CN115679844A - Integrated dismantling method for steel pipe concrete arch bridge - Google Patents
Integrated dismantling method for steel pipe concrete arch bridge Download PDFInfo
- Publication number
- CN115679844A CN115679844A CN202211260692.4A CN202211260692A CN115679844A CN 115679844 A CN115679844 A CN 115679844A CN 202211260692 A CN202211260692 A CN 202211260692A CN 115679844 A CN115679844 A CN 115679844A
- Authority
- CN
- China
- Prior art keywords
- cable
- arch
- bridge
- suspender
- dismantling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域technical field
本发明涉及钢管混凝土拱桥拆建一体化拆除方法。The invention relates to an integrated demolition method for the demolition and construction of a steel pipe concrete arch bridge.
背景技术Background technique
随着经济的发展,我国建设了一批世界级的大跨径刚拱桥,如上海卢浦大桥和重庆朝天门大桥。随着科技的发展和水泥的出现,钢筋混凝土和预应力混凝土拱桥的建设出现了高潮,然而更大跨径桥梁的出现,钢筋混凝土拱桥和预应力混凝土拱桥的自重和施工架设问题愈发突出。部分钢管混凝土拱桥上部结构面临着拆除置换的结局。With the development of the economy, my country has built a number of world-class long-span rigid arch bridges, such as Shanghai Lupu Bridge and Chongqing Chaotianmen Bridge. With the development of science and technology and the emergence of cement, the construction of reinforced concrete and prestressed concrete arch bridges has reached a climax. However, with the emergence of larger span bridges, the problems of self-weight and construction erection of reinforced concrete arch bridges and prestressed concrete arch bridges have become more and more prominent. Part of the superstructure of concrete-filled steel tube arch bridges is facing the end of demolition and replacement.
传统的拆除施工方法1:传统的拆除方案处于低成本的考虑,为爆破法和机械拆除法,仅考虑了结构拆除,往往拆除结束后再考虑新建施工重新施工架设系统,是资源的巨大浪费。传统的拆除施工方法2:桥下搭设钢支撑排架+大型汽车吊拆除法。此方案受地形的制约较大,对于山区大跨径桥梁,桥梁下部设置钢支撑排架施工困难,且桥梁标高较高,大型吊装设备无法位于地面作业。拆除方案存在很大的局限性,不适用于在原位重新新建钢管混凝土的桥梁。Traditional demolition construction method 1: Traditional demolition schemes are based on low cost considerations. They are blasting and mechanical demolition methods, which only consider structural demolition, and often consider new construction and erection systems after demolition is completed, which is a huge waste of resources. Traditional demolition construction method 2: Erection of steel support bent frames under the bridge + large truck crane demolition method. This scheme is greatly restricted by the terrain. For large-span bridges in mountainous areas, it is difficult to install steel support bent frames at the lower part of the bridge, and the bridge elevation is high, so large-scale hoisting equipment cannot be located on the ground. The demolition scheme has great limitations and is not suitable for rebuilding the CFST bridge in situ.
发明内容Contents of the invention
本发明的目的之一是为了克服现有技术中的不足,提供一种钢管混凝土拱桥拆建一体化拆除方法。One of the purposes of the present invention is to provide an integrated demolition method for concrete-filled steel tube arch bridges in order to overcome the deficiencies in the prior art.
为实现以上目的,本发明通过以下技术方案实现:To achieve the above object, the present invention is achieved through the following technical solutions:
一种钢管混凝土拱桥拆建一体化拆除方法,其特征在于,包括步骤:An integrated dismantling method for demolition and construction of a steel pipe concrete arch bridge, characterized in that it comprises the steps of:
A、利用斜拉扣索拉住拱肋;A. Use the cable-stayed buckle to pull the arch rib;
B、跨中打断,拆除桥面系纵横梁;按照从跨中向墩顶方向拆除;每拆除一跨纵梁,然后拆除横梁;B. The mid-span is interrupted, and the longitudinal and horizontal beams of the bridge deck are removed; it is removed in the direction from the mid-span to the top of the pier; each time a span longitudinal beam is removed, then the cross beam is removed;
C、拆除吊杆,利用缆索吊装将待拆除横梁固定并减小吊杆受力,然后对吊杆进行切割,吊杆切割完成后吊走横梁及吊杆;C. Remove the suspender, fix the beam to be removed by cable hoisting and reduce the force on the suspender, then cut the suspender, and hoist the beam and suspender away after the suspender is cut;
D、拆除拱肋,拱肋拆除前利用斜拉扣索体系对主拱肋内力进行调整,使拱顶跨中截面内力为零;然后采用绳锯等切割设备沿拱顶截面将拱肋切开,使结构体系从拱结构转换为悬臂体系,按照节段划分完成拱肋结构的拆除,按照从跨中向两侧的顺序拆除拱肋;D. Remove the arch rib. Before removing the arch rib, use the cable-stayed buckle system to adjust the internal force of the main arch rib, so that the internal force of the mid-span section of the vault is zero; then use cutting equipment such as wire saws to cut the arch rib along the vault section , so that the structural system is converted from an arch structure to a cantilever system, and the demolition of the arch rib structure is completed according to the division of segments, and the arch ribs are removed in the order from the mid-span to both sides;
E、新建主拱圈,保留桥梁拆除使用的缆索吊,扣索系统,采用缆索吊扣索系统更换新的主拱圈;E. Newly build the main arch circle, retain the cable hanger and buckle system used for bridge demolition, and use the cable hanger system to replace the new main arch circle;
F、依次完成主拱圈、桥面系、吊杆、横梁安装、更换桥面,主拱圈和吊杆施工完成,完成桥梁新建。F. Complete the installation of the main arch ring, bridge deck system, suspenders, beams, and replacement of the bridge deck in sequence. The construction of the main arch ring and suspenders is completed, and the bridge is newly built.
本发明中的钢管混凝土拱桥拆建一体化拆除方法,解决了钢管混凝土拱桥拆建同步施工难题。拆除顺序遵循“由上而下、化整为零”的规律,遵循“对称、平衡”的原则。The integrated demolition method of the steel pipe concrete arch bridge in the present invention solves the problem of synchronous construction of the steel pipe concrete arch bridge. The dismantling sequence follows the law of "from top to bottom, breaking into parts" and the principle of "symmetry and balance".
为了保证拆桥过程的安全性,使扣索在张拉的过程中,拱圈不至于因局部应力过大遭到破坏,对整个拱圈的应力情况进行了验算分析。In order to ensure the safety of the bridge demolition process, so that the arch ring will not be damaged due to excessive local stress during the tensioning process of the buckle cable, the stress situation of the entire arch ring is checked and analyzed.
利用缆索吊吊钩,横向由外侧向内侧逐步拆除,拆除时上下游对称;纵向由中跨向两侧桥头对称拆除。采用切割法将主拱圈分段切割后,由缆索吊吊运;Use the cable hook to remove it gradually from the outside to the inside in the horizontal direction, and the upstream and downstream are symmetrical during the demolition; the longitudinal removal is symmetrical from the middle span to the bridge heads on both sides. After the main arch ring is cut into sections by cutting method, it is hoisted by cable;
缆索吊装拆除在拆除上构、拱上建筑等时不需要封闭航道,在吊装拱圈时为了保证安全,吊装跨需要临时封闭航道,封闭时间约1~2小时,其他未施工跨段不需要封闭航道,整个拆除期间对航道通行影响较小。The cable hoisting and dismantling does not need to close the channel when removing the upper structure and arched buildings. In order to ensure safety when hoisting the arch ring, the hoisting span needs to temporarily close the channel. The closing time is about 1 to 2 hours, and other unconstructed spans do not need to be closed During the entire demolition period, there is little impact on the passage of the channel.
缆索吊装拆除方案中,缆索吊系统在进行桥面系拆除期间即进行安装,拱上建筑和拱圈拆除均可用到缆索系统,同时,新建桥若采用利于吊装的形式,亦可利用缆索吊进行施工。极大的节约了成本和工期。In the cable hoisting and dismantling scheme, the cable crane system is installed during the demolition of the bridge deck system. The cable system can be used for the construction on the arch and the demolition of the arch ring. construction. Greatly save cost and construction period.
附图说明Description of drawings
图1为本发明步骤A完成后的状态示意图;Fig. 1 is the state schematic diagram after step A of the present invention is finished;
图2为本发明步骤B完成后的状态示意图。Fig. 2 is a schematic diagram of the state after step B of the present invention is completed.
图3为本发明步骤C完成后的状态示意图。Fig. 3 is a schematic diagram of the state after step C of the present invention is completed.
图4为本发明步骤D完成后的状态示意图。Fig. 4 is a schematic diagram of the state after step D of the present invention is completed.
图5为本发明步骤E完成后的状态示意图。Fig. 5 is a schematic diagram of the state after step E of the present invention is completed.
图6为本发明步骤F完成后的状态示意图。Fig. 6 is a schematic diagram of the state after step F of the present invention is completed.
具体实施方式Detailed ways
一种钢管混凝土拱桥拆建一体化拆除方法,其特征在于,包括步骤:An integrated dismantling method for demolition and construction of a steel pipe concrete arch bridge, characterized in that it comprises the steps of:
A、如图1所示,利用斜拉扣索1拉住拱肋2;A. As shown in Figure 1, use the cable-stayed
B、如图2所示,跨中打断,拆除桥面系纵横梁;按照从跨中向墩顶方向拆除;每拆除一跨纵梁3,然后拆除横梁4;B. As shown in Figure 2, the middle of the span is interrupted, and the longitudinal and horizontal beams of the bridge deck are removed; according to the direction from the middle of the span to the top of the pier, the
C、如图3所示,拆除吊杆5,利用缆索吊6将待拆除横梁4固定并减小吊杆5受力,然后对吊杆5进行切割,吊杆5切割完成后吊走横梁4及吊杆5;C, as shown in Figure 3, remove the boom 5, use the
D、如图4所示,拆除拱肋2,拱肋2拆除前利用斜拉扣索1体系对主拱肋2内力进行调整,使拱顶跨中截面内力为零;然后采用绳锯等切割设备沿拱顶截面将拱肋2切开,使结构体系从拱结构转换为悬臂体系,按照节段划分完成拱肋结构的拆除,按照从跨中向两侧的顺序拆除拱肋2;D. As shown in Figure 4, remove the
E、如图5所示,新建主拱圈11,保留桥梁拆除使用的缆索吊6,斜拉扣索1,采用缆索吊6扣索系统更换新的主拱圈11;E, as shown in Figure 5, build
F、如图6所示,依次完成主拱圈11、桥面系12、吊杆、横梁安装、更换桥面,主拱圈和吊杆施工完成,完成桥梁新建。F. As shown in Figure 6, the installation of the
本发明中的钢管混凝土拱桥拆建一体化拆除方法,解决了钢管混凝土拱桥拆建同步施工难题。拆除顺序遵循“由上而下、化整为零”的规律,遵循“对称、平衡”的原则。The integrated demolition method of the steel pipe concrete arch bridge in the present invention solves the problem of synchronous construction of the steel pipe concrete arch bridge. The dismantling sequence follows the law of "from top to bottom, breaking into parts" and the principle of "symmetry and balance".
为了保证拆桥过程的安全性,使扣索在张拉的过程中,拱圈不至于因局部应力过大遭到破坏,对整个拱圈的应力情况进行了验算分析。In order to ensure the safety of the bridge demolition process, so that the arch ring will not be damaged due to excessive local stress during the tensioning process of the buckle cable, the stress situation of the entire arch ring is checked and analyzed.
利用缆索吊,横向由外侧向内侧逐步拆除,拆除时上下游对称;纵向由中跨向两侧桥头对称拆除。采用切割法将主拱圈分段切割后,由缆索吊吊运;Use cable cranes to dismantle gradually from the outside to the inside in the horizontal direction, and the upstream and downstream are symmetrical during the dismantling; the longitudinal dismantling is symmetrical from the middle span to the bridge heads on both sides. After the main arch ring is cut into sections by cutting method, it is hoisted by cable;
缆索吊装拆除在拆除上构、拱上建筑等时不需要封闭航道,在吊装拱圈时为了保证安全,吊装跨需要临时封闭航道,封闭时间约1~2小时,其他未施工跨段不需要封闭航道,整个拆除期间对航道通行影响较小。The cable hoisting and dismantling does not need to close the channel when removing the upper structure and arched buildings. In order to ensure safety when hoisting the arch ring, the hoisting span needs to temporarily close the channel. The closing time is about 1 to 2 hours, and other unconstructed spans do not need to be closed During the entire demolition period, there is little impact on the passage of the channel.
缆索吊装拆除方案中,缆索吊系统在进行桥面系拆除期间即进行安装,拱上建筑和拱圈拆除均可用到缆索系统,同时,新建桥若采用利于吊装的形式,亦可利用缆索吊进行施工。极大的节约了成本和工期。In the cable hoisting and dismantling scheme, the cable crane system is installed during the demolition of the bridge deck system. The cable system can be used for the construction on the arch and the demolition of the arch ring. construction. Greatly save cost and construction period.
本发明中的钢管混凝土拱桥拆建一体化拆除方法,将钢混混凝土上部结构拆除后,还可以利用原有桥墩结构,重建钢混混凝土上部结构。In the integrated dismantling method of the steel pipe concrete arch bridge in the present invention, after the steel-concrete superstructure is dismantled, the original bridge pier structure can also be used to rebuild the steel-concrete superstructure.
以上仅为本发明较佳的实施例,并不用于局限本发明的保护范围,任何在本发明精神内的修改、等同替换或改进等,都涵盖在本发明的权利要求范围内。The above are only preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Any modification, equivalent replacement or improvement within the spirit of the present invention is covered by the claims of the present invention.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211260692.4A CN115679844A (en) | 2022-10-14 | 2022-10-14 | Integrated dismantling method for steel pipe concrete arch bridge |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211260692.4A CN115679844A (en) | 2022-10-14 | 2022-10-14 | Integrated dismantling method for steel pipe concrete arch bridge |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN115679844A true CN115679844A (en) | 2023-02-03 |
Family
ID=85066704
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211260692.4A Pending CN115679844A (en) | 2022-10-14 | 2022-10-14 | Integrated dismantling method for steel pipe concrete arch bridge |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115679844A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116335057A (en) * | 2023-02-08 | 2023-06-27 | 武汉二航路桥特种工程有限责任公司 | A method for dismantling arch bridges without tower buckle cables |
| CN116856253A (en) * | 2023-06-28 | 2023-10-10 | 哈尔滨工业大学 | Large-span steel tube concrete arch bridge structure capable of improving wind resistance and construction method thereof |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2004019357A (en) * | 2002-06-19 | 2004-01-22 | Mitsubishi Heavy Ind Ltd | Erection method and apparatus for arch bridge |
| CN108532465A (en) * | 2018-04-20 | 2018-09-14 | 中交第三航务工程局有限公司 | A kind of construction method of Through Steel case arch bridge |
| CN111576256A (en) * | 2020-06-12 | 2020-08-25 | 兰州交通大学 | A cable replacement device for a concrete-filled steel tube arch bridge |
| CN112144424A (en) * | 2020-10-29 | 2020-12-29 | 魏家乐 | Construction method for removing arch ribs of steel pipe concrete arch bridge with dumbbell-shaped cross section |
| CN112267367A (en) * | 2020-11-20 | 2021-01-26 | 中铁九桥工程有限公司 | Method for converting arch-first beam-later system of self-anchored steel box tied arch bridge |
| CN112942125A (en) * | 2021-03-11 | 2021-06-11 | 中铁二院工程集团有限责任公司 | Bridge forming method for concrete tie beam with continuous structure of half-through arch bridge |
-
2022
- 2022-10-14 CN CN202211260692.4A patent/CN115679844A/en active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2004019357A (en) * | 2002-06-19 | 2004-01-22 | Mitsubishi Heavy Ind Ltd | Erection method and apparatus for arch bridge |
| CN108532465A (en) * | 2018-04-20 | 2018-09-14 | 中交第三航务工程局有限公司 | A kind of construction method of Through Steel case arch bridge |
| CN111576256A (en) * | 2020-06-12 | 2020-08-25 | 兰州交通大学 | A cable replacement device for a concrete-filled steel tube arch bridge |
| CN112144424A (en) * | 2020-10-29 | 2020-12-29 | 魏家乐 | Construction method for removing arch ribs of steel pipe concrete arch bridge with dumbbell-shaped cross section |
| CN112267367A (en) * | 2020-11-20 | 2021-01-26 | 中铁九桥工程有限公司 | Method for converting arch-first beam-later system of self-anchored steel box tied arch bridge |
| CN112942125A (en) * | 2021-03-11 | 2021-06-11 | 中铁二院工程集团有限责任公司 | Bridge forming method for concrete tie beam with continuous structure of half-through arch bridge |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116335057A (en) * | 2023-02-08 | 2023-06-27 | 武汉二航路桥特种工程有限责任公司 | A method for dismantling arch bridges without tower buckle cables |
| CN116856253A (en) * | 2023-06-28 | 2023-10-10 | 哈尔滨工业大学 | Large-span steel tube concrete arch bridge structure capable of improving wind resistance and construction method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102352597B (en) | Prestressed ultrahigh-performance concrete continuous box girder bridge and construction method thereof | |
| CN100590266C (en) | Reverse-sequence dismantling method for prestressed concrete tied arch bridge | |
| CN102418315B (en) | Construction Method of Concrete Steel Tube Arch Bridge with Large Bridge Width Erected by Low Buckle Towers | |
| CN103243658B (en) | The spelling method of cable stayed bridge dragging suspension basket | |
| CN109162209B (en) | Construction method for quick replacement of hanger rods of middle-bearing and lower-bearing arch bridges | |
| US20250129556A1 (en) | A method for rapid and safe construction and intelligent monitoring and controlling of continuous arch bridge | |
| CN109944170A (en) | Integrated construction system and construction method of cast-in-place section and closed section of high pier continuous beam side span | |
| CN104652293B (en) | A kind of Cable-Stayed Bridge Structure for reinforcing PSC Continuous Box Girder Bridge and construction method | |
| WO2011055996A2 (en) | Method for constructing a suspension bridge using temporary cables under tensionless stay cable conditions, and temporary cable for same | |
| CN101220580A (en) | Longitudinal multi-point continuous drag construction method for steel truss girders | |
| CN110904868A (en) | Bridge dismantling construction method for reverse segment hoisting of bridge girder erection machine | |
| WO2018133045A1 (en) | Method for mounting self-anchored suspension bridge | |
| CN109137739B (en) | Tower anchor-pier anchor combined rapid construction method of self-anchored suspension bridge | |
| CN107190627A (en) | Part earth anchored suspension bridge and its construction method | |
| CN115679844A (en) | Integrated dismantling method for steel pipe concrete arch bridge | |
| CN106988229A (en) | An arch-beam composite continuous rigid frame bridge buckle-hanging-support combined construction device and method | |
| CN108374320A (en) | A kind of construction and construction method of novel RC-masonry combination arch bridge | |
| CN116446303A (en) | Synchronous construction method for Shan Xuanbei tower beams of steel truss girder cable-stayed bridge | |
| CN102154990A (en) | Electing method for side span overhang-middle span cable-stayed three-tower self-anchored type combination suspension bridge | |
| CN110468734A (en) | Steel lagging jack pushing tow system and steel lagging jack push construction method | |
| CN212714544U (en) | Rhombus is hung basket and is retreated and demolishd horizontal extension reinforcement construction structure | |
| CN216712992U (en) | Prefabricated-cast-in-place underground continuous wall structure based on BIM technology | |
| CN107419670A (en) | Hybrid structure of arch and beam formula continuous rigid frame bridge winds up walking cradle construction device and method | |
| CN113944114A (en) | Dismantling construction method for large-span prestressed concrete cable-stayed bridge | |
| CN205557349U (en) | Device is changed to jib |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |