[go: up one dir, main page]

CN115305836A - Bridge stay cable lag tensioning construction process - Google Patents

Bridge stay cable lag tensioning construction process Download PDF

Info

Publication number
CN115305836A
CN115305836A CN202210989142.XA CN202210989142A CN115305836A CN 115305836 A CN115305836 A CN 115305836A CN 202210989142 A CN202210989142 A CN 202210989142A CN 115305836 A CN115305836 A CN 115305836A
Authority
CN
China
Prior art keywords
hanging basket
loading
tensioning
unloading
rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210989142.XA
Other languages
Chinese (zh)
Inventor
冯前进
卿迟
刘文浩
周日瑜
郭俊江
孙劲声
曹冬健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong No 2 Hydropower Engineering Co Ltd
Original Assignee
Guangdong No 2 Hydropower Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong No 2 Hydropower Engineering Co Ltd filed Critical Guangdong No 2 Hydropower Engineering Co Ltd
Priority to CN202210989142.XA priority Critical patent/CN115305836A/en
Publication of CN115305836A publication Critical patent/CN115305836A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/04Cable-stayed bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/16Suspension cables; Cable clamps for suspension cables ; Pre- or post-stressed cables

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to the field of constructional engineering, in particular to a construction process for lagging and tensioning a stay cable of a bridge, which comprises the following steps: a) Mounting a hanging basket; b) Prepressing the hanging basket; c) Mounting a bottom die and an outer die, mounting a steel bar in a prestressed manner, and mounting a similar template; d) Pouring and maintaining concrete; e) Stretching the three-way prestressed tendons; f) Grouting and sealing the anchor; g) The next section of forward construction of the hanging basket; h) Although the stress of the main beam is different from the original process in the bridge forming state, the tension force of the stay cable is not changed correspondingly, the stress in the bridge forming state is basically the same as the original process, and the construction progress is accelerated compared with the original process.

Description

一种桥梁斜拉索滞后张拉施工工艺A Construction Technology of Bridge Stay Cable Lag Tension

技术领域technical field

本发明涉及建筑工程技术领域,尤其涉及一种桥梁斜拉索滞后张拉施工工艺。The invention relates to the technical field of construction engineering, in particular to a bridge stay cable hysteresis tensioning construction technology.

背景技术Background technique

随着我国城市化进展而进行交通建设的加快,国内桥梁建设也随之进入一个新的发展阶段,大型跨江跨河桥梁工程不断出现,一般的桥悬浇节段施工顺序原设计为:浇筑节段梁、张拉箱室内纵向预应力、斜拉索安装、挂篮前移至下一节段,在斜拉索安装后进行挂篮前移至下一节段,容易被斜拉索影响,挂篮前移的难度较高,故而施工时间较长,为了为加快施工进度,提出一种拉索滞后张拉的施工工艺。With the progress of urbanization in my country and the acceleration of traffic construction, domestic bridge construction has also entered a new stage of development. Large-scale cross-river and cross-river bridge projects continue to appear. Segmental beams, longitudinal prestressing in the tension box, cable stay installation, and hanging basket moving forward to the next section. After the stay cable is installed, the hanging basket is moved forward to the next section, which is easily affected by the stay cable , it is more difficult to move the hanging basket forward, so the construction time is longer. In order to speed up the construction progress, a construction technology of lagging tension of the cable is proposed.

发明内容Contents of the invention

本发明目的在于提供一种加快施工进度的一种桥梁斜拉索滞后张拉施工工艺。The object of the present invention is to provide a bridge stay cable hysteresis tensioning construction process which can speed up the construction progress.

为实现上述目的,本发明的技术方案如下:To achieve the above object, the technical scheme of the present invention is as follows:

一种桥梁斜拉索滞后张拉施工工艺,其特征在于:所述施工工艺步骤如下:a)、安装挂篮;b)、挂篮预压;c)、底模、外模安装,钢筋预应力安装,类模板安装;d)、砼浇筑并养护;e)、张拉三向预应力束;f)、压浆,封锚;g)、挂篮前移施工的下一节段;h)、本梁端安装斜拉索张拉。A kind of bridge stay cable hysteresis stretching construction technology, it is characterized in that: described construction technology step is as follows: a), install hanging basket; b), hang basket preload; Stress installation, similar formwork installation; d), concrete pouring and maintenance; e), tensioning three-way prestressed beams; f), grouting, anchor sealing; g), the next section of the hanging basket moving forward construction; h ), the beam ends are installed with stay cables for tensioning.

优选的,所述步骤a)、安装挂篮中挂篮所有结构件均由塔吊和履带吊安装,主桁在地面拼装成整体后整体吊装,继而安装底篮系统和侧面系统;具体步骤为:轨道系统安装、在地面拼接成主桁系统整体后整体吊装、安装锚固系统、安装前上横梁、安装挂篮前后悬吊、安装挂篮底篮系统、安装挂篮平台系统、安装挂篮液压系统。Preferably, in the step a), all structural parts of the hanging basket in the installation of the hanging basket are installed by tower cranes and crawler cranes, and the main girder is assembled on the ground and hoisted as a whole, and then the bottom basket system and the side system are installed; the specific steps are: Track system installation, overall hoisting after splicing the main truss system on the ground, installation of anchor system, installation of front upper beam, installation of hanging basket front and rear suspension, installation of hanging basket bottom basket system, installation of hanging basket platform system, installation of hanging basket hydraulic system .

优选的,所述步骤b)、挂篮预压的加载方式为将加载分四次进行:0%、80%、100%、110%,每次加载完毕后,对挂篮进行沉降观测,当24h的沉降量平均值小于2mm时,进行下一次加载,且最后一级稳定时间为72小时,若沉降未稳定,应继续持荷预压,直至托架变形趋于稳定停止;Preferably, the step b), the loading method of the preloading of the hanging basket is to divide the loading into four times: 0%, 80%, 100%, and 110%. After each loading, the hanging basket is subjected to settlement observation. When the average settlement of 24h is less than 2mm, the next loading is carried out, and the last level of stabilization time is 72 hours. If the settlement is not stable, the preload should be continued until the bracket deformation tends to be stable and stop;

加载顺序为从墩中心向两侧依次,由近及远前后左右对称进行,先压载底板和腹板;The loading sequence is from the center of the pier to both sides, from near to far, front to back, left to right, symmetrically, and the bottom plate and web are first ballasted;

预压测点布置在主桁、导梁、前后下横梁、纵梁处;The pre-compression measuring points are arranged at the main truss, guide beam, front and rear lower beams, and longitudinal beams;

观测方法为在预压之前、分级加载、预压荷载全部加载完成及卸载后均要进行高程测量,认记录以上所有测点测量结果,并计算出其弹性变形,即在加载前,测量测点高程,作为起始数据,级加载完成后,应每间隔12h对支架沉降量进行监测,当支架测点12h的沉降差平均值均小于2mm时,可进行下一级加载,当加载110%后相邻 24h的沉降量平均值小于1mm或各监测点最初72h的沉降量平均值小于5mm,即可卸载,卸载时要两侧对称卸载,卸载的顺序与加载的顺序相反,先加载的后卸载,后加载的先卸载,卸载完成后观察一次,卸载6h观测各测点标高,预压时间不少于三天,预压完成后,根据所得数据计算出挂篮的弹性及非弹性变形值,计算公式为:非弹性变形值=加载前高程-卸载后高程、弹性变形值=卸载后高程-卸载前高程;The observation method is to carry out elevation measurement before preloading, step-by-step loading, and after all preloading loads are loaded and unloaded, and record the measurement results of all the above measuring points, and calculate their elastic deformation, that is, measure the measuring points before loading Elevation, as the initial data, after the stage loading is completed, the settlement of the support should be monitored every 12 hours. When the average settlement difference of the support measuring points for 12 hours is less than 2mm, the next stage of loading can be carried out. When the loading is 110% If the average settlement of the adjacent 24 hours is less than 1mm or the average settlement of each monitoring point for the first 72 hours is less than 5mm, it can be unloaded. When unloading, it should be unloaded symmetrically on both sides. The order of unloading is opposite to that of loading. , after loading, unload first, observe once after unloading is completed, observe the elevation of each measuring point after unloading 6h, preloading time is not less than three days, after preloading is completed, calculate the elastic and non-elastic deformation values of the hanging basket according to the obtained data, The calculation formula is: inelastic deformation value = height before loading - height after unloading, elastic deformation value = height after unloading - height before unloading;

加载完成后,在确认挂篮已经稳定并完成各项数据观测后,即可卸载。After the loading is complete, after confirming that the hanging basket is stable and completing various data observations, it can be unloaded.

优选的,所述步骤g)、挂篮前移施工的下一节段,即进行挂篮行走,挂篮首次行走或轨道设计为前后倒换使用的,需准确测放出挂篮前移轨道位置,按设计图纸铺设或倒换轨道垫梁和轨道,轨道需接长的,利用螺栓和两块连接板把两根轨道连成一整体,利用箱梁的竖向精扎螺纹钢、通过轨道压梁锚固轨道,完成轨道安装,轨道保证顶面水平,轨道前移到位安放好后将千斤顶缓缓下放,使前支座作用在轨道上,完成轨道前移作业,继而平联桁架两侧各安装1根吊杆吊住后下横梁,平联两侧上的吊杆垫梁应临时点焊在平联桁架下平杆或上平杆上,然后再拆除锚在箱梁上的其它后下横梁上的吊杆,底篮后下横梁同时用钢丝绳、葫芦悬挂在侧模上的滑动导梁上加以保护,在后锚压梁上利用螺旋千斤顶缓慢放松主桁后锚杆,使反扣轮扣住轨道,反扣轮完全受力后,收回千斤顶,松开后锚杆,在外滑梁后端平台及箱内拆除后锚杆,进而在轨道前端安装一个垫梁,通过垫梁穿一根精轧钢至前支座,在前支座后端安装穿心式千斤顶,使用螺帽与精轧钢连接,同时将千斤顶连接油泵;Preferably, the step g), the next section of the construction of the hanging basket moving forward, is to carry out the hanging basket walking, the hanging basket is walking for the first time or the track is designed to be used in reverse, it is necessary to accurately measure and release the hanging basket forward track position, Lay or reverse the track pad beam and track according to the design drawings. If the track needs to be extended, use bolts and two connecting plates to connect the two tracks into a whole, use the vertical fine-tie rebar of the box girder, and anchor the track through the track pressure beam , complete the track installation, ensure that the top surface of the track is level, move the track forward and place it in place, and then lower the jack slowly so that the front support acts on the track to complete the track forward operation, and then install a crane on both sides of the parallel truss The rod hangs the rear lower beam, and the suspender pad beams on both sides of the parallel truss should be temporarily spot-welded on the lower or upper flat rod of the parallel truss, and then remove the suspenders on the other rear lower beams anchored on the box girder At the same time, the lower crossbeam of the bottom basket is suspended on the sliding guide beam on the side formwork with wire ropes and gourds for protection, and the screw jack is used to slowly loosen the rear anchor rod of the main truss on the rear anchor beam, so that the buckle pulley buckles the track, and reverse After the pulley is fully stressed, retract the jack, loosen the rear anchor rod, remove the rear anchor rod in the rear end platform of the outer sliding beam and the box, and then install a pad beam at the front end of the track, and pass a piece of fine-rolled steel through the pad beam to the front support. Install a through-type jack at the rear end of the front support, use a nut to connect with the precision-rolled steel, and connect the jack to the oil pump at the same time;

最后进行挂篮的行走,挂篮行走时,需保持主桁架同步向前行进,反扣轮行走至轨道压梁处时,先在反扣轮后压一根轨道压梁,然后将反扣轮前压梁拆除,主桁前移到位后,等到下横梁箱室内预留孔、后锚预留孔与横梁吊具、后锚节点箱等对齐,随后立即对挂篮后锚点进行锚固,然后安装底篮后吊杆、翼板吊杆,放松行走后吊杆,调整模板位置及标高,继而移动滚动吊具到预留孔处,重新穿吊杆,等待下一次行走。Finally, carry out the walking of the hanging basket. When walking on the hanging basket, it is necessary to keep the main truss moving forward synchronously. After the front pressure beam is removed and the main truss is moved forward, wait until the reserved holes in the box chamber of the lower beam and the rear anchor are aligned with the beam spreader and the rear anchor node box, and then immediately anchor the rear anchor point of the hanging basket, and then After installing the bottom basket boom and wing boom, loosen the boom after walking, adjust the position and elevation of the formwork, then move the rolling spreader to the reserved hole, put the boom again, and wait for the next walk.

优选的,所述步骤c)、底模、外模安装,钢筋预应力安装,类模板安装;Preferably, the step c), bottom formwork, external formwork installation, reinforcement prestressed installation, similar formwork installation;

优选的,所述d)、砼浇筑并养护中混凝土采用集中拌制,两悬臂端对称浇筑,同一悬臂的两侧腹板也对称浇筑,入仓混凝土的不平衡重量不得超过梁段重量的1/4,砼灌注时应先浇注底板,后腹板、再顶板,且遵循先前后尾,两腹板对称浇注混凝土的顺序。Preferably, the concrete in d), concrete pouring and curing adopts centralized mixing, and the two cantilever ends are poured symmetrically, and the webs on both sides of the same cantilever are also poured symmetrically, and the unbalanced weight of the concrete in the warehouse must not exceed 1% of the weight of the beam section. /4. When pouring concrete, the bottom plate, the rear web, and then the top plate should be poured first, and the sequence of pouring concrete symmetrically to the front, rear, and two webs should be followed.

优选的,所述e)、张拉三向预应力束为布置纵、横、竖向钢束,预应力钢束均钢绞线,钢绞线为低松弛高强度预应力钢绞线,控制应力采用张拉应力与伸长量进行双控,张拉时应对称均匀张拉;Preferably, said e), the tensioning three-way prestressed beam is to arrange longitudinal, horizontal and vertical steel beams, and the prestressed steel beams are all steel strands, and the steel strands are low-relaxation high-strength prestressed steel strands, and the control Stress is double controlled by tensile stress and elongation, and it should be symmetrically and evenly stretched during tension;

张拉顺序:纵向预应力束→横向预应力束,含拉索区的横隔板预应力束→竖向预应力束,竖向预应力束滞后一个梁段张拉,箱梁顶板悬臂二次张拉预应力和竖向预应力采用低回缩二次张拉预应力锚固系统。Tensioning sequence: longitudinal prestressed beam→transverse prestressed beam, diaphragm prestressed beam with cable area→vertical prestressed beam, vertical prestressed beam lags behind one beam section tension, box girder roof cantilever twice Tensile prestress and vertical prestress adopt low retraction secondary tension prestress anchor system.

优选的,所述d)、砼浇筑并养护是采用覆盖洒水养护;所述步骤f)、压浆,封锚中采用二次收浆工艺,收浆抹面完成后,立即采用土工布进行覆盖,并在土工布上方洒水保湿,腹板及底板均为带模洒水养护,在预应力张拉、压浆完成后,挂篮前移时,拆除模板,养护时间不得低于7天。Preferably, said d), concrete pouring and maintenance are covered and sprinkled for maintenance; said step f), grouting, and anchor sealing adopt a secondary slurry collection process, and after the slurry collection and plastering is completed, immediately use geotextiles to cover, Sprinkle water on the top of the geotextile to keep it moisturized. Both the web and the bottom plate are sprinkled with water for curing. After the prestressed tension and grouting are completed, when the hanging basket moves forward, the formwork is removed. The curing time should not be less than 7 days.

本发明的优点:本发明通过改变施工工艺,将一般的桥悬浇节段施工顺序的斜拉索安装改变顺序在挂篮前移至下一节段后,减少被斜拉索影响,解决挂篮前移的难度较高,通过挂篮的安装步骤和结构特点,保证拉索滞后张拉后桥的应力在安全范围内,在成桥状态下主梁应力虽与原工序有所差别,但张拉索力没有相应发生变化,做到成桥状态下的应力与原工序基本相同,相对原工序,加快了施工进度。Advantages of the present invention: By changing the construction process, the present invention changes the installation order of the cable stays in the construction sequence of the general suspension cast section of the bridge. It is more difficult to move the basket forward. Through the installation steps and structural characteristics of the hanging basket, the stress of the bridge after the lagging of the cables is guaranteed to be within a safe range. Although the stress of the main girder in the bridge state is different from the original process, the There is no corresponding change in tension cable force, so that the stress in the bridge state is basically the same as the original process, and the construction progress is accelerated compared with the original process.

附图说明Description of drawings

图1为本实施例的总体施工工艺流程图。Fig. 1 is the overall construction process flow chart of the present embodiment.

图2为本实施例的挂篮悬浇施工工艺流程图。Fig. 2 is a flow chart of the suspension casting construction process of the hanging basket in this embodiment.

图3为本实施例的挂篮安装施工工艺流程。Fig. 3 is the installation and construction process flow of the hanging basket in this embodiment.

图4为本实施例的原工序及斜拉索滞后张拉工序对比图。Fig. 4 is a comparison diagram of the original process of this embodiment and the hysteresis tensioning process of the stay cables.

图5为本实施例的梁段移挂篮之后的最大、最小应力计算结果图。Fig. 5 is a diagram of the calculation results of the maximum and minimum stresses after the beam section is moved to the hanging basket in this embodiment.

具体实施方式Detailed ways

以下结合附图对本发明进行详细的描述。The present invention will be described in detail below in conjunction with the accompanying drawings.

实施例1Example 1

如图1-3所示,一种桥梁斜拉索滞后张拉施工工艺,所述施工工艺步骤如下:a)、安装挂篮;b)、挂篮预压;c)、底模、外模安装,钢筋预应力安装,类模板安装;d)、砼浇筑并养护;e)、张拉三向预应力束;f)、压浆,封锚;g)、挂篮前移施工的下一节段;h)、本梁端安装斜拉索张拉。As shown in Fig. 1-3, a kind of bridge stay cable hysteresis stretching construction process, described construction process steps are as follows: a), installation hanging basket; b), hanging basket preloading; c), bottom formwork, outer formwork Installation, steel prestressed installation, similar formwork installation; d), concrete pouring and maintenance; e), tensioning three-way prestressed beams; f), grouting, anchor sealing; g), hanging basket forward construction next step Segment; h), the beam ends are installed with stay cables for tension.

优选的,所述步骤a)、安装挂篮中挂篮所有结构件均由塔吊和履带吊安装,主桁在地面拼装成整体后整体吊装,继而安装底篮系统和侧面系统;具体步骤为:轨道系统安装、在地面拼接成主桁系统整体后整体吊装、安装锚固系统、安装前上横梁、安装挂篮前后悬吊、安装挂篮底篮系统、安装挂篮平台系统、安装挂篮液压系统。Preferably, in the step a), all structural parts of the hanging basket in the installation of the hanging basket are installed by tower cranes and crawler cranes, and the main girder is assembled on the ground and hoisted as a whole, and then the bottom basket system and the side system are installed; the specific steps are: Track system installation, overall hoisting after splicing the main truss system on the ground, installation of anchor system, installation of front upper beam, installation of hanging basket front and rear suspension, installation of hanging basket bottom basket system, installation of hanging basket platform system, installation of hanging basket hydraulic system .

优选的,所述步骤b)、挂篮预压的加载方式为将加载分四次进行:0%、80%、100%、110%,每次加载完毕后,对挂篮进行沉降观测,当24h的沉降量平均值小于2mm时,进行下一次加载,且最后一级稳定时间为72小时,若沉降未稳定,应继续持荷预压,直至托架变形趋于稳定停止;Preferably, the step b), the loading method of the preloading of the hanging basket is to divide the loading into four times: 0%, 80%, 100%, and 110%. After each loading, the hanging basket is subjected to settlement observation. When the average settlement of 24h is less than 2mm, the next loading is carried out, and the last level of stabilization time is 72 hours. If the settlement is not stable, the preload should be continued until the bracket deformation tends to be stable and stop;

加载顺序为从墩中心向两侧依次,由近及远前后左右对称进行,先压载底板和腹板;The loading sequence is from the center of the pier to both sides, from near to far, front to back, left to right, symmetrically, and the bottom plate and web are first ballasted;

预压测点布置在主桁、导梁、前后下横梁、纵梁处;The pre-compression measuring points are arranged at the main truss, guide beam, front and rear lower beams, and longitudinal beams;

观测方法为在预压之前、分级加载、预压荷载全部加载完成及卸载后均要进行高程测量,认记录以上所有测点测量结果,并计算出其弹性变形,即在加载前,测量测点高程,作为起始数据,级加载完成后,应每间隔12h对支架沉降量进行监测,当支架测点12h的沉降差平均值均小于2mm时,可进行下一级加载,当加载110%后相邻 24h的沉降量平均值小于1mm或各监测点最初72h的沉降量平均值小于5mm,即可卸载,卸载时要两侧对称卸载,卸载的顺序与加载的顺序相反,先加载的后卸载,后加载的先卸载,卸载完成后观察一次,卸载6h观测各测点标高,预压时间不少于三天,预压完成后,根据所得数据计算出挂篮的弹性及非弹性变形值,计算公式为:非弹性变形值=加载前高程-卸载后高程、弹性变形值=卸载后高程-卸载前高程;The observation method is to carry out elevation measurement before preloading, step-by-step loading, and after all preloading loads are loaded and unloaded, and record the measurement results of all the above measuring points, and calculate their elastic deformation, that is, measure the measuring points before loading Elevation, as the initial data, after the stage loading is completed, the settlement of the support should be monitored every 12 hours. When the average settlement difference of the support measuring points for 12 hours is less than 2mm, the next stage of loading can be carried out. When the loading is 110% If the average settlement of the adjacent 24 hours is less than 1mm or the average settlement of each monitoring point for the first 72 hours is less than 5mm, it can be unloaded. When unloading, it should be unloaded symmetrically on both sides. The order of unloading is opposite to that of loading. , after loading, unload first, observe once after unloading is completed, observe the elevation of each measuring point after unloading 6h, preloading time is not less than three days, after preloading is completed, calculate the elastic and non-elastic deformation values of the hanging basket according to the obtained data, The calculation formula is: inelastic deformation value = height before loading - height after unloading, elastic deformation value = height after unloading - height before unloading;

加载完成后,在确认挂篮已经稳定并完成各项数据观测后,即可卸载。After the loading is complete, after confirming that the hanging basket is stable and completing various data observations, it can be unloaded.

优选的,所述步骤g)、挂篮前移施工的下一节段,即进行挂篮行走,挂篮首次行走或轨道设计为前后倒换使用的,需准确测放出挂篮前移轨道位置,按设计图纸铺设或倒换轨道垫梁和轨道,轨道需接长的,利用螺栓和两块连接板把两根轨道连成一整体,利用箱梁的竖向精扎螺纹钢、通过轨道压梁锚固轨道,完成轨道安装,轨道保证顶面水平,轨道前移到位安放好后将千斤顶缓缓下放,使前支座作用在轨道上,完成轨道前移作业,继而平联桁架两侧各安装1根吊杆吊住后下横梁,平联两侧上的吊杆垫梁应临时点焊在平联桁架下平杆或上平杆上,然后再拆除锚在箱梁上的其它后下横梁上的吊杆,底篮后下横梁同时用钢丝绳、葫芦悬挂在侧模上的滑动导梁上加以保护,在后锚压梁上利用螺旋千斤顶缓慢放松主桁后锚杆,使反扣轮扣住轨道,反扣轮完全受力后,收回千斤顶,松开后锚杆,在外滑梁后端平台及箱内拆除后锚杆,进而在轨道前端安装一个垫梁,通过垫梁穿一根精轧钢至前支座,在前支座后端安装穿心式千斤顶,使用螺帽与精轧钢连接,同时将千斤顶连接油泵;Preferably, the step g), the next section of the construction of the hanging basket moving forward, is to carry out the hanging basket walking, the hanging basket is walking for the first time or the track is designed to be used in reverse, it is necessary to accurately measure and release the hanging basket forward track position, Lay or reverse the track pad beam and track according to the design drawings. If the track needs to be extended, use bolts and two connecting plates to connect the two tracks into a whole, use the vertical fine-tie rebar of the box girder, and anchor the track through the track pressure beam , complete the track installation, ensure that the top surface of the track is level, move the track forward and place it in place, and then lower the jack slowly so that the front support acts on the track to complete the track forward operation, and then install a crane on both sides of the parallel truss The rod hangs the rear lower beam, and the suspender pad beams on both sides of the parallel truss should be temporarily spot-welded on the lower or upper flat rod of the parallel truss, and then remove the suspenders on the other rear lower beams anchored on the box girder At the same time, the lower crossbeam of the bottom basket is suspended on the sliding guide beam on the side formwork with wire ropes and gourds for protection, and the screw jack is used to slowly loosen the rear anchor rod of the main truss on the rear anchor beam, so that the buckle pulley buckles the track, and reverse After the pulley is fully stressed, retract the jack, loosen the rear anchor rod, remove the rear anchor rod in the rear end platform of the outer sliding beam and the box, and then install a pad beam at the front end of the track, and pass a piece of fine-rolled steel through the pad beam to the front support. Install a through-type jack at the rear end of the front support, use a nut to connect with the precision-rolled steel, and connect the jack to the oil pump at the same time;

最后进行挂篮的行走,挂篮行走时,需保持主桁架同步向前行进,反扣轮行走至轨道压梁处时,先在反扣轮后压一根轨道压梁,然后将反扣轮前压梁拆除,主桁前移到位后,等到下横梁箱室内预留孔、后锚预留孔与横梁吊具、后锚节点箱等对齐,随后立即对挂篮后锚点进行锚固,然后安装底篮后吊杆、翼板吊杆,放松行走后吊杆,调整模板位置及标高,继而移动滚动吊具到预留孔处,重新穿吊杆,等待下一次行走。Finally, carry out the walking of the hanging basket. When walking on the hanging basket, it is necessary to keep the main truss moving forward synchronously. After the front pressure beam is removed and the main truss is moved forward, wait until the reserved holes in the box chamber of the lower beam and the rear anchor are aligned with the beam spreader and the rear anchor node box, and then immediately anchor the rear anchor point of the hanging basket, and then After installing the bottom basket boom and wing boom, loosen the boom after walking, adjust the position and elevation of the formwork, then move the rolling spreader to the reserved hole, put the boom again, and wait for the next walk.

优选的,所述步骤c)、底模、外模安装,钢筋预应力安装,类模板安装;Preferably, the step c), bottom formwork, external formwork installation, reinforcement prestressed installation, similar formwork installation;

优选的,所述d)、砼浇筑并养护中混凝土采用集中拌制,两悬臂端对称浇筑,同一悬臂的两侧腹板也对称浇筑,入仓混凝土的不平衡重量不得超过梁段重量的1/4,砼灌注时应先浇注底板,后腹板、再顶板,且遵循先前后尾,两腹板对称浇注混凝土的顺序。Preferably, the concrete in d), concrete pouring and curing adopts centralized mixing, and the two cantilever ends are poured symmetrically, and the webs on both sides of the same cantilever are also poured symmetrically, and the unbalanced weight of the concrete in the warehouse must not exceed 1% of the weight of the beam section. /4. When pouring concrete, the bottom plate, the rear web, and then the top plate should be poured first, and the sequence of pouring concrete symmetrically to the front, rear, and two webs should be followed.

优选的,所述e)、张拉三向预应力束为布置纵、横、竖向钢束,预应力钢束均钢绞线,钢绞线为低松弛高强度预应力钢绞线,控制应力采用张拉应力与伸长量进行双控,张拉时应对称均匀张拉;Preferably, said e), the tensioning three-way prestressed beam is to arrange longitudinal, horizontal and vertical steel beams, and the prestressed steel beams are all steel strands, and the steel strands are low-relaxation high-strength prestressed steel strands, and the control Stress is double controlled by tensile stress and elongation, and it should be symmetrically and evenly stretched during tension;

张拉顺序:纵向预应力束→横向预应力束,含拉索区的横隔板预应力束→竖向预应力束,竖向预应力束滞后一个梁段张拉,箱梁顶板悬臂二次张拉预应力和竖向预应力采用低回缩二次张拉预应力锚固系统。Tensioning sequence: longitudinal prestressed beam→transverse prestressed beam, diaphragm prestressed beam with cable area→vertical prestressed beam, vertical prestressed beam lags behind one beam section tension, box girder roof cantilever twice Tensile prestress and vertical prestress adopt low retraction secondary tension prestress anchor system.

优选的,所述d)、砼浇筑并养护是采用覆盖洒水养护;所述步骤f)、压浆,封锚中采用二次收浆工艺,收浆抹面完成后,立即采用土工布进行覆盖,并在土工布上方洒水保湿,腹板及底板均为带模洒水养护,在预应力张拉、压浆完成后,挂篮前移时,拆除模板。养护时间不得低于7天。Preferably, said d), concrete pouring and maintenance are covered and sprinkled for maintenance; said step f), grouting, and anchor sealing adopt a secondary slurry collection process, and after the slurry collection and plastering is completed, immediately use geotextiles to cover, Sprinkle water on the top of the geotextile to keep it moist. Both the web and the bottom plate are sprinkled with water for maintenance. After the prestressed tension and grouting are completed, the formwork is removed when the hanging basket moves forward. The curing time shall not be less than 7 days.

在本实施例中,主梁箱梁悬浇共有17个节段(1~17#),节段组成(3×3.5+14×4)m,主桥采用菱形挂篮对称进行悬浇施工,挂篮主桁在后场拼装,0#块浇筑完成后,采用塔吊吊装挂篮杆件,在0# 块上方拼装挂篮,挂篮拼装完成后,进行预压并记录变形情况,安装底模、外模、绑扎钢筋、安装内模,对称浇筑1~17#梁段。In this embodiment, there are 17 segments (1~17#) in the cantilever casting of the main girder box girder, and the segments consist of (3×3.5+14×4) m. The main truss of the hanging basket is assembled in the back field. After the 0# block is poured, use the tower crane to hoist the hanging basket rods, and assemble the hanging basket above the 0# block. After the hanging basket is assembled, pre-press and record the deformation, and install the bottom form , Outer formwork, tying steel bars, installation of inner formwork, symmetrical pouring of 1~17# beam sections.

在浇筑4~15#梁段同步安装斜拉索,根据现场施工监控,进行索力调整,斜拉索张拉完成后,挂篮往前移动进行下一节段施工,如此循环,直至完成最后15#梁段悬浇,斜拉索安装完成。The stay cables are installed synchronously in the pouring 4~15# beam section, and the cable force is adjusted according to the construction monitoring on site. Cantilever casting of 15# beam section, installation of stay cables is completed.

在本实施例中:挂篮由主桁系统、行走系统、锚固系统、悬吊系统、底篮系统、模板系统及操作平台防护系统组成;其中主桁系统是挂篮的主要受力构件,由菱形桁架、销轴、横向平联桁架、前上横梁等部件组成,菱形桁架由受力杆件和箱体采用销轴销结,便于拆装和运输,菱形桁架竖放于箱梁腹板位置,采用两片桁架,两片桁架横向通过平联桁架连成整体,前上横梁架设在菱形桁架的前端节点上,上设吊点,作为悬吊底篮系统和内外模滑梁用,横梁同时起到将主桁架连成整体的作用,主桁系统由3榀菱形主桁架、横向联结系组成。3 榀主桁架中心间距为8.4/8.6m,中心高3.5米,每榀桁架前后节点间距均为4.2m,总长12.2m。桁架主杆件采用[]40a槽钢焊接的格构式结构,节点通过箱体采用销轴联结。横向联结系采用[]14槽钢焊接,设于两榀主桁架的竖杆上,其作用是保证主桁架的横向稳定,并在走行状态悬吊底模平台后横梁。挂篮主桁采用钢垫块调整水平,保证主桁垂直;In this embodiment: the hanging basket is composed of a main truss system, a walking system, an anchoring system, a suspension system, a bottom basket system, a formwork system and an operating platform protection system; the main truss system is the main force-bearing component of the hanging basket, and is composed of The rhombus truss, pin shaft, horizontal parallel truss, front upper beam and other components, the rhombus truss is composed of force-bearing members and boxes with pins, which is easy to disassemble and transport, and the rhombus truss is vertically placed on the web of the box girder , two trusses are used, and the two trusses are connected horizontally through parallel trusses to form a whole. The front upper beam is erected on the front node of the diamond-shaped truss, and a lifting point is set on it, which is used as the suspension bottom basket system and the sliding beam of the inner and outer molds. The beam is at the same time It plays the role of connecting the main trusses into a whole. The main truss system is composed of 3 rhombus-shaped main trusses and horizontal connecting systems. 3 The center distance of the main truss is 8.4/8.6m, the center height is 3.5m, the distance between the front and rear nodes of each truss is 4.2m, and the total length is 12.2m. The main member of the truss adopts a lattice structure welded by []40a channel steel, and the nodes are connected by pins through the box. The horizontal connection system is welded by []14 channel steel, and it is set on the vertical rods of the two main trusses. Its function is to ensure the lateral stability of the main truss, and to suspend the rear beam of the bottom formwork platform in the running state. The main truss of the hanging basket adopts steel pads to adjust the level to ensure that the main truss is vertical;

行走系统主要由行走轨道、滑座、吊挂滚轮、轨道压梁、轨道垫梁等部分组成。轨道主要供挂篮空载前移使用。挂篮前移时,主千斤顶顶起前支座,滑座与轨道脱开,整体轨道向前拖动后锚固,然后吊挂滚轮反扣在轨道上,主桁前支座下放置在轨道上,最后采用两个32t液压千斤顶作动力,行走时用一根较长的Φ32mm精轧螺纹钢一头锚固在轨道前端,一头锚固在挂篮前支点32t千斤顶上,通过电动油泵供油,千斤顶推动前支点滑动带动整个挂篮前移,达到一个行程后液压泵回油,反复循环至到推至锚固位置;The walking system is mainly composed of walking track, sliding seat, hanging roller, track pressure beam, track pad beam and other parts. The track is mainly used for the forward movement of the hanging basket without load. When the hanging basket moves forward, the main jack lifts the front support, the sliding seat is disengaged from the track, the whole track is dragged forward and then anchored, then the hanging rollers are reversed on the track, and the main truss is placed on the track under the front support Finally, two 32t hydraulic jacks are used as power. When walking, one end of a longer Φ32mm fine-rolled rebar is anchored to the front end of the track, and the other end is anchored to the 32t jack at the front fulcrum of the hanging basket. Oil is supplied by an electric oil pump, and the jack pushes forward The sliding of the fulcrum drives the entire hanging basket to move forward. After reaching a stroke, the hydraulic pump returns oil, and the cycle is repeated until it is pushed to the anchoring position;

其中锚固系统为主桁系统的自锚平衡装置,由扁担梁、精轧螺纹钢、连接器螺帽、垫块等部分组成。当挂篮在灌注混凝土时,后端利用Φ32mm精轧螺纹钢筋(外套PVC保护管)穿过预埋孔对拉在已浇注的梁段顶板上,后锚梁采用双拼槽钢,单片菱形架设置3根后锚梁,6根后锚吊杆,后锚吊杆通过梁体在边腹板预埋精轧螺纹钢筋和顶板上预留孔锚固,锚固时需加设斜垫块,以保证后锚杆垂直受力。Among them, the anchorage system is the self-anchor balancing device of the main truss system, which is composed of pole beams, precision-rolled rebar, connector nuts, pads and other parts. When the hanging basket is pouring concrete, the rear end uses Φ32mm fine-rolled threaded steel bar (coated with PVC protection pipe) to pass through the pre-buried hole and pull it on the top plate of the poured beam section. The rear anchor beam adopts double channel steel, single-piece diamond 3 rear anchor beams and 6 rear anchor suspenders are installed in the frame, and the rear anchor suspenders are anchored through the pre-embedded fine-rolled threaded steel bars on the side webs of the beams and the reserved holes on the top plate. Ensure that the rear anchor rod bears vertical force.

其中底篮系统直接承受梁段混凝土重量,并为立模,钢筋绑扎,混凝土浇筑等工序提供操作场地。其由底模板、纵梁和前后横梁组成,底模板采用大块钢模板。其中纵梁采用H350×175型钢,前、后下横梁采用2HN400×200型钢组焊。前后横梁中心距为5.5m.纵梁与横梁螺栓连接;Among them, the bottom basket system directly bears the concrete weight of the beam section, and provides an operating site for forming forms, steel bar binding, concrete pouring and other processes. It consists of bottom formwork, longitudinal beams and front and rear beams, and the bottom formwork adopts large steel formwork. Among them, the longitudinal beam is made of H350×175 steel, and the front and rear lower beams are assembled and welded with 2HN400×200 steel. The distance between the centers of the front and rear beams is 5.5m. The longitudinal beams are connected to the beams with bolts;

其中悬吊系统用于悬吊底模平台和外模。并将底模平台、侧模的自重、梁段混凝土重量及其它施工荷载传递到主构架和己成梁段上。悬吊系统包括前上横梁、底模平台前后吊杆、侧模导梁前后吊杆、滑道梁吊杆、垫梁、扁担梁及螺旋千斤顶。Among them, the suspension system is used to suspend the bottom mold platform and the outer mold. And transfer the self-weight of the bottom formwork platform, side formwork, beam section concrete weight and other construction loads to the main frame and the finished beam section. The suspension system includes the front upper beam, the front and rear suspenders of the bottom form platform, the front and rear suspenders of the side form guide beam, the slideway beam suspender, the pad beam, the pole beam and the screw jack.

其中模板系统主要由外侧模、内模、底模和端模四部分组成。外侧模为钢模板,由面板、横肋、竖肋和骨架组成,模板根据箱梁结构分块加工,采用螺拴连接。骨架和模板一般分开运输,到现场进行组装拼接。底模和由面板和横肋组成,模板根据箱梁结构分块加工,采用螺栓连接。The formwork system is mainly composed of four parts: outer mold, inner mold, bottom mold and end mold. The outer formwork is a steel formwork, which is composed of panels, transverse ribs, vertical ribs and skeletons. The formwork is processed in blocks according to the box girder structure and connected by bolts. Skeleton and formwork are generally transported separately and assembled on site. The bottom formwork is composed of panels and transverse ribs, and the formwork is processed in blocks according to the box girder structure and connected by bolts.

其中施工平台分底施工平台、侧模工作平台和底模前工作平台。底施工平台主要用于底锚的拆装及箱梁底面的砼表面处理,位于底模后部。侧工作平台主要用于处理侧面砼和滑梁吊轮的拆卸,位于底模两端。底模前工作平台主要用于箱梁前端的封端、张拉,位于底模前部。The construction platform is divided into bottom construction platform, side form work platform and bottom form front work platform. The bottom construction platform is mainly used for the disassembly and assembly of the bottom anchor and the concrete surface treatment of the bottom surface of the box girder, and is located at the rear of the bottom formwork. The side working platform is mainly used to disassemble the side concrete and the sliding beam suspension wheel, and is located at both ends of the bottom form. The working platform in front of the bottom mold is mainly used for sealing and tensioning the front end of the box girder, and is located at the front of the bottom mold.

总体的施工为:The overall construction is:

步骤一:主桥下构及0号块施工完毕;Step 1: The construction of the lower structure of the main bridge and Block 0 is completed;

步骤二:0号块施工完成后,安装挂篮。Step 2: After the construction of Block 0 is completed, install the hanging basket.

步骤三:(1)利用挂篮对称悬浇1号块;(2)张拉1号块预应力;(3)前移挂篮;(4)重复1~3步,完成2~3号块浇筑;Step 3: (1) Utilize the hanging basket to hang and pour the No. 1 block symmetrically; (2) Tension the prestressed force of the No. 1 block; (3) Move the hanging basket forward; (4) Repeat steps 1 to 3 to complete the No. 2 to 3 blocks pouring;

步骤四:(1)利用挂篮对称悬浇4号块;(2)张拉4号块预应力;(3)架设并张拉斜拉索;(4)前移挂篮;(5)重复1~4步,完成5~15号块及斜拉索张拉;(6)搭设边跨现浇段支架;Step 4: (1) Utilize the hanging basket to cast No. 4 block symmetrically; (2) Stretch the prestress of No. 4 block; (3) Erect and stretch the stay cable; (4) Move the hanging basket forward; (5) Repeat Steps 1 to 4, complete the tensioning of blocks No. 5 to No. 15 and stay cables; (6) Set up the support of the cast-in-place section of the side span;

步骤五:(1)利用挂篮对称悬浇16和17号块;(2)张拉相应预应力;(3)同时采用支架法完成边跨现浇段;Step 5: (1) Use the hanging basket to symmetrically cast No. 16 and No. 17 blocks; (2) Stretch the corresponding prestress; (3) Use the bracket method to complete the cast-in-place section of the side span;

步骤六:(1)合拢按照先边跨,后中跨原则;(2)拆除12#墩边跨部分支架使边跨侧挂篮模板进入,13#墩挂篮前移2m到18#梁段,边跨挂篮吊杆与19#梁段相交50cm,停止前移;(3)挂篮就位后,安装吊杆,然后安装边跨合拢段模板、钢筋,在13#两侧悬臂端(17# 梁段端头)安放换重水箱,加水重量54吨;(4)连续测量合拢段,在一天中温度低的时间段用劲性骨架锁定合拢段,浇筑混凝土,边浇筑混凝土等量卸载换重(中跨侧不卸载),混凝土达到强度合格后,张拉部分边跨合拢段预应力钢束,拆除劲性骨架,按设计张拉全部边跨合拢段预应力钢束;(5)拆除边跨支架及13#墩挂篮;(6)12号墩边跨合拢段施工时,同时采用盘扣支架施工15号墩边跨合拢段;Step 6: (1) Close up according to the principle of side span first, then middle span; (2) Remove part of the side span support of 12# pier so that the side span side hanging basket formwork enters, and the 13# pier hanging basket moves forward 2m to the 18# beam section , the side-span hanging basket suspender intersects the 19# beam section by 50cm, and stops moving forward; (3) After the hanging basket is in place, install the suspender, and then install the side-span closing section formwork and steel bars, at the cantilever ends on both sides of 13# ( 17# end of the beam section) to place a re-weighting water tank, and add water to the weight of 54 tons; (4) Continuously measure the closing section, lock the closing section with strength during the low temperature period of the day, pour concrete, and unload and change the weight in the same amount as the concrete is being poured ( The middle span side is not unloaded), after the concrete reaches the qualified strength, stretch the prestressed steel tendons of part of the side span closing section, remove the stiff skeleton, and stretch all the prestressed steel tendons of the side span closing section according to the design; (5) Remove the side span Bracket and 13# pier hanging basket; (6) During the construction of the side span closure section of No. 12 pier, the buckle support is used to construct the side span closure section of No. 15 pier at the same time;

步骤七:(1)主跨合龙采用吊挂法,挂篮退回主墩拆除,中跨合拢前纵向施加3000KN顶推力;(2)中跨合拢段安装模板、钢筋;(3) 在中跨合拢段梁段(17#梁段端头)安放换重水箱,13号和14号墩加水重量54吨;Step 7: (1) The main span closure adopts the hanging method, the hanging basket is returned to the main pier for removal, and a 3000KN jacking force is applied longitudinally before the mid-span closure; (2) Formwork and steel bars are installed at the mid-span closure section; (3) The mid-span closure The section beam section (the end of the 17# beam section) is placed to replace the heavy water tank, and the water weight of No. 13 and No. 14 piers is 54 tons;

(4)连续测量合拢段,在一天中温度低的时间段用劲性骨架锁定合拢段,浇筑混凝土,边浇筑混凝土等量卸载换重;(5)混凝土达到强度合格后,先部分张拉预应力钢束,拆除劲性骨架,按设计张拉全部中跨合拢钢束预应力;(4) Continuously measure the closing section, lock the closing section with a stiff skeleton during the low temperature period of the day, pour concrete, and unload and change weight in equal amounts while pouring concrete; (5) After the concrete reaches the qualified strength, first partially stretch the prestress For steel tendons, remove the rigid frame and stretch all the mid-span closed steel tendons for prestress according to the design;

步骤八:施工桥面系。Step 8: Construction of bridge deck system.

经由上述工序,节约工期,原n号斜拉索张拉工况在n号梁段预应力张拉工况之后,在n+1号梁段移挂篮工况之前进行,改为在n+1 号梁段移挂篮工况之后,在n+1号梁段浇混凝土之前进行,即桥梁斜拉索滞后张拉施工工艺,以4号梁段和5号梁段为例,原工序及斜拉索滞后张拉工序如附图4所示。Through the above process, the construction period is saved. The original tensioning condition of No. n stay cables is carried out after the prestressed tensioning condition of No. n beam section and before the No. After the No. 1 beam section is moved to the hanging basket, it is carried out before the concrete pouring of the n+1 beam section, that is, the lagging tension construction process of the bridge stay cable. Taking the No. 4 beam section and the No. 5 beam section as examples, the original process and The hysteresis tensioning process of the stay cables is shown in Figure 4.

在本计算分析中斜拉索的张拉时机发生了变化,但斜拉索的张拉力不变;In this calculation and analysis, the tension timing of the stay cables has changed, but the tension of the stay cables remains unchanged;

在标准梁段施工过程中当斜拉索滞后张拉之后,受力最不利工况为各梁段移挂篮之后的工况。5至16号梁段移挂篮之后的最大、最小应力计算结果如附图5表格所示,由表可知,各工况最大拉应力为 0.1MPa,最大压应力为13.6MPa,在施工过程中主梁受力安全;In the construction process of the standard beam section, when the stay cables are stretched behind, the most unfavorable working condition is the working condition after each beam section is moved to the hanging basket. The maximum and minimum stress calculation results of No. 5 to No. 16 beam sections after moving the hanging basket are shown in the table of attached drawing 5. It can be seen from the table that the maximum tensile stress of each working condition is 0.1MPa, and the maximum compressive stress is 13.6MPa. During the construction process Main girder stress safety;

由以上计算结果可知,将n号梁段斜拉索的张拉时机改到n+1 号梁段移挂篮之后是可行的,施工过程中主梁应力安全。From the above calculation results, it can be seen that it is feasible to change the tensioning timing of the stay cables of the nth beam section to after the n+1 beam section is moved to the hanging basket, and the stress of the main girder is safe during the construction process.

在成桥状态下主梁应力虽与原工序有所差别,通过对斜拉索的张拉索力进行相应的变化,则可以做到成桥状态下的应力与原工序基本相同。Although the stress of the main girder in the completed bridge state is different from the original process, the stress in the completed bridge state can be basically the same as the original process by changing the tension force of the stay cables accordingly.

故而本发明的步骤在改变工序后,加快了施工工期,且不影响桥梁安全。Therefore, after the steps of the present invention are changed, the construction period is accelerated without affecting the safety of the bridge.

以上是结合具体的实施例对本发明所作的详细说明,不能认定本发明的具体实施方式只局限于这些说明。对于本发明所属技术领域的普通技术人员来说,在不脱离本发明构思的前提下做出若干等同替代或明显变型,而且性能或用途相同,都应当视为属于本发明由所提交的权利要求书确定的专利保护范围。The above is a detailed description of the present invention in conjunction with specific embodiments, and it cannot be assumed that the specific embodiments of the present invention are limited to these descriptions. For those of ordinary skill in the technical field to which the present invention belongs, several equivalent substitutions or obvious modifications are made without departing from the concept of the present invention, and the performance or use is the same, all should be regarded as belonging to the present invention by the submitted claims The scope of patent protection determined by the book.

Claims (7)

1. A bridge stay cable lag tensioning construction process is characterized in that: the construction process comprises the following steps:
a) Mounting a hanging basket; b) Prepressing the hanging basket; c) Mounting a bottom die and an outer die, mounting a steel bar in a prestressed manner, and mounting a similar template; d) Pouring and maintaining concrete; e) Stretching the three-way prestressed tendons; f) Grouting and sealing the anchor; g) The next section of forward construction of the hanging basket; h) And the beam end is provided with a stay cable for tensioning.
2. The bridge stay cable lag tensioning construction process according to claim 1, characterized in that: step a), mounting all structural members of a hanging basket in the hanging basket by using a tower crane and a crawler crane, integrally hoisting a main truss after the main truss is integrally assembled on the ground, and then mounting a bottom basket system and a side system; the method comprises the following specific steps: the method comprises the following steps of installing a track system, integrally hoisting the main truss system after splicing the main truss system on the ground, installing an anchoring system, installing a front upper crossbeam, installing a front suspension and a rear suspension of a cradle, installing a bottom basket system of the cradle, installing a cradle platform system and installing a cradle hydraulic system.
3. The bridge stay cable lag tensioning construction process according to claim 1, characterized in that: the loading mode of the step b) and the hanging basket prepressing is to divide the loading into four times: 0%, 80%, 100% and 110%, after each loading, carrying out settlement observation on the hanging basket, carrying out next loading when the average value of the settlement amount of 24 hours is less than 2mm, wherein the last stage of stabilization time is 72 hours, and if the settlement is not stable, continuing to carry out load pre-pressing until the deformation of the bracket tends to be stable and stops;
the loading sequence is that the loading is carried out from the center of the pier to two sides in sequence, and the loading is carried out from near to far, front to back and left to right symmetrically, and a bottom plate and a web plate are ballasted firstly;
the pre-pressing measuring points are arranged at the main truss, the guide beam, the front and rear lower cross beams and the longitudinal beam;
the observation method comprises the steps of carrying out elevation measurement before prepressing, step loading, after all loading of prepressing load and after unloading, recognizing and recording measurement results of all the measuring points, and calculating elastic deformation of the measurement results, namely measuring the elevation of the measuring points before loading to serve as initial data, monitoring the settlement of the support at intervals of 12 hours after step loading is finished, carrying out next-stage loading when the average value of the settlement difference of 12 hours of the measuring points of the support is smaller than 2mm, carrying out unloading when the average value of the settlement of 24 hours adjacent to each other after 110% of loading is smaller than 1mm or the average value of the settlement of the initial 72 hours of each monitoring point is smaller than 5mm, carrying out bilateral symmetry unloading when unloading is carried out, wherein the unloading sequence is opposite to the loading sequence, the first-stage unloading is carried out, the second-stage loading is carried out, the first-stage unloading is carried out after the second-stage loading is carried out, the elevation of each measuring point is observed once after the unloading is carried out for 6 hours, and after the prepressing is finished, calculating the elastic and inelastic values of the cradle according to the obtained data, and calculating formula is as follows: the inelastic deformation value = elevation before loading-elevation after unloading, and the elastic deformation value = elevation after unloading-elevation before unloading;
after the loading is finished, unloading can be carried out after the cradle is confirmed to be stable and various data observation is finished.
4. The bridge stay cable lag tensioning construction process according to claim 1, characterized in that: step g) the next section of the forward movement construction of the hanging basket, namely, the hanging basket is moved for the first time or the rail is designed to be used in a front-back reversing way, the position of the forward movement rail of the hanging basket needs to be accurately measured, a rail pad beam and the rail need to be laid or reversed according to the design drawing, the rail needs to be lengthened, the two rails are connected into a whole by using bolts and two connecting plates, the rail is anchored by using the vertical fine-rolled thread steel of a box girder and a rail pressing beam, the rail installation is completed, the rail ensures the top surface to be horizontal, a jack is slowly placed after the rail is moved forward in place, a front support is acted on the rail to complete the forward movement operation of the rail, then, 1 suspender is respectively arranged at the two sides of the parallel truss to suspend a rear lower cross beam, the suspension rod pad beams on two sides of the flat coupling are temporarily spot-welded on a lower flat rod or an upper flat rod of a flat coupling truss, then suspension rods anchored on other rear lower cross beams on a box girder are removed, a bottom basket rear lower cross beam is simultaneously suspended on a sliding guide beam on a side mold by using a steel wire rope and a hoist for protection, a main truss rear anchor rod is slowly loosened on a rear anchor pressing beam by using a screw jack, a left-hand fastening wheel fastens a track, the jack is withdrawn after the left-hand fastening wheel is completely stressed, the rear anchor rod is loosened, the rear anchor rod is removed in a platform at the rear end of an outer sliding beam and a box, then a pad beam is installed at the front end of the track, a piece of precision steel is threaded through the pad beam to a front support, a through type jack is installed at the rear end of the front support, the through type jack is connected with the precision steel by using a nut, and the jack is connected with an oil pump;
and finally, carrying out hanging basket walking, wherein the main truss needs to be kept to synchronously move forwards during hanging basket walking, when the left hand thread wheel walks to a rail pressing beam, firstly pressing a rail pressing beam behind the left hand thread wheel, then dismantling the front pressing beam of the left hand thread wheel, after the main truss moves forwards, waiting until a lower cross beam box indoor reserved hole, aligning a rear anchor reserved hole with a cross beam lifting appliance, a rear anchor node box and the like, then immediately anchoring a rear anchor point of the hanging basket, then installing a rear bottom basket lifting rod and a wing plate lifting rod, loosening the walking rear lifting rod, adjusting the position and the elevation of the template, then moving the rolling lifting appliance to the reserved hole, threading the lifting rod again, and waiting for next walking.
5. The bridge stay cable lag tensioning construction process according to claim 1, characterized in that: d) during concrete pouring and curing, the concrete is intensively mixed, the two cantilever ends are symmetrically poured, the webs on the two sides of the same cantilever are also symmetrically poured, the unbalanced weight of the concrete put into the warehouse cannot exceed 1/4 of the weight of the beam section, a bottom plate, a web plate and a top plate are firstly poured during concrete pouring, and the sequence of symmetrically pouring the concrete by the two webs, namely front, rear and tail parts, is followed.
6. The bridge stay cable lag tensioning construction process according to claim 1, characterized in that: the e) tensioning three-way prestressed strand is a longitudinal, transverse and vertical steel strand, the prestressed steel strands are all steel strands, the steel strands are low-relaxation high-strength prestressed steel strands, the stress is controlled by adopting tensioning stress and elongation for double control, and the tensioning is balanced and uniform;
the tensioning sequence is longitudinal prestressed beam → transverse prestressed beam, diaphragm prestressed beam → vertical prestressed beam containing cable area, the vertical prestressed beam lags behind one beam section for tensioning, and the box girder top plate cantilever secondary tensioning prestress and the vertical prestress adopt low retraction secondary tensioning prestress anchoring system.
7. The bridge stay cable lag tensioning construction process according to claim 1, characterized in that: d) pouring and curing the concrete by covering and watering; and f), grouting, wherein a secondary grouting process is adopted in anchor sealing, after grouting and plastering are finished, geotextile is immediately adopted for covering, water is sprayed above the geotextile for moisturizing, both the web plate and the bottom plate are subjected to watering maintenance with a die, after prestress tensioning and grouting are finished, when the hanging basket moves forwards, the die plate is removed, and the maintenance time is not less than 7 days.
CN202210989142.XA 2022-08-17 2022-08-17 Bridge stay cable lag tensioning construction process Pending CN115305836A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210989142.XA CN115305836A (en) 2022-08-17 2022-08-17 Bridge stay cable lag tensioning construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210989142.XA CN115305836A (en) 2022-08-17 2022-08-17 Bridge stay cable lag tensioning construction process

Publications (1)

Publication Number Publication Date
CN115305836A true CN115305836A (en) 2022-11-08

Family

ID=83863691

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210989142.XA Pending CN115305836A (en) 2022-08-17 2022-08-17 Bridge stay cable lag tensioning construction process

Country Status (1)

Country Link
CN (1) CN115305836A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100969005B1 (en) * 2009-11-06 2010-07-09 동아대학교 산학협력단 Constructing method of suspension bridge and temporary cable therefor
CN111455855A (en) * 2020-04-16 2020-07-28 中交一公局第四工程有限公司 Construction process of main bridge of double-tower single-cable-plane short-tower cable-stayed bridge

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100969005B1 (en) * 2009-11-06 2010-07-09 동아대학교 산학협력단 Constructing method of suspension bridge and temporary cable therefor
CN111455855A (en) * 2020-04-16 2020-07-28 中交一公局第四工程有限公司 Construction process of main bridge of double-tower single-cable-plane short-tower cable-stayed bridge

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
吴小军;邹力;: "洪溪特大桥"斜拉索滞后张拉"施工技术", 世界桥梁, no. 05, 28 September 2020 (2020-09-28), pages 3 *
张巍;胡成;郑报文;: "有索区挂篮前移顺序对矮塔斜拉桥施工影响分析", 安徽建筑工业学院学报(自然科学版), no. 03, 15 June 2012 (2012-06-15) *
高安荣;许鹏;闫石;刘秀丽;: "汉江五桥主桥超宽断面箱梁悬浇挂篮设计与施工关键技术", 公路交通科技(应用技术版), no. 10, 15 October 2013 (2013-10-15) *

Similar Documents

Publication Publication Date Title
JP7429940B2 (en) Construction method of steel concrete main girder of cable-stayed bridge
CN101476291B (en) Segment-assembling simply supported box girder movable falsework construction method
CN102912738B (en) Overall prepressing device for hanging basket
CN111926720A (en) Construction method suitable for continuous steel-structure cantilever beam closure in loess area
CN208815424U (en) A kind of bridge descending hanging basket
CN110528402B (en) Construction method of ultra-wide box girder multi-truss-piece combined hanging basket
CN110331668A (en) A kind of back-cable-free cable-stayed bridge inclined in two-way V-shaped bridge tower construction method
CN113550237B (en) A hanging basket used for cantilever casting of continuous beams
CN108004927B (en) Double-limb triangular hanging basket and construction method for cantilever beam section of large-span continuous rigid frame bridge
CN101224856A (en) Large-span heavy-duty cable crane and its installation method
CN204690605U (en) The self-propelled triangular truss hanging basket of large span beam bridge
CN106284080A (en) Continuous rigid frame aqueduct closure segment construction method
CN110453613B (en) Full-section one-step suspension casting construction method for large-span beam bridge box girder
CN201172597Y (en) Large-span heavy-duty cable crane
CN104631343A (en) Self-travelling diamond-shaped pin-connected truss-type form traveler structure and form traveler travelling and constructing method
CN107034791A (en) A kind of assembling method of Cantilever Casting Construction Hanging Basket
CN104631333A (en) Moving hanger frame and method for small cross beam, small longitudinal beam and bridge deck slab cast-in-situ construction of arch bridge
CN107905124B (en) A kind of symmetrical expression rigid frame-continuous girder construction technology
CN111485500A (en) Transverse lengthening reinforcing construction method and structure for retreating and dismantling of rhombic hanging basket
CN111074795A (en) Construction method for pouring continuous beam in cantilever mode spanning existing railway
CN107905111B (en) A kind of construction technology of rigid frame continuous beam side span
CN101481903B (en) The method of erecting the main truss of the suspension bridge in mountainous area by reversing the cable-span crane
CN209468703U (en) Beams of concrete and steel box-girder general-purpose construction device
CN105484166B (en) A kind of ladder type masts type cantilever loop wheel machine
CN212714544U (en) Rhombus is hung basket and is retreated and demolishd horizontal extension reinforcement construction structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination