtain the configuration parameters of the flexible power transformer of the power system. The invention can deploy a proper flexible power transformer for the power system and improve the new energy output capability.

Description

柔性电力变压器的配置方法及装置Configuration method and device of flexible power transformer

技术领域technical field

本发明涉及电力系统技术领域,尤其涉及一种柔性电力变压器的配置方法及装置。The invention relates to the technical field of power systems, in particular to a configuration method and device for a flexible power transformer.

背景技术Background technique

本部分旨在为权利要求书中陈述的本发明实施例提供背景或上下文。此处的描述不因为包括在本部分中就承认是现有技术。This section is intended to provide a background or context to embodiments of the invention that are recited in the claims. The descriptions herein are not admitted to be prior art by inclusion in this section.

随着大规模新能源接入电网、特高压交直流输电工程相继投产以及常规火电机组逐步退出,电网形态发生了深刻变化,电网调压和潮流控制难度日益加大。在暂态方面,大规模新能源通过交直流远距离输电,电网故障下,近区动态无功支撑能力不足,故障后,新能源机端暂态过电压过高,可能引起过电压保护动作脱网,从而进一步加剧电压升高,最终导致大规模风电机组、光伏连锁脱网。在稳态方面,受大量新能源接入末端变电站影响,当新能源场站外送的功率较大时,容易引起低电压的问题,多个变电站的电压波动率多次超标,严重影响地区供电质量。因此,新能源出力的波动性、新能源对常规电源的大规模替代,电网结构的变化等引起的功率和电压快速频繁变化,高/低电压越限等情况,限制了电网对新能源的消纳能力,亟需提高电网的运行调节能力。With the integration of large-scale new energy into the power grid, the successive commissioning of UHV AC and DC transmission projects, and the gradual withdrawal of conventional thermal power units, the form of the power grid has undergone profound changes, and the difficulty of power grid voltage regulation and power flow control has become increasingly difficult. In terms of transient state, large-scale new energy transmits power through long-distance AC and DC. When the power grid fails, the dynamic reactive power support capacity in the near area is insufficient. grid, thus further aggravating the voltage rise, and eventually leading to large-scale wind turbines and photovoltaic chains going off-grid. In terms of steady state, due to the influence of a large number of new energy sources connected to terminal substations, when the power sent out by new energy stations is large, it is easy to cause low voltage problems. The voltage fluctuation rate of multiple substations has repeatedly exceeded the standard, which seriously affects the regional power supply. quality. Therefore, the fluctuation of new energy output, the large-scale replacement of conventional power by new energy, the rapid and frequent changes in power and voltage caused by changes in the grid structure, and the high/low voltage limit, etc., limit the consumption of new energy by the grid. Therefore, there is an urgent need to improve the operation regulation capacity of the power grid.

柔性电力变压器因结合电力电子技术与常规电磁变压器优势,可以用较小容量的换流器实现电力变压器电压的快速连续、精确调节,提升新型电力系统对新能源的消纳能力,保证电网的可靠运行。因此有必要提出一种适用于新能源场站侧的柔性电力变压器配置方法。Due to the combination of power electronics technology and the advantages of conventional electromagnetic transformers, flexible power transformers can use small-capacity converters to realize rapid, continuous and precise adjustment of power transformer voltages, improve the ability of new power systems to absorb new energy, and ensure the reliability of power grids run. Therefore, it is necessary to propose a flexible power transformer configuration method suitable for the new energy station side.

目前,国内外对柔性电力变压器的研究基本围绕着简化电路进行原理分析,对测试样机相关研制也较少,为了更好的解决电力系统中发生的低电压和过电压问题,需要提出一种柔性电力变压器的配置方法来根据应用场景和需求分析来部署合适的柔性电力变压器。At present, the research on flexible power transformers at home and abroad basically focuses on the principle analysis of simplified circuits, and there are few related developments on test prototypes. In order to better solve the problems of low voltage and overvoltage in power systems, it is necessary to propose a flexible The configuration method of power transformers is used to deploy suitable flexible power transformers according to application scenarios and demand analysis.

发明内容Contents of the invention

本发明实施例提供一种柔性电力变压器的配置方法,用以在规划设计阶段确定合适的柔性电力变压器配置参数,为电力系统部署合适的柔性电力变压器,提升新能源送出能力,提高电网运行调节能力,该方法包括:The embodiment of the present invention provides a flexible power transformer configuration method, which is used to determine the appropriate flexible power transformer configuration parameters in the planning and design stage, deploy a suitable flexible power transformer for the power system, improve the ability to send out new energy, and improve the operation and regulation ability of the power grid , the method includes:

收集电力系统数据;所述电力系统数据包括电力系统的短路容量、电力系统中多个新能源场站的装机容量;Collect power system data; the power system data includes the short-circuit capacity of the power system and the installed capacity of multiple new energy stations in the power system;

根据电力系统的短路容量、电力系统中多个新能源场站的装机容量,确定电力系统适合配置柔性电力变压器后,计算电力系统中每个新能源场站的新能源多场站短路比;According to the short-circuit capacity of the power system and the installed capacity of multiple new energy stations in the power system, after determining that the power system is suitable for configuring flexible power transformers, calculate the new energy multi-site short-circuit ratio of each new energy station in the power system;

对新能源多场站短路比不大于第一预设阈值的每一新能源场站:按照柔性电力变压器容量从小到大的顺序,依次接入柔性电力变压器,在每次接入柔性电力变压器后重新计算新能源场站的新能源多场站短路比,当重新计算的新能源场站的新能源多场站短路比大于第一预设阈值,确定新能源场站接入柔性电力变压器的配置参数;所述配置参数包括柔性电力变压器的型号和接入位置;For each new energy station whose short-circuit ratio is not greater than the first preset threshold: according to the order of the capacity of the flexible power transformer from small to large, connect the flexible power transformer in turn, after connecting the flexible power transformer each time Recalculate the new energy multi-station short-circuit ratio of the new energy station, and when the recalculated new energy multi-station short-circuit ratio of the new energy station is greater than the first preset threshold, determine the configuration of the new energy station connected to the flexible power transformer parameters; the configuration parameters include the type and access position of the flexible power transformer;

利用柔性电力变压器的过流阈值和耐压阈值,对各新能源场站接入柔性电力变压器的配置参数进行筛选,得到电力系统的柔性电力变压器的配置参数。Using the overcurrent threshold and withstand voltage threshold of the flexible power transformer, the configuration parameters of the flexible power transformer connected to each new energy station are screened to obtain the configuration parameters of the flexible power transformer in the power system.

本发明实施例还提供一种柔性电力变压器的配置装置,用以在规划设计阶段确定合适的柔性电力变压器配置参数,为电力系统部署合适的柔性电力变压器,提升新能源送出能力,提高电网运行调节能力,该装置包括:The embodiment of the present invention also provides a flexible power transformer configuration device, which is used to determine the appropriate flexible power transformer configuration parameters in the planning and design stage, deploy a suitable flexible power transformer for the power system, improve the ability to send new energy, and improve the operation and regulation of the power grid capabilities, the device includes:

数据收集模块,用于收集电力系统数据;所述电力系统数据包括电力系统的短路容量、电力系统中多个新能源场站的装机容量;The data collection module is used to collect power system data; the power system data includes the short-circuit capacity of the power system and the installed capacity of multiple new energy stations in the power system;

配置准备模块,用于根据电力系统的短路容量、电力系统中多个新能源场站的装机容量,确定电力系统适合配置柔性电力变压器后,计算电力系统中每个新能源场站的新能源多场站短路比;The configuration preparation module is used to calculate the new energy capacity of each new energy station in the power system after determining that the power system is suitable for configuring flexible power transformers according to the short-circuit capacity of the power system and the installed capacity of multiple new energy stations in the power system. Station short circuit ratio;

柔性电力变压器配置确定模块,用于对新能源多场站短路比不大于第一预设阈值的每一新能源场站:按照柔性电力变压器容量从小到大的顺序,依次接入柔性电力变压器,在每次接入柔性电力变压器后重新计算新能源场站的新能源多场站短路比,当重新计算的新能源场站的新能源多场站短路比大于第一预设阈值,确定新能源场站接入柔性电力变压器的配置参数;所述配置参数包括柔性电力变压器的型号和接入位置;The flexible power transformer configuration determination module is used for each new energy station whose short-circuit ratio of new energy multi-site stations is not greater than the first preset threshold: connect the flexible power transformers sequentially according to the order of the capacity of the flexible power transformers from small to large, Recalculate the new energy multi-station short-circuit ratio of the new energy station every time the flexible power transformer is connected. When the recalculated new energy multi-station short-circuit ratio of the new energy station is greater than the first preset threshold, determine the new energy The configuration parameters of the station access to the flexible power transformer; the configuration parameters include the type and access location of the flexible power transformer;

柔性电力变压器配置筛选模块,用于利用柔性电力变压器的过流阈值和耐压阈值,对各新能源场站接入柔性电力变压器的配置参数进行筛选,得到电力系统的柔性电力变压器的配置参数。The flexible power transformer configuration screening module is used to screen the configuration parameters of each new energy station connected to the flexible power transformer by using the overcurrent threshold and withstand voltage threshold of the flexible power transformer, and obtain the configuration parameters of the flexible power transformer of the power system.

本发明实施例还提供一种计算机设备,包括存储器、处理器及存储在存储器上并可在处理器上运行的计算机程序,所述处理器执行所述计算机程序时实现上述柔性电力变压器的配置方法。The embodiment of the present invention also provides a computer device, including a memory, a processor, and a computer program stored on the memory and operable on the processor, and the processor implements the configuration method of the above-mentioned flexible power transformer when executing the computer program .

本发明实施例还提供一种计算机可读存储介质,所述计算机可读存储介质存储有计算机程序,所述计算机程序被处理器执行时实现上述柔性电力变压器的配置方法。The embodiment of the present invention also provides a computer-readable storage medium, the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the above-mentioned method for configuring the flexible power transformer is implemented.

本发明实施例还提供一种计算机程序产品,所述计算机程序产品包括计算机程序,所述计算机程序被处理器执行时实现上述柔性电力变压器的配置方法。The embodiment of the present invention also provides a computer program product, the computer program product includes a computer program, and when the computer program is executed by a processor, the above-mentioned method for configuring the flexible power transformer is realized.

本发明实施例中,首先收集电力系统数据,利用电力系统数据中电力系统的短路容量、电力系统中多个新能源场站的装机容量判断电力系统是否适合配置柔性电力变压器;当确定电力系统适合配置柔性电力变压器,计算各新能源多场站短路比;当新能源多场站短路比符合条件,即小于或等于第一预设阈值时,为该新能源场站接入柔性电力变压器;在选择要接入新能源场站的柔性电力变压器时,按照柔性电力变压器容量从小到大的顺序依次接入,在每次接入柔性电力变压器后重新计算新能源场站的新能源多场站短路比,当重新计算的新能源场站的新能源多场站短路比大于第一预设阈值,确定新能源场站接入柔性电力变压器的配置参数;最后利用柔性电力变压器的过流阈值和耐压阈值,对各新能源场站接入柔性电力变压器的配置参数进行筛选,得到电力系统的柔性电力变压器的配置参数,从而得到电力系统的柔性电力变压器的配置方案。本发明实施例实现了通过新能源多场站短路比确定接入柔性电力变压器的配置参数,并通过柔性电力变压器的过流阈值和耐压阈值对配置参数进行筛选,可在规划设计阶段为新能源场站部署合适的柔性电力变压器,提升了新能源送出能力,提高了电网运行调节能力。In the embodiment of the present invention, the power system data is first collected, and the short-circuit capacity of the power system in the power system data and the installed capacity of multiple new energy stations in the power system are used to judge whether the power system is suitable for configuring flexible power transformers; when it is determined that the power system is suitable for Configure flexible power transformers to calculate the short-circuit ratio of each new energy multi-site station; when the new energy multi-site short-circuit ratio meets the conditions, that is, when it is less than or equal to the first preset threshold, connect the flexible power transformer to the new energy station; When selecting the flexible power transformer to be connected to the new energy station, connect it in order according to the capacity of the flexible power transformer from small to large, and recalculate the new energy multi-site short circuit of the new energy station after each connection of the flexible power transformer ratio, when the recalculated new energy multi-station short-circuit ratio of the new energy station is greater than the first preset threshold, determine the configuration parameters of the new energy station connected to the flexible power transformer; finally use the overcurrent threshold and the withstand voltage of the flexible power transformer The voltage threshold value is used to screen the configuration parameters of the flexible power transformers connected to each new energy station to obtain the configuration parameters of the flexible power transformers of the power system, thereby obtaining the configuration scheme of the flexible power transformers of the power system. The embodiment of the present invention realizes the determination of the configuration parameters of the connected flexible power transformer through the short circuit ratio of new energy multi-site stations, and screens the configuration parameters through the overcurrent threshold and withstand voltage threshold of the flexible power transformer, which can be used in the planning and design stage for new Deploying suitable flexible power transformers in energy stations has improved the ability to send new energy and improve the ability to regulate grid operation.

附图说明Description of drawings

为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。在附图中:In order to more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the following will briefly introduce the drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description are only These are some embodiments of the present invention. Those skilled in the art can also obtain other drawings based on these drawings without creative work. In the attached picture:

图1为本发明实施例中柔性电力变压器的配置方法的流程示意图;Fig. 1 is a schematic flow chart of a method for configuring a flexible power transformer in an embodiment of the present invention;

图2为本发明实施例中大规模新能源经交流输电线路送出拓扑图;Fig. 2 is a topological diagram of sending large-scale new energy through an AC transmission line in an embodiment of the present invention;

图3为本发明实施例中接入柔性电力变压器的电力系统示意图;3 is a schematic diagram of a power system connected to a flexible power transformer in an embodiment of the present invention;

图4为本发明实施例中柔性电力变压器的配置方法的一具体实例图;Fig. 4 is a specific example diagram of the configuration method of the flexible power transformer in the embodiment of the present invention;

图5为本发明实施例中柔性电力变压器的配置装置的示意图。Fig. 5 is a schematic diagram of a configuration device of a flexible power transformer in an embodiment of the present invention.

具体实施方式Detailed ways

为使本发明实施例的目的、技术方案和优点更加清楚明白,下面结合附图对本发明实施例做进一步详细说明。在此,本发明的示意性实施例及其说明用于解释本发明,但并不作为对本发明的限定。In order to make the purpose, technical solutions and advantages of the embodiments of the present invention more clear, the embodiments of the present invention will be further described in detail below in conjunction with the accompanying drawings. Here, the exemplary embodiments and descriptions of the present invention are used to explain the present invention, but not to limit the present invention.

首先对本发明实施例涉及的技术名词进行解释说明。First, technical terms involved in the embodiments of the present invention are explained.

柔性电力变压器:将电力电子有源部分与常规电磁变压器相结合,实现交流电力变压器电压的快速、连续、精确调节,提升新型电力系统对新能源的消纳能力,保证电网的可靠运行。一般配网电压等级的柔性电力变压器采用带补偿绕组的三绕组电力变压器和电压源型逆变器组成,电压源型逆变器与电力变压器的补偿绕组联结,在运行时为负荷提供连续可调的电压调节服务。应用在高电压等级的柔性电力变压器一般采用在变压器与新能源场站相联的绕组中性点侧串接进一个串联变压器,然后将串联变压器的二次侧与电压源型逆变器相联,在运行时通过电压源型逆变器和串联变压器为电力变压器的一次绕组提供幅值和方向可控的电压分量,改善新能源场站的并网电压。Flexible power transformer: Combining the active part of power electronics with a conventional electromagnetic transformer to realize rapid, continuous and precise adjustment of the voltage of the AC power transformer, improve the ability of the new power system to absorb new energy, and ensure the reliable operation of the power grid. The flexible power transformer of the general distribution network voltage level is composed of a three-winding power transformer with compensation winding and a voltage source inverter. voltage regulation service. Flexible power transformers used at high voltage levels generally use a series transformer connected in series on the neutral point side of the winding that connects the transformer to the new energy station, and then connect the secondary side of the series transformer to the voltage source inverter , during operation, the voltage source inverter and series transformer provide voltage components with controllable amplitude and direction for the primary winding of the power transformer, so as to improve the grid-connected voltage of the new energy station.

新能源多场站短路比:可以反映新能源并网点的电压支撑强度,有效指导电网和新能源的发展运行。新能源发电单元升压变低压侧的多场站短路比不应低于1.5,且新能源并网点的多场站短路比不应低于2.0、宜高于3.0。New energy multi-station short-circuit ratio: It can reflect the voltage support strength of new energy grid-connected points, and effectively guide the development and operation of power grids and new energy. The multi-site short-circuit ratio of the step-up transformer low-voltage side of the new energy power generation unit should not be lower than 1.5, and the multi-site short-circuit ratio of the new energy grid-connected point should not be lower than 2.0, preferably higher than 3.0.

申请人发现,柔性电力变压器因结合电力电子技术与常规电磁变压器优势,可以用较小容量的换流器实现电力变压器电压的快速连续、精确调节,提升新型电力系统对新能源的消纳能力,保证电网的可靠运行,因此有必要提出一种适用于新能源场站侧的柔性电力变压器配置方法。然而,国内外对柔性电力变压器的研究基本围绕着简化电路进行原理分析,对测试样机相关研制较少,为了更好的解决电力系统中发生的低电压和过电压问题,需要提出一种柔性电力变压器的配置方法来根据应用场景和需求分析来部署合适的柔性电力变压器。为此申请人提出了一种柔性电力变压器的配置方法。The applicant found that due to the combination of power electronics technology and the advantages of conventional electromagnetic transformers, the flexible power transformer can use a small-capacity converter to realize rapid, continuous and precise adjustment of the power transformer voltage, and improve the ability of the new power system to absorb new energy. To ensure the reliable operation of the power grid, it is necessary to propose a flexible power transformer configuration method suitable for the new energy station side. However, the research on flexible power transformers at home and abroad is basically based on the principle analysis of simplified circuits, and there are few related developments on test prototypes. In order to better solve the problems of low voltage and overvoltage in power systems, it is necessary to propose a flexible power transformer. Transformer configuration methods to deploy suitable flexible power transformers according to application scenarios and demand analysis. For this reason, the applicant proposes a method for configuring a flexible power transformer.

图1为本发明实施例中柔性电力变压器的配置方法的流程示意图,如图1所示,该方法包括:Fig. 1 is a schematic flowchart of a method for configuring a flexible power transformer in an embodiment of the present invention. As shown in Fig. 1, the method includes:

步骤101、收集电力系统数据;所述电力系统数据包括电力系统的短路容量、电力系统中多个新能源场站的装机容量;Step 101, collecting power system data; the power system data includes the short-circuit capacity of the power system and the installed capacity of multiple new energy stations in the power system;

步骤102、根据电力系统的短路容量、电力系统中多个新能源场站的装机容量,确定电力系统适合配置柔性电力变压器后,计算电力系统中每个新能源场站的新能源多场站短路比;Step 102. According to the short-circuit capacity of the power system and the installed capacity of multiple new energy stations in the power system, after determining that the power system is suitable for configuring flexible power transformers, calculate the new energy multi-site short circuit of each new energy station in the power system Compare;

步骤103、对新能源多场站短路比不大于第一预设阈值的每一新能源场站:按照柔性电力变压器容量从小到大的顺序,依次接入柔性电力变压器,在每次接入柔性电力变压器后重新计算新能源场站的新能源多场站短路比,当重新计算的新能源场站的新能源多场站短路比大于第一预设阈值,确定新能源场站接入柔性电力变压器的配置参数;Step 103. For each new energy station whose short-circuit ratio is not greater than the first preset threshold: according to the order of the capacity of the flexible power transformer from small to large, connect the flexible power transformer in sequence, and connect the flexible power transformer each time. After the power transformer, recalculate the new energy multi-station short-circuit ratio of the new energy station. When the recalculated new energy multi-station short-circuit ratio of the new energy station is greater than the first preset threshold, it is determined that the new energy station is connected to flexible power. Transformer configuration parameters;

步骤104、利用柔性电力变压器的过流阈值和耐压阈值,对各新能源场站接入柔性电力变压器的配置参数进行筛选,得到电力系统的柔性电力变压器的配置参数。Step 104: Use the overcurrent threshold and withstand voltage threshold of the flexible power transformer to screen the configuration parameters of each new energy station connected to the flexible power transformer to obtain the configuration parameters of the flexible power transformer in the power system.

从图1所示流程可以看出,本发明实施例实现了通过新能源多场站短路比确定接入柔性电力变压器的配置参数,并通过柔性电力变压器的过流阈值和耐压阈值对配置参数进行筛选,可在规划设计阶段为新能源场站部署合适的柔性电力变压器,提升了新能源送出能力,提高了电网运行调节能力。It can be seen from the process shown in Figure 1 that the embodiment of the present invention realizes the determination of the configuration parameters of the connected flexible power transformer through the short-circuit ratio of new energy multi-site stations, and configures the parameters through the overcurrent threshold and withstand voltage threshold of the flexible power transformer Through screening, suitable flexible power transformers can be deployed for new energy stations in the planning and design stage, which improves the ability to send new energy and improve the ability to regulate grid operation.

下面对本发明实施例进行详细解释。The embodiments of the present invention are explained in detail below.

首先收集电力系统数据。图2为本发明实施例中大规模新能源经交流输电线路送出拓扑图,如图2所示,电力系统包括多个新能源场站,图2中虚线框位置为新能源场站,多个新能源场站可构成新能源等效系统,所述电力系统数据包括电力系统的短路容量Sac、电力系统中多个新能源场站的装机容量的集合S={S1,S2,...,Sm}、电力系统的阻抗矩阵Z、各新能源场站输入电网的有功功率集合P={P1,P2,...,Pm}、各新能源场站输出侧电压集合U={U1,U2,...,Um},其中,m表示电力系统中新能源场站个数,Sm、Pm、Um分别为第m个新能源场站的装机容量、输入电网的有功功率、输出侧电压。另外可以提前获取待接入新能源场站的柔性电力变压器的型号及其参数。需要说明的是,电力系统数据不仅限于以上数据,在此不做限定,仅作示例。Start by collecting power system data. Fig. 2 is a topological diagram of large-scale new energy sent through AC transmission lines in the embodiment of the present invention. As shown in Fig. 2, the power system includes multiple new energy stations. New energy stations can constitute a new energy equivalent system. The power system data includes the short-circuit capacity S ac of the power system, the set of installed capacities of multiple new energy stations in the power system S={S 1 ,S 2 ,. ..,S m }, the impedance matrix Z of the power system, the active power set P={P 1 ,P 2 ,...,P m } of each new energy station input to the grid, and the output side voltage of each new energy station Set U={U 1 , U 2 ,...,U m }, where m represents the number of new energy stations in the power system, S m , P m , and U m are the Installed capacity, active power input to the grid, and output side voltage. In addition, the model and parameters of the flexible power transformer to be connected to the new energy station can be obtained in advance. It should be noted that the power system data is not limited to the above data, which is not limited here and is only used as an example.

然后,根据收集的电力系统数据,判断该电力系统是否适合配置柔性电力变压器。实施时,可以根据电力系统短路比判断该电力系统是否适合配置柔性电力变压器。Then, according to the collected power system data, it is judged whether the power system is suitable for configuring flexible power transformers. During implementation, it can be judged whether the power system is suitable for configuring flexible power transformers according to the short-circuit ratio of the power system.

在一个实施例中,步骤102中根据电力系统的短路容量、电力系统中多个新能源场站的装机容量,确定电力系统适合配置柔性电力变压器,可以包括:In one embodiment, in step 102, according to the short-circuit capacity of the power system and the installed capacity of multiple new energy stations in the power system, it is determined that the power system is suitable for configuring a flexible power transformer, which may include:

根据电力系统的短路容量、电力系统中多个新能源场站的装机容量,计算电力系统短路比;当电力系统短路比小于或等于第二预设阈值,确定电力系统适合配置柔性电力变压器。According to the short-circuit capacity of the power system and the installed capacity of multiple new energy stations in the power system, the short-circuit ratio of the power system is calculated; when the short-circuit ratio of the power system is less than or equal to the second preset threshold, it is determined that the power system is suitable for configuring flexible power transformers.

具体实施时,第一步,参照图2,按如下公式根据电力系统的短路容量Sac、电力系统中多个新能源场站的装机容量的集合S,计算电力系统短路比SCR:In the specific implementation, the first step, referring to Fig. 2, calculates the short-circuit ratio SCR of the power system according to the following formula according to the short-circuit capacity S ac of the power system and the set S of installed capacities of multiple new energy stations in the power system:

Figure BDA0004135065630000061
Figure BDA0004135065630000061

Figure BDA0004135065630000062
Figure BDA0004135065630000062

上式中,电力系统的短路容量

Figure BDA0004135065630000063
Sg为新能源等效额定容量,其中U0为新能源场站并网点处的电压,Z0为新能源场站并网点处的阻抗。In the above formula, the short-circuit capacity of the power system
Figure BDA0004135065630000063
S g is the equivalent rated capacity of new energy, where U 0 is the voltage at the grid connection point of the new energy station, and Z 0 is the impedance at the grid connection point of the new energy station.

第二步,将电力系统短路比SCR与第二预设阈值SCR0进行比较,该第二预设阈值SCR0用于表征电力系统的强弱性,可以设置为2.0至3.0,优选为3.0。当电力系统短路比SCR大于或等于第二预设阈值SCR0,表明该电力系统为较强或强系统,那么确定该电力系统不适合配置柔性电力变压器;当电力系统短路比SCR小于第二预设阈值SCR0,表明该电力系统为弱系统,那么确定该电力系统适合配置柔性电力变压器。本例中,在为电力系统配置柔性电力变压器前,先进行是否适合配置柔性电力变压器的判断,可以提高电力系统中柔性电力变压器的部署效率。In the second step, the power system short circuit ratio SCR is compared with a second preset threshold SCR 0 , which is used to characterize the strength of the power system and can be set to 2.0 to 3.0, preferably 3.0. When the power system short-circuit ratio SCR is greater than or equal to the second preset threshold SCR 0 , indicating that the power system is relatively strong or strong, then it is determined that the power system is not suitable for configuring flexible power transformers; when the power system short-circuit ratio SCR is less than the second preset The threshold SCR 0 is set to indicate that the power system is a weak system, so it is determined that the power system is suitable for configuring a flexible power transformer. In this example, before configuring the flexible power transformer for the power system, it is first judged whether it is suitable to configure the flexible power transformer, which can improve the deployment efficiency of the flexible power transformer in the power system.

当确定电力系统适合配置柔性电力变压器后,根据新能源多场站短路比确定合适的柔性电力变压器配置参数。When it is determined that the power system is suitable for configuring flexible power transformers, the appropriate flexible power transformer configuration parameters are determined according to the short-circuit ratio of new energy multi-site stations.

在一个实施例中,按如下公式计算新能源场站的新能源多场站短路比:In one embodiment, the new energy multi-station short-circuit ratio of the new energy station is calculated according to the following formula:

Figure BDA0004135065630000071
Figure BDA0004135065630000071

其中,MRSCRi为第i个新能源场站的新能源多场站短路比,Saci为第i个新能源场站处的系统短路容量;Pi为第i个新能源场站输入电网的有功功率,Pj为第j个新能源场站输入电网的有功功率,Zeqij为第i个新能源场站和第j个新能源场站之间的互阻抗,Zeqii为第i个新能源场站的自阻抗,n为新能源场站的个数,j为整数。Among them, MRSCR i is the new energy multi-station short-circuit ratio of the i-th new energy station, S aci is the system short-circuit capacity at the i-th new energy station; P i is the input power of the i-th new energy station Active power, P j is the active power of the j-th new energy station input to the grid, Z eqij is the mutual impedance between the i-th new energy station and the j-th new energy station, Z eqii is the i-th new energy station The self-impedance of the energy station, n is the number of new energy stations, and j is an integer.

实施时,对电力系统中每个新能源场站计算新能源多场站短路比,将每个新能源场站的新能源多场站短路比与第一预设阈值进行比较;当一新能源场站的新能源多场站短路比大于第一预设阈值时,认为电力系统可对新能源快速消纳,电网运行可靠,此时无需为该新能源场站配置柔性电力变压器;若某一新能源场站的新能源多场站短路比小于或等于第一预设阈值时,认为电网运行调节能力、对新能源的消纳能力还有待提高,此时需要为该新能源场站配置柔性电力变压器。其中,该第一预设阈值可以设置为1.5至2.5,优选为1.5。During implementation, calculate the new energy multi-station short-circuit ratio for each new energy station in the power system, and compare the new energy multi-station short-circuit ratio of each new energy station with the first preset threshold; when a new energy When the new energy multi-station short-circuit ratio of the station is greater than the first preset threshold, it is considered that the power system can quickly absorb new energy and the power grid operates reliably. At this time, there is no need to configure a flexible power transformer for the new energy station; if a When the new energy multi-station short-circuit ratio of the new energy station is less than or equal to the first preset threshold, it is considered that the grid operation adjustment capability and the ability to absorb new energy need to be improved. At this time, it is necessary to configure flexible power transformer. Wherein, the first preset threshold can be set to 1.5 to 2.5, preferably 1.5.

在规划阶段选择接入新能源场站的柔性电力变压器时,根据已有的柔性电力变压器资料,可知柔性电力变压器的型号、容量等参数,为电力系统选择合适的接入新能源场站的备选柔性电力变压器,需要说明的是,型号不一致的柔性电力变压器,其容量可能是一致的。When selecting the flexible power transformer connected to the new energy station in the planning stage, according to the existing flexible power transformer data, the parameters such as the model and capacity of the flexible power transformer can be known, and the appropriate backup for the power system to be connected to the new energy station can be selected. When choosing a flexible power transformer, it should be noted that the capacities of flexible power transformers with inconsistent models may be the same.

具体实施时,对新能源多场站短路比不大于第一预设阈值的每一新能源场站:按照柔性电力变压器容量从小到大的顺序,依次接入柔性电力变压器,在每次接入柔性电力变压器后重新计算新能源场站的新能源多场站短路比,当重新计算的新能源场站的新能源多场站短路比大于第一预设阈值,认定此时新能源场站的电网运行调节能力精确、反应快速,运行可靠,则判断此时接入的柔性电力变压器合适,进而确定新能源场站接入该柔性电力变压器的配置参数。During specific implementation, for each new energy station whose short-circuit ratio is not greater than the first preset threshold value: according to the order of the capacity of the flexible power transformer from small to large, the flexible power transformer is connected in turn, and each time it is connected After the flexible power transformer recalculates the new energy multi-station short-circuit ratio of the new energy station, when the recalculated new energy multi-station short-circuit ratio of the new energy station is greater than the first preset threshold, it is determined that the new energy station at this time If the power grid operation adjustment ability is accurate, the response is fast, and the operation is reliable, it is judged that the flexible power transformer connected at this time is suitable, and then the configuration parameters of the new energy station connected to the flexible power transformer are determined.

图3为本发明实施例中接入柔性电力变压器的电力系统示意图,图3中大的虚线框为柔性电力变压器,柔性电力变压器由带补偿绕组的三绕组电力变压器(小的虚线框)和电压源型逆变器组成。对每个需要接入柔性电力变压器的新能源场站按照同样的方式部署,可以得到各新能源场站接入柔性电力变压器的配置参数,该配置参数可以包括柔性电力变压器的型号、接入位置等信息。Fig. 3 is a schematic diagram of a power system connected to a flexible power transformer in an embodiment of the present invention. The large dotted frame in Fig. 3 is a flexible power transformer, and the flexible power transformer consists of a three-winding power transformer (small dotted frame) with a compensation winding and a voltage Composed of source inverters. For each new energy station that needs to be connected to a flexible power transformer, it is deployed in the same way, and the configuration parameters of each new energy station connected to the flexible power transformer can be obtained. The configuration parameters can include the model of the flexible power transformer and the location of the connection. and other information.

本发明实施例中柔性电力变压器的接入位置可以包括电压等级220/35kV、电压等级110/35kV、电压等级110/10kV、电压等级66/10kV等,具有较广的应用范围。不同的接入位置对柔性电力变压器开关管耐压水平、过流能力、过负荷能力、容量要求均不同,本发明实施例中可以在规划阶段选择合适的接入位置,能量化反映柔性电力变压器的开关管耐压水平、过流能力、过负荷能力等涉网特性。In the embodiment of the present invention, the connection positions of the flexible power transformer can include voltage levels of 220/35kV, 110/35kV, 110/10kV, 66/10kV, etc., which have a wide range of applications. Different access locations have different requirements for the withstand voltage level, overcurrent capability, overload capability, and capacity of the switching tube of the flexible power transformer. In the embodiment of the present invention, an appropriate access location can be selected in the planning stage, and the energy can reflect the flexible power transformer. The switching tube withstand voltage level, over-current capacity, overload capacity and other network-related characteristics.

得到各新能源场站接入柔性电力变压器的配置参数后,可以生成电力系统的柔性电力变压器的配置方案。但是,为了提高接入柔性电力变压器的可靠性,本发明实施例中,利用柔性电力变压器的过流阈值和耐压阈值,对各新能源场站接入柔性电力变压器的配置参数进行筛选,将不符合条件的柔性电力变压器去除,可以得到高可靠性的各新能源场站接入柔性电力变压器的配置参数,即得到高可靠性的电力系统的柔性电力变压器的配置参数,从而确定了最终的电力系统的柔性电力变压器的配置方案。After obtaining the configuration parameters of flexible power transformers connected to each new energy station, the configuration scheme of flexible power transformers in the power system can be generated. However, in order to improve the reliability of access to flexible power transformers, in the embodiment of the present invention, the overcurrent threshold and voltage withstand threshold of flexible power transformers are used to screen the configuration parameters of each new energy station connected to flexible power transformers, and the The flexible power transformers that do not meet the conditions can be removed, and the configuration parameters of the flexible power transformers connected to the new energy stations with high reliability can be obtained, that is, the configuration parameters of the flexible power transformers of the high-reliability power system can be obtained, thereby determining the final Configuration scheme of flexible power transformer for power system.

在一个实施例中,柔性电力变压器的过流阈值按如下公式得到:In one embodiment, the overcurrent threshold of the flexible power transformer is obtained according to the following formula:

Io=k1×IN I o =k 1 ×I N

其中,Io为柔性电力变压器的过流阈值,k1为过流系数,IN为柔性电力变压器的额定电流。Among them, I o is the over-current threshold of the flexible power transformer, k 1 is the over-current coefficient, and I N is the rated current of the flexible power transformer.

在一个实施例中,柔性电力变压器的耐压阈值按如下公式得到:In one embodiment, the withstand voltage threshold of the flexible power transformer is obtained according to the following formula:

ΔUo=(k2-1)×UN ΔU o =(k 2 -1)×U N

其中,ΔUo为柔性电力变压器的耐压阈值,k2为耐压系数,UN为柔性电力变压器的额定电压。Among them, ΔU o is the withstand voltage threshold of the flexible power transformer, k 2 is the withstand voltage coefficient, and U N is the rated voltage of the flexible power transformer.

为了提高接入柔性电力变压器的可靠性,在一个实施例中,利用柔性电力变压器的过流阈值和耐压阈值,对各新能源场站接入柔性电力变压器的配置参数进行筛选,得到电力系统的柔性电力变压器的配置参数,可以包括:In order to improve the reliability of connecting flexible power transformers, in one embodiment, the configuration parameters of each new energy station connected to flexible power transformers are screened by using the overcurrent threshold and withstand voltage threshold of flexible power transformers to obtain the power system The configuration parameters of the flexible power transformer can include:

计算每一新能源场站接入的柔性电力变压器的高压侧出口单相接地故障短路电流,当任一新能源场站接入的柔性电力变压器的高压侧出口单相接地故障短路电流大于柔性电力变压器的过流阈值,为该新能源场站去除该柔性电力变压器;Calculate the single-phase ground fault short-circuit current of the high-voltage side outlet of the flexible power transformer connected to each new energy station. When the single-phase ground fault short-circuit current of the high-voltage side outlet of the flexible power transformer connected to any new energy station is greater than the The overcurrent threshold of the transformer removes the flexible power transformer for the new energy station;

计算每一新能源场站接入的柔性电力变压器高压侧出口单相接地故障新能源机端过电压,当任一新能源场站接入的柔性电力变压器高压侧出口单相接地故障新能源机端过电压大于柔性电力变压器的耐压阈值,为该新能源场站去除该柔性电力变压器。Calculate the overvoltage of the new energy machine terminal with a single-phase ground fault at the outlet of the high-voltage side of the flexible power transformer connected to each new energy station. If the terminal overvoltage is greater than the withstand voltage threshold of the flexible power transformer, the flexible power transformer is removed for the new energy site.

实施时,新能源场站接入的柔性电力变压器的高压侧出口单相接地故障短路电流I按如下公式计算:During implementation, the single-phase ground fault short-circuit current I of the high-voltage side outlet of the flexible power transformer connected to the new energy station is calculated according to the following formula:

Figure BDA0004135065630000091
Figure BDA0004135065630000091

其中,

Figure BDA0004135065630000092
为型号为Ti的柔性电力变压器阻抗,/>
Figure BDA0004135065630000093
为与型号Ti的柔性电力变压器低压侧相连的线路Li的阻抗,Ui为第i个新能源场机端电压。in,
Figure BDA0004135065630000092
is the impedance of the flexible power transformer whose type is T i , />
Figure BDA0004135065630000093
is the impedance of the line L i connected to the low-voltage side of the flexible power transformer of type T i , and U i is the terminal voltage of the i-th new energy field.

实施时,新能源场站接入的柔性电力变压器高压侧出口单相接地故障新能源机端过电压ΔU按如下公式计算:During implementation, the overvoltage ΔU of the new energy machine terminal for single-phase ground fault at the high-voltage side outlet of the flexible power transformer connected to the new energy station is calculated according to the following formula:

Figure BDA0004135065630000094
Figure BDA0004135065630000094

其中,E为交流系统等值电势,UN为标称电压,MRSCRi为第i个新能源场站的新能源多场站短路比。Among them, E is the equivalent potential of the AC system, U N is the nominal voltage, and MRSCR i is the new energy multi-station short-circuit ratio of the i-th new energy station.

图4为本发明实施例中柔性电力变压器的配置方法的一具体实例图,如图4所示,该方法包括:Fig. 4 is a diagram of a specific example of the configuration method of the flexible power transformer in the embodiment of the present invention. As shown in Fig. 4, the method includes:

1、输入阻抗矩阵Z、新能源场站的装机容量的集合S={S1,S2,...,Sm}、各新能源场站输入电网的有功功率集合P={P1,P2,...,Pm}、各新能源场站输出侧电压(各节点)集合U={U1,U2,...,Um}、第一阈值SCR0、第二阈值MRSCR0、柔性电力变压器过流阈值Io、柔性电力变压器的耐压阈值ΔUo1. The input impedance matrix Z, the set of installed capacities of new energy stations S={S 1 ,S 2 ,...,S m }, the set of active power input to the power grid of each new energy station P={P 1 , P 2 ,...,P m }, output side voltage (each node) set of each new energy station U={U 1 ,U 2 ,...,U m }, first threshold SCR 0 , second threshold MRSCR 0 , flexible power transformer overcurrent threshold I o , flexible power transformer withstand voltage threshold ΔU o ;

2、计算电力系统短路比SCR;2. Calculate the short circuit ratio SCR of the power system;

3、当电力系统短路比SCR>SCR0,确定该电力系统不适合配置柔性电力变压器;3. When the power system short-circuit ratio SCR>SCR 0 , it is determined that the power system is not suitable for configuring flexible power transformers;

4、当电力系统短路比SCR≤SCR0,计算每个新能源场站的新能源多场站短路比MRSCR;4. When the power system short-circuit ratio SCR≤SCR 0 , calculate the new energy multi-station short-circuit ratio MRSCR for each new energy station;

5、将每个新能源场站的新能源多场站短路比MRSCR与第二阈值MRSCR0比较,MRSCR0优选为1.5,当MRSCR>MRSCR0,确定该新能源场站不适合配置柔性电力变压器;当MRSCR≤MRSCR0,为该新能源场站接入柔性电力变压器;5. Compare the new energy multi-station short-circuit ratio MRSCR of each new energy station with the second threshold MRSCR 0. MRSCR 0 is preferably 1.5. When MRSCR>MRSCR 0 , it is determined that the new energy station is not suitable for configuring flexible power transformers ; When MRSCR≤MRSCR 0 , connect the flexible power transformer to the new energy station;

6、重新计算接入柔性电力变压器的新能源场站的新能源多场站短路比,当接入柔性电力变压器的新能源场站的新能源多场站短路比大于MRSCR0,认为该柔性电力变压器接入适合,确定该新能源场站接入柔性电力变压器的配置参数;6. Recalculate the new energy multi-station short-circuit ratio of the new energy station connected to the flexible power transformer. When the new energy multi-station short-circuit ratio of the new energy station connected to the flexible power transformer is greater than MRSCR 0 , it is considered that the flexible power The transformer connection is suitable, and the configuration parameters of the flexible power transformer connected to the new energy station are determined;

7、计算每一新能源场站接入的柔性电力变压器的高压侧出口单相接地故障短路电流I,当任一新能源场站接入的柔性电力变压器的高压侧出口单相接地故障短路电流I大于柔性电力变压器的过流阈值Io,为该新能源场站去除该柔性电力变压器;7. Calculate the single-phase ground fault short-circuit current I of the high-voltage side outlet of the flexible power transformer connected to each new energy station. I is greater than the overcurrent threshold I o of the flexible power transformer, and the flexible power transformer is removed for the new energy station;

8、计算每一新能源场站接入的柔性电力变压器高压侧出口单相接地故障新能源机端过电压ΔU,当任一新能源场站接入的柔性电力变压器高压侧出口单相接地故障新能源机端过电压ΔU大于柔性电力变压器的耐压阈值ΔUo,为该新能源场站去除该柔性电力变压器;8. Calculate the single-phase grounding fault at the high-voltage side outlet of the flexible power transformer connected to each new energy station. The new energy machine terminal overvoltage ΔU, when any new energy station is connected to the flexible power transformer high-voltage side outlet single-phase grounding fault The overvoltage ΔU at the terminal of the new energy machine is greater than the withstand voltage threshold ΔU o of the flexible power transformer, and the flexible power transformer is removed for the new energy station;

9、根据筛选结果,确定最终的电力系统的柔性电力变压器的配置方案。9. According to the screening results, determine the configuration scheme of the flexible power transformer for the final power system.

综上,对于电力系统中的低电压和过电压问题,本发明实施例提供了一种应用场景和需求分析来配置合适的柔性电力变压器部署方案,该方案可以应用至柔直孤岛、微网、大规模新能源外送系统等场景,可以能量化反映柔性电力变压器的开关管耐压水平、过流能力、过负荷能力等涉网特性,提高电网的运行调节能力。In summary, for the low voltage and overvoltage problems in the power system, the embodiment of the present invention provides an application scenario and demand analysis to configure a suitable flexible power transformer deployment scheme, which can be applied to flexible islands, microgrids, Scenarios such as large-scale new energy external transmission systems can quantify and reflect the grid-related characteristics of flexible power transformers such as switch tube withstand voltage level, over-current capacity, and overload capacity, and improve the operation and regulation capabilities of the grid.

本发明实施例中还提供了一种柔性电力变压器的配置装置,如下面的实施例所述。由于该装置解决问题的原理与柔性电力变压器的配置方法相似,因此该装置的实施可以参见柔性电力变压器的配置方法的实施,重复之处不再赘述。Embodiments of the present invention also provide a device for configuring a flexible power transformer, as described in the following embodiments. Since the problem-solving principle of the device is similar to the configuration method of the flexible power transformer, the implementation of the device can refer to the implementation of the configuration method of the flexible power transformer, and the repetition will not be repeated.

图5为本发明实施例中柔性电力变压器的配置装置的示意图,如图5所示,该装置包括:Fig. 5 is a schematic diagram of a configuration device of a flexible power transformer in an embodiment of the present invention. As shown in Fig. 5, the device includes:

数据收集模块501,用于收集电力系统数据;所述电力系统数据包括电力系统的短路容量、电力系统中多个新能源场站的装机容量;The data collection module 501 is used to collect power system data; the power system data includes the short-circuit capacity of the power system and the installed capacity of multiple new energy stations in the power system;

配置准备模块502,用于根据电力系统的短路容量、电力系统中多个新能源场站的装机容量,确定电力系统适合配置柔性电力变压器后,计算电力系统中每个新能源场站的新能源多场站短路比;The configuration preparation module 502 is used to calculate the new energy of each new energy station in the power system after determining that the power system is suitable for configuring flexible power transformers according to the short-circuit capacity of the power system and the installed capacity of multiple new energy stations in the power system Multi-site short-circuit ratio;

柔性电力变压器配置确定模块503,用于对新能源多场站短路比不大于第一预设阈值的每一新能源场站:按照柔性电力变压器容量从小到大的顺序,依次接入柔性电力变压器,在每次接入柔性电力变压器后重新计算新能源场站的新能源多场站短路比,当重新计算的新能源场站的新能源多场站短路比大于第一预设阈值,确定新能源场站接入柔性电力变压器的配置参数;The flexible power transformer configuration determination module 503 is used to connect the flexible power transformers sequentially according to the order of the capacity of the flexible power transformers from small to large for each new energy site whose short-circuit ratio of multiple new energy sites is not greater than the first preset threshold , recalculate the new energy multi-station short-circuit ratio of the new energy station every time the flexible power transformer is connected, and when the recalculated new energy multi-station short-circuit ratio of the new energy station is greater than the first preset threshold, determine the new The configuration parameters of the flexible power transformer connected to the energy station;

柔性电力变压器配置筛选模块504,用于利用柔性电力变压器的过流阈值和耐压阈值,对各新能源场站接入柔性电力变压器的配置参数进行筛选,得到电力系统的柔性电力变压器的配置参数。The flexible power transformer configuration screening module 504 is used to use the overcurrent threshold and withstand voltage threshold of the flexible power transformer to screen the configuration parameters of the flexible power transformer connected to each new energy station, and obtain the configuration parameters of the flexible power transformer in the power system .

在一个实施例中,配置准备模块502具体用于:In one embodiment, the configuration preparation module 502 is specifically used to:

根据电力系统的短路容量、电力系统中多个新能源场站的装机容量,计算电力系统短路比;According to the short-circuit capacity of the power system and the installed capacity of multiple new energy stations in the power system, calculate the short-circuit ratio of the power system;

当电力系统短路比小于或等于第二预设阈值,确定电力系统适合配置柔性电力变压器。When the short-circuit ratio of the power system is less than or equal to the second preset threshold, it is determined that the power system is suitable for configuring a flexible power transformer.

在一个实施例中,配置准备模块502具体用于按如下公式计算新能源场站的新能源多场站短路比:In one embodiment, the configuration preparation module 502 is specifically used to calculate the new energy multi-station short-circuit ratio of the new energy station according to the following formula:

Figure BDA0004135065630000111
Figure BDA0004135065630000111

其中,MRSCRi为第i个新能源场站的新能源多场站短路比,Saci为第i个新能源场站处的系统短路容量;Pi为第i个新能源场站输入电网的有功功率,Pj为第j个新能源场站输入电网的有功功率,Zeqij为第i个新能源场站和第j个新能源场站之间的互阻抗,Zeqii为第i个新能源场站的自阻抗,n为新能源场站的个数,j为整数。Among them, MRSCR i is the new energy multi-station short-circuit ratio of the i-th new energy station, S aci is the system short-circuit capacity at the i-th new energy station; P i is the input power of the i-th new energy station Active power, P j is the active power of the j-th new energy station input to the grid, Z eqij is the mutual impedance between the i-th new energy station and the j-th new energy station, Z eqii is the i-th new energy station The self-impedance of the energy station, n is the number of new energy stations, and j is an integer.

在一个实施例中,柔性电力变压器配置筛选模块504具体用于:In one embodiment, the flexible power transformer configuration screening module 504 is specifically used for:

计算每一新能源场站接入的柔性电力变压器的高压侧出口单相接地故障短路电流,当任一新能源场站接入的柔性电力变压器的高压侧出口单相接地故障短路电流大于柔性电力变压器的过流阈值,为该新能源场站去除该柔性电力变压器;Calculate the single-phase ground fault short-circuit current of the high-voltage side outlet of the flexible power transformer connected to each new energy station. When the single-phase ground fault short-circuit current of the high-voltage side outlet of the flexible power transformer connected to any new energy station is greater than the The overcurrent threshold of the transformer removes the flexible power transformer for the new energy station;

计算每一新能源场站接入的柔性电力变压器高压侧出口单相接地故障新能源机端过电压,当任一新能源场站接入的柔性电力变压器高压侧出口单相接地故障新能源机端过电压大于柔性电力变压器的耐压阈值,为该新能源场站去除该柔性电力变压器。Calculate the overvoltage of the new energy machine terminal with a single-phase ground fault at the outlet of the high-voltage side of the flexible power transformer connected to each new energy station. If the terminal overvoltage is greater than the withstand voltage threshold of the flexible power transformer, the flexible power transformer is removed for the new energy site.

在一个实施例中,柔性电力变压器配置筛选模块504具体用于按如下公式计算每一新能源场站接入的柔性电力变压器的高压侧出口单相接地故障短路电流:In one embodiment, the flexible power transformer configuration screening module 504 is specifically used to calculate the single-phase ground fault short-circuit current of the high-voltage side outlet of the flexible power transformer connected to each new energy station according to the following formula:

Figure BDA0004135065630000112
Figure BDA0004135065630000112

其中,I为新能源场站接入的柔性电力变压器的高压侧出口单相接地故障短路电流,

Figure BDA0004135065630000121
为型号为Ti的柔性电力变压器阻抗,/>
Figure BDA0004135065630000122
为与型号Ti的柔性电力变压器低压侧相连的线路Li的阻抗,Ui为第i个新能源场机端电压。Among them, I is the single-phase ground fault short-circuit current of the high-voltage side outlet of the flexible power transformer connected to the new energy station,
Figure BDA0004135065630000121
is the impedance of the flexible power transformer whose type is T i , />
Figure BDA0004135065630000122
is the impedance of the line L i connected to the low-voltage side of the flexible power transformer of type T i , and U i is the terminal voltage of the i-th new energy field.

在一个实施例中,柔性电力变压器配置筛选模块504具体用于按如下公式计算每一新能源场站接入的柔性电力变压器高压侧出口单相接地故障新能源机端过电压:In one embodiment, the flexible power transformer configuration screening module 504 is specifically used to calculate the overvoltage of the new energy machine terminal of the flexible power transformer connected to the high-voltage side of the high-voltage side outlet of each new energy station according to the following formula:

Figure BDA0004135065630000123
Figure BDA0004135065630000123

其中,ΔU为新能源场站配置的柔性电力变压器高压侧出口单相接地故障新能源机端过电压,E为交流系统等值电势,UN为标称电压,MRSCRi为第i个新能源场站的新能源多场站短路比。Among them, ΔU is the single-phase ground fault overvoltage of the new energy machine terminal of the high-voltage side outlet of the flexible power transformer configured in the new energy station, E is the equivalent potential of the AC system, U N is the nominal voltage, and MRSCR i is the ith new energy New energy multi-station short-circuit ratio of the station.

在一个实施例中,柔性电力变压器的过流阈值按如下公式得到:In one embodiment, the overcurrent threshold of the flexible power transformer is obtained according to the following formula:

Io=k1×IN I o =k 1 ×I N

其中,Io为柔性电力变压器的过流阈值,k1为过流系数,IN为柔性电力变压器的额定电流。Among them, I o is the over-current threshold of the flexible power transformer, k 1 is the over-current coefficient, and I N is the rated current of the flexible power transformer.

在一个实施例中,柔性电力变压器的耐压阈值按如下公式得到:In one embodiment, the withstand voltage threshold of the flexible power transformer is obtained according to the following formula:

ΔUo=(k2-1)×UN ΔU o =(k 2 -1)×U N

其中,ΔUo为柔性电力变压器的耐压阈值,k2为耐压系数,UN为柔性电力变压器的额定电压。Among them, ΔU o is the withstand voltage threshold of the flexible power transformer, k 2 is the withstand voltage coefficient, and U N is the rated voltage of the flexible power transformer.

在一个实施例中,该装置中所述柔性电力变压器的配置参数包括如下任一柔性电力变压器的接入位置:电压等级220/35kV、电压等级110/35kV、电压等级110/10kV、电压等级66/10kV。In one embodiment, the configuration parameters of the flexible power transformer in the device include the access position of any of the following flexible power transformers: voltage level 220/35kV, voltage level 110/35kV, voltage level 110/10kV, voltage level 66 /10kV.

本发明实施例还提供一种计算机设备,包括存储器、处理器及存储在存储器上并可在处理器上运行的计算机程序,所述处理器执行所述计算机程序时实现上述柔性电力变压器的配置方法。The embodiment of the present invention also provides a computer device, including a memory, a processor, and a computer program stored on the memory and operable on the processor, and the processor implements the configuration method of the above-mentioned flexible power transformer when executing the computer program .

本发明实施例还提供一种计算机可读存储介质,所述计算机可读存储介质存储有计算机程序,所述计算机程序被处理器执行时实现上述柔性电力变压器的配置方法。The embodiment of the present invention also provides a computer-readable storage medium, the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the above-mentioned method for configuring the flexible power transformer is realized.

本发明实施例还提供一种计算机程序产品,所述计算机程序产品包括计算机程序,所述计算机程序被处理器执行时实现上述柔性电力变压器的配置方法。The embodiment of the present invention also provides a computer program product, the computer program product includes a computer program, and when the computer program is executed by a processor, the above-mentioned method for configuring the flexible power transformer is realized.

本发明实施例中,首先收集电力系统数据,利用电力系统数据中电力系统的短路容量、电力系统中多个新能源场站的装机容量判断电力系统是否适合配置柔性电力变压器;当确定电力系统适合配置柔性电力变压器,计算各新能源多场站短路比;当新能源多场站短路比符合条件,即小于或等于第一预设阈值时,为该新能源场站接入柔性电力变压器;在选择要接入新能源场站的柔性电力变压器时,按照柔性电力变压器容量从小到大的顺序依次接入,在每次接入柔性电力变压器后重新计算新能源场站的新能源多场站短路比,当重新计算的新能源场站的新能源多场站短路比大于第一预设阈值,确定新能源场站接入柔性电力变压器的配置参数;最后利用柔性电力变压器的过流阈值和耐压阈值,对各新能源场站接入柔性电力变压器的配置参数进行筛选,得到电力系统的柔性电力变压器的配置参数,从而得到电力系统的柔性电力变压器的配置方案。本发明实施例实现了通过新能源多场站短路比确定接入柔性电力变压器的配置参数,并通过柔性电力变压器的过流阈值和耐压阈值对配置参数进行筛选,可在规划设计阶段为新能源场站部署合适的柔性电力变压器,提升了新能源送出能力,提高了电网运行调节能力。In the embodiment of the present invention, the power system data is first collected, and the short-circuit capacity of the power system in the power system data and the installed capacity of multiple new energy stations in the power system are used to judge whether the power system is suitable for configuring flexible power transformers; when it is determined that the power system is suitable for Configure flexible power transformers to calculate the short-circuit ratio of each new energy multi-site station; when the new energy multi-site short-circuit ratio meets the conditions, that is, when it is less than or equal to the first preset threshold, connect the flexible power transformer to the new energy station; When selecting the flexible power transformer to be connected to the new energy station, connect it in order according to the capacity of the flexible power transformer from small to large, and recalculate the new energy multi-site short circuit of the new energy station after each connection of the flexible power transformer ratio, when the recalculated new energy multi-station short-circuit ratio of the new energy station is greater than the first preset threshold, determine the configuration parameters of the new energy station connected to the flexible power transformer; finally use the overcurrent threshold and the withstand voltage of the flexible power transformer The voltage threshold value is used to screen the configuration parameters of the flexible power transformers connected to each new energy station to obtain the configuration parameters of the flexible power transformers of the power system, thereby obtaining the configuration scheme of the flexible power transformers of the power system. The embodiment of the present invention realizes the determination of the configuration parameters of the connected flexible power transformer through the short circuit ratio of new energy multi-site stations, and screens the configuration parameters through the overcurrent threshold and withstand voltage threshold of the flexible power transformer, which can be used in the planning and design stage for new Deploying suitable flexible power transformers in energy stations has improved the ability to send new energy and improve the ability to regulate grid operation.

本领域内的技术人员应明白,本发明的实施例可提供为方法、系统、或计算机程序产品。因此,本发明可采用完全硬件实施例、完全软件实施例、或结合软件和硬件方面的实施例的形式。而且,本发明可采用在一个或多个其中包含有计算机可用程序代码的计算机可用存储介质(包括但不限于磁盘存储器、CD-ROM、光学存储器等)上实施的计算机程序产品的形式。Those skilled in the art should understand that the embodiments of the present invention may be provided as methods, systems, or computer program products. Accordingly, the present invention can take the form of an entirely hardware embodiment, an entirely software embodiment, or an embodiment combining software and hardware aspects. Furthermore, the present invention may take the form of a computer program product embodied on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) having computer-usable program code embodied therein.

本发明是参照根据本发明实施例的方法、设备(系统)、和计算机程序产品的流程图和/或方框图来描述的。应理解可由计算机程序指令实现流程图和/或方框图中的每一流程和/或方框、以及流程图和/或方框图中的流程和/或方框的结合。可提供这些计算机程序指令到通用计算机、专用计算机、嵌入式处理机或其他可编程数据处理设备的处理器以产生一个机器,使得通过计算机或其他可编程数据处理设备的处理器执行的指令产生用于实现在流程图一个流程或多个流程和/或方框图一个方框或多个方框中指定的功能的装置。The present invention is described with reference to flowchart illustrations and/or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of the invention. It should be understood that each procedure and/or block in the flowchart and/or block diagram, and a combination of procedures and/or blocks in the flowchart and/or block diagram can be realized by computer program instructions. These computer program instructions may be provided to a general purpose computer, special purpose computer, embedded processor, or processor of other programmable data processing equipment to produce a machine such that the instructions executed by the processor of the computer or other programmable data processing equipment produce a An apparatus for realizing the functions specified in one or more procedures of the flowchart and/or one or more blocks of the block diagram.

这些计算机程序指令也可存储在能引导计算机或其他可编程数据处理设备以特定方式工作的计算机可读存储器中,使得存储在该计算机可读存储器中的指令产生包括指令装置的制造品,该指令装置实现在流程图一个流程或多个流程和/或方框图一个方框或多个方框中指定的功能。These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing apparatus to operate in a specific manner, such that the instructions stored in the computer-readable memory produce an article of manufacture comprising instruction means, the instructions The device realizes the function specified in one or more procedures of the flowchart and/or one or more blocks of the block diagram.

这些计算机程序指令也可装载到计算机或其他可编程数据处理设备上,使得在计算机或其他可编程设备上执行一系列操作步骤以产生计算机实现的处理,从而在计算机或其他可编程设备上执行的指令提供用于实现在流程图一个流程或多个流程和/或方框图一个方框或多个方框中指定的功能的步骤。These computer program instructions can also be loaded onto a computer or other programmable data processing device, causing a series of operational steps to be performed on the computer or other programmable device to produce a computer-implemented process, thereby The instructions provide steps for implementing the functions specified in the flow chart or blocks of the flowchart and/or the block or blocks of the block diagrams.

以上所述的具体实施例,对本发明的目的、技术方案和有益效果进行了进一步详细说明,所应理解的是,以上所述仅为本发明的具体实施例而已,并不用于限定本发明的保护范围,凡在本发明的精神和原则之内,所做的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The specific embodiments described above have further described the purpose, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above descriptions are only specific embodiments of the present invention and are not intended to limit the scope of the present invention. Protection scope, within the spirit and principles of the present invention, any modification, equivalent replacement, improvement, etc., shall be included in the protection scope of the present invention.

Claims (21)

1. A method of configuring a flexible power transformer, comprising:
collecting power system data; the power system data comprise short circuit capacity of the power system and installed capacity of a plurality of new energy stations in the power system;
according to the short-circuit capacity of the power system and the installed capacity of a plurality of new energy stations in the power system, after the power system is determined to be suitable for configuring a flexible power transformer, calculating the short-circuit ratio of the new energy stations of each new energy station in the power system;
for each new energy station with the new energy multi-station short-circuit ratio not greater than a first preset threshold value: sequentially accessing the flexible power transformers according to the sequence from small to large of the capacity of the flexible power transformers, recalculating the short-circuit ratio of the new energy multi-station of the new energy station after accessing the flexible power transformers each time, and determining the configuration parameters of the new energy station accessed to the flexible power transformers when the recalculated short-circuit ratio of the new energy multi-station of the new energy station is larger than a first preset threshold value;
and screening the configuration parameters of the flexible power transformer accessed to each new energy station by utilizing the overcurrent threshold and the withstand voltage threshold of the flexible power transformer to obtain the configuration parameters of the flexible power transformer of the power system.
2. The method of claim 1, wherein determining that the power system is suitable for configuring the flexible power transformer based on a short circuit capacity of the power system, an installed capacity of a plurality of new energy sites in the power system, comprises:
calculating the short circuit ratio of the power system according to the short circuit capacity of the power system and the installed capacities of a plurality of new energy stations in the power system;
and when the short circuit ratio of the power system is smaller than or equal to a second preset threshold value, determining that the power system is suitable for configuring the flexible power transformer.
3. The method of claim 1, wherein the new energy multi-station short ratio of the new energy station is calculated according to the following formula:
Figure FDA0004135065580000011
wherein MRSCR i A new energy multi-station short-circuit ratio for the ith new energy station, S aci Short-circuit capacity for the system at the ith new energy station; p (P) i Inputting active power of a power grid for an ith new energy station, and P j Inputting active power of a power grid for a jth new energy station, Z eqij Z is the transimpedance between the ith new energy station and the jth new energy station eqii The self impedance of the ith new energy station is represented by n, the number of the new energy stations is represented by n, and j is an integer.
4. The method of claim 1, wherein the screening the configuration parameters of the flexible power transformer of the power system for each new energy station access by using the overcurrent threshold and the withstand voltage threshold of the flexible power transformer comprises:
Calculating the single-phase ground fault short-circuit current of the high-voltage side outlet of the flexible power transformer connected with each new energy station, and removing the flexible power transformer for the new energy station when the single-phase ground fault short-circuit current of the high-voltage side outlet of the flexible power transformer connected with any new energy station is larger than the overcurrent threshold of the flexible power transformer;
and calculating the overvoltage of the single-phase ground fault new energy machine end of the high-voltage side outlet of the flexible power transformer connected with each new energy station, and removing the flexible power transformer for the new energy station when the overvoltage of the single-phase ground fault new energy machine end of the high-voltage side outlet of the flexible power transformer connected with any new energy station is larger than the withstand voltage threshold of the flexible power transformer.
5. The method of claim 4, wherein the high side outlet single phase ground fault short circuit current of each flexible power transformer accessed by a new energy station is calculated as:
Figure FDA0004135065580000021
wherein I is the single-phase ground fault short-circuit current of the high-voltage side outlet of the flexible power transformer accessed by the new energy station,
Figure FDA0004135065580000022
is of the type T i Flexible power transformer impedance of>
Figure FDA0004135065580000023
Is of the type T i Line impedance, U, of the flexible power transformer low voltage side connection i The voltage of the field machine end of the ith new energy source is obtained.
6. The method of claim 4, wherein the high-side outlet single-phase ground fault new energy source machine-side overvoltage of the flexible power transformer to which each new energy source station is connected is calculated according to the following formula:
Figure FDA0004135065580000024
wherein DeltaU is the overvoltage of the single-phase ground fault new energy machine end at the high-voltage side outlet of the flexible power transformer configured by the new energy station, E is the equivalent potential of an alternating current system, U N For nominal voltage, MRSCR i And the new energy multi-station short-circuit ratio is the ith new energy station.
7. The method of claim 4, wherein the overcurrent threshold of the flexible power transformer is obtained as follows:
I o =k 1 ×I N
wherein I is o Is the overcurrent threshold, k of the flexible power transformer 1 For overcurrent coefficient, I N Is the rated current of the flexible power transformer.
8. The method of claim 4, wherein the withstand voltage threshold of the flexible power transformer is obtained as follows:
ΔU o =(k 2 -1)×U N
wherein DeltaU o Is the withstand voltage threshold value, k of the flexible power transformer 2 Is a pressure-resistant coefficient, U N Is the rated voltage of the flexible power transformer.
9. The method of claim 1, wherein the configuration parameters of the flexible power transformer include an access location of any one of the following flexible power transformers: 220/35kV voltage class, 110/10kV voltage class and 66/10kV voltage class.
10. A configuration device of a flexible power transformer, comprising:
the data collection module is used for collecting power system data; the power system data comprise short circuit capacity of the power system and installed capacity of a plurality of new energy stations in the power system;
the configuration preparation module is used for calculating the short-circuit ratio of the new energy multi-station of each new energy station in the power system after determining that the power system is suitable for configuring the flexible power transformer according to the short-circuit capacity of the power system and the installed capacities of the plurality of new energy stations in the power system;
the flexible power transformer configuration determining module is used for each new energy station with the short circuit ratio of the new energy stations not larger than a first preset threshold value: sequentially accessing the flexible power transformers according to the sequence from small to large of the capacity of the flexible power transformers, recalculating the short-circuit ratio of the new energy multi-station of the new energy station after accessing the flexible power transformers each time, and determining the configuration parameters of the new energy station accessed to the flexible power transformers when the recalculated short-circuit ratio of the new energy multi-station of the new energy station is larger than a first preset threshold value;
and the flexible power transformer configuration screening module is used for screening the configuration parameters of the flexible power transformer accessed to each new energy station by utilizing the overcurrent threshold and the withstand voltage threshold of the flexible power transformer to obtain the configuration parameters of the flexible power transformer of the power system.
11. The apparatus of claim 10, wherein the configuration preparation module is specifically configured to:
calculating the short circuit ratio of the power system according to the short circuit capacity of the power system and the installed capacities of a plurality of new energy stations in the power system;
and when the short circuit ratio of the power system is smaller than or equal to a second preset threshold value, determining that the power system is suitable for configuring the flexible power transformer.
12. The apparatus of claim 10, wherein the configuration preparation module is specifically configured to calculate a new energy multi-station short-circuit ratio for the new energy station according to the following formula:
Figure FDA0004135065580000041
wherein MRSCR i A new energy multi-station short-circuit ratio for the ith new energy station, S aci Short-circuit capacity for the system at the ith new energy station; p (P) i Inputting active power of a power grid for an ith new energy station, and P j Inputting active power of a power grid for a jth new energy station, Z eqij Z is the transimpedance between the ith new energy station and the jth new energy station eqii Is the self-impedance of the ith new energy station.
13. The apparatus of claim 10, wherein the flexible power transformer configuration screening module is specifically configured to:
calculating the single-phase ground fault short-circuit current of the high-voltage side outlet of the flexible power transformer connected with each new energy station, and removing the flexible power transformer for the new energy station when the single-phase ground fault short-circuit current of the high-voltage side outlet of the flexible power transformer connected with any new energy station is larger than the overcurrent threshold of the flexible power transformer;
And calculating the overvoltage of the single-phase ground fault new energy machine end of the high-voltage side outlet of the flexible power transformer connected with each new energy station, and removing the flexible power transformer for the new energy station when the overvoltage of the single-phase ground fault new energy machine end of the high-voltage side outlet of the flexible power transformer connected with any new energy station is larger than the withstand voltage threshold of the flexible power transformer.
14. The apparatus of claim 13, wherein the flexible power transformer configuration screening module is specifically configured to calculate a high side outlet single phase ground fault short circuit current of the flexible power transformer for each new energy station access according to the following formula:
Figure FDA0004135065580000042
wherein I is the single-phase ground fault short-circuit current of the high-voltage side outlet of the flexible power transformer accessed by the new energy station,
Figure FDA0004135065580000043
is of the type T i Flexible power transformer impedance of>
Figure FDA0004135065580000044
Is of the type T i Line impedance, U, of the flexible power transformer low voltage side connection i The voltage of the field machine end of the ith new energy source is obtained.
15. The apparatus of claim 13, wherein the flexible power transformer configuration screening module is specifically configured to calculate a single-phase ground fault new energy source terminal overvoltage at a high-voltage side outlet of the flexible power transformer to which each new energy station is connected according to the following formula:
Figure FDA0004135065580000045
Wherein DeltaU is the overvoltage of the single-phase ground fault new energy machine end at the high-voltage side outlet of the flexible power transformer configured by the new energy station, E is the equivalent potential of an alternating current system, U N For nominal voltage, MRSCR i And the new energy multi-station short-circuit ratio is the ith new energy station.
16. The apparatus of claim 13, wherein the overcurrent threshold of the flexible power transformer is obtained as follows:
I o =k 1 ×I N
wherein I is o Is the overcurrent threshold, k of the flexible power transformer 1 For overcurrent coefficient, I N Is the rated current of the flexible power transformer.
17. The apparatus of claim 13, wherein the withstand voltage threshold of the flexible power transformer is obtained as follows:
ΔU o =(k 2 -1)×U N
wherein DeltaU o Is the withstand voltage threshold value, k of the flexible power transformer 2 Is a pressure-resistant coefficient, U N Is the rated voltage of the flexible power transformer.
18. The apparatus of claim 10, wherein the configuration parameters of the flexible power transformer include an access location of any one of the following flexible power transformers: 220/35kV voltage class, 110/10kV voltage class and 66/10kV voltage class.
19. A computer device comprising a memory, a processor and a computer program stored on the memory and executable on the processor, characterized in that the processor implements the method of any of claims 1 to 9 when executing the computer program.
20. A computer readable storage medium, characterized in that the computer readable storage medium stores a computer program which, when executed by a processor, implements the method of any of claims 1 to 9.
21. A computer program product, characterized in that the computer program product comprises a computer program which, when executed by a processor, implements the method of any of claims 1 to 9.
CN202310271987.XA 2023-03-16 2023-03-16 Configuration method and device of flexible power transformer Pending CN116316779A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310271987.XA CN116316779A (en) 2023-03-16 2023-03-16 Configuration method and device of flexible power transformer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310271987.XA CN116316779A (en) 2023-03-16 2023-03-16 Configuration method and device of flexible power transformer

Publications (1)

Publication Number Publication Date
CN116316779A true CN116316779A (en) 2023-06-23

Family

ID=86777612

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310271987.XA Pending CN116316779A (en) 2023-03-16 2023-03-16 Configuration method and device of flexible power transformer

Country Status (1)

Country Link
CN (1) CN116316779A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030011348A1 (en) * 2001-07-10 2003-01-16 Abb Ab System, method, rotating machine and computer program product for enhancing electric power produced by renewable facilities
CN114421529A (en) * 2022-01-30 2022-04-29 中国电力科学研究院有限公司 New energy cluster multi-station short circuit ratio calculation method and system
CN115441513A (en) * 2022-08-05 2022-12-06 国网冀北电力有限公司电力科学研究院 Method and device for determining a condenser suitable for new energy stations

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030011348A1 (en) * 2001-07-10 2003-01-16 Abb Ab System, method, rotating machine and computer program product for enhancing electric power produced by renewable facilities
CN114421529A (en) * 2022-01-30 2022-04-29 中国电力科学研究院有限公司 New energy cluster multi-station short circuit ratio calculation method and system
CN115441513A (en) * 2022-08-05 2022-12-06 国网冀北电力有限公司电力科学研究院 Method and device for determining a condenser suitable for new energy stations

Similar Documents

Publication Publication Date Title
CN112564175B (en) New energy multi-station short circuit ratio calculation method and device and storage medium
CN113381445B (en) A method and system for optimal configuration of a condenser for suppressing transient overvoltage of new energy sources
CA2760888C (en) Fault-ride-through method, converter and power generating unit for a wind turbine
Park et al. The effect of SFCL on electric power grid with wind-turbine generation system
CN103094905B (en) Selection method of dynamic reactive power compensation configuration point
CN108400609B (en) Method for suppressing multi-feed-in direct current commutation failure site selection suitable for phase modulator
CN114460414B (en) Breaker breaking capacity verification method for power grid bus
Beekmann et al. Wind energy converters with FACTS Capabilities for optimized integration of wind power into transmission and distribution systems
Ugalde-Loo et al. Open access simulation toolbox for the grid connection of offshore wind farms using multi-terminal HVDC networks
CN111697626A (en) Photovoltaic power station, power generation control method and string inverter
Rohouma et al. Development of a capacitor-less D-STATCOM for power quality improvement in low voltage network
Hadavi et al. Optimal placement and sizing of DGs considering static voltage stability
Kolparambath et al. DC/DC converters for interconnecting independent HVDC systems into multiterminal DC grids
CN106356872A (en) Configuration method for static synchronous compensator of ultrahigh-voltage weak-direct-current receiving end power grid
CN115061025A (en) Photovoltaic inverter high voltage ride through detection method and system
CN116316779A (en) Configuration method and device of flexible power transformer
CN106972518A (en) Small-sized local power network and Energy Base direct current delivery system access module system of selection
CN103996149B (en) Regional power grid wind-powered electricity generation topological analysis method based on static electric voltage stability
Ruddy et al. Harmonic stability of VSC connected Low Frequency AC offshore transmission with long HVAC cables
Gandotra et al. The VSC-HVDC Transmission System Performance Assessment
Zhang et al. Magnetically Controlled Shunt Reactor Configuration Method Based on Single-Infeed Renewables-Integrated Effective Short Circuit Ratio
Menzel et al. Controlling Strategies for Meshed Offshore DC Collector Grids
Yang et al. Analysis and Suppression of Offshore Wind Power Broadband Oscillation Based on HVDC Transmission Technology
Memisevic et al. Stability Analysis of a Wind Park Based on DFIG Technology Supported by A Battery Energy Storage System
Liu et al. Electromechanical-electromagnetic Transient Hybrid Simulation Research on AC Fault Ride-through Characteristics at Receiving-end of LCC-VSC Hybrid Cascaded DC System

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination