[go: up one dir, main page]

CN115235417A - Monitoring point setting method based on angle between stacked tunnels - Google Patents

Monitoring point setting method based on angle between stacked tunnels Download PDF

Info

Publication number
CN115235417A
CN115235417A CN202210859704.9A CN202210859704A CN115235417A CN 115235417 A CN115235417 A CN 115235417A CN 202210859704 A CN202210859704 A CN 202210859704A CN 115235417 A CN115235417 A CN 115235417A
Authority
CN
China
Prior art keywords
monitoring
angle
subsidence
frequency
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210859704.9A
Other languages
Chinese (zh)
Other versions
CN115235417B (en
Inventor
江华
江玉生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology Beijing CUMTB
Original Assignee
China University of Mining and Technology Beijing CUMTB
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology Beijing CUMTB filed Critical China University of Mining and Technology Beijing CUMTB
Priority to CN202210859704.9A priority Critical patent/CN115235417B/en
Publication of CN115235417A publication Critical patent/CN115235417A/en
Application granted granted Critical
Publication of CN115235417B publication Critical patent/CN115235417B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C5/00Measuring height; Measuring distances transverse to line of sight; Levelling between separated points; Surveyors' levels
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明涉及一种基于叠落式隧道之间的角度的监测点设置方法,所述方法至少包括:基于与所述监测断面对应的叠落式隧道之间的净间距和/或角度确定设置于所述监测断面的监测点的数量以及分布范围,其中,在两叠落隧道之间的角度在40°~60°这一区间时,若两隧道的净间距固定,随着两叠落隧道之间的角度的减小,在沉降影响的范围内设置更多的监测点,并且加大检测频率。针对现有技术中的各个监测面的监测点数量均大于五个并导致无效数据多的缺陷,本发明基于与监测断面对应的叠落式隧道之间的净间距和/或角度确定设置于监测断面的监测点的数量,减少无效监测点的布置,减少大量无效数据的采集和储存。

Figure 202210859704

The present invention relates to a method for setting monitoring points based on the angle between stacked tunnels. The method includes at least: determining the setting of monitoring points based on the clear spacing and/or angle between stacked tunnels corresponding to the monitoring section. The number and distribution range of the monitoring points of the monitoring section, wherein, when the angle between the two stacking tunnels is in the range of 40° to 60°, if the clear distance between the two tunnels is fixed, as the distance between the two stacking tunnels is fixed. To reduce the angle between the two, set up more monitoring points within the range of settlement influence, and increase the detection frequency. In view of the defect in the prior art that the number of monitoring points on each monitoring surface is greater than five and leads to a large number of invalid data, the present invention is based on the clear spacing and/or angle between the stacked tunnels corresponding to the monitoring sections. The number of monitoring points on the cross-section reduces the arrangement of invalid monitoring points, and reduces the collection and storage of a large amount of invalid data.

Figure 202210859704

Description

一种基于叠落式隧道之间的角度的监测点设置方法A monitoring point setting method based on the angle between stacked tunnels

本申请是申请号为202210327480.7,申请日为2022年3月31日,发明名称为一种上下叠落式隧道完全叠落段监测装置及方法,专利类型为发明的专利申请的分案申请。The application number is 202210327480.7, the application date is March 31, 2022, the name of the invention is a device and method for monitoring the complete stacking section of an upper and lower stacking tunnel, and the patent type is a divisional application of the patent application for invention.

技术领域technical field

本发明涉及叠落式隧道施工技术领域,尤其涉及一种基于叠落式隧道之间的角度的监测点设置方法。The invention relates to the technical field of stacked tunnel construction, in particular to a monitoring point setting method based on the angle between stacked tunnels.

背景技术Background technique

地铁隧道施工对地表的扰动是不可避免的,各种工法中盾构工法对地表的扰动相对较小,由于地铁区间施工大都处于城市相对繁华、人口密集地区,地表变形大于变形临界值就会对周边高层建筑、道路、地下管线等产生较大影响,因此对盾构隧道区间进行监测来反馈施工显得尤为重要。The disturbance to the surface of the subway tunnel construction is unavoidable. Among the various construction methods, the shield construction method has relatively little disturbance to the surface. Since most of the subway construction is located in the relatively prosperous and densely populated areas of the city, the surface deformation is greater than the deformation critical value. The surrounding high-rise buildings, roads, underground pipelines, etc. have a great impact, so it is particularly important to monitor the shield tunnel section to feedback the construction.

随着地下空间的开发和利用,越来越多的隧道开始采用上下叠落式布置,而盾构上下叠落施工对上方地表影响范围及大小与正常平行隧道完全不同,并且无既有经验参考。With the development and utilization of underground space, more and more tunnels begin to be arranged in the upper and lower layers. However, the impact range and size of the shield construction on the upper surface are completely different from those of normal parallel tunnels, and there is no existing experience to refer to. .

盾构推进过程中,其上部建筑或者人们就会受到其所引起的地基或者地表的振动以及由此产生的二次振动的影响,特别会对古、旧建筑物的结构安全带来影响,另外,可能会使人体感到不同程度的不适从而影响人们的身体健康,干扰人们的正常生活,尤其上行隧道施工时对上部的影响更大。In the process of shield tunneling, its superstructure or people will be affected by the vibration of the foundation or the surface and the secondary vibration caused by it, which will especially affect the structural safety of ancient and old buildings. , may make the human body feel different degrees of discomfort and affect people's health and interfere with people's normal life, especially when the upward tunnel construction has a greater impact on the upper part.

现有技术公开了部分相关的技术方案,但是没有解决上述技术问题。The prior art discloses some related technical solutions, but does not solve the above technical problems.

例如,中国专利文献CN103277110 A公开了一种叠落式盾构隧道的施工方法,施工步骤包括:下行盾构隧道掘进施工,隧道结构采用加强型管片;下行隧道在二次注浆孔中通过注浆管向上行隧道和下行隧道之间的所夹土体进行注浆;上行隧道施工前在下行隧道内设置台车支撑体系来保护下行隧道;上行盾构隧道掘进施工,施工过程中下行隧道支撑台车保持与上行隧道掘进同步跟进;上行隧道在二次注浆孔中通过注浆管向上行隧道和下行隧道之间的所夹土体进行注浆。For example, Chinese patent document CN103277110 A discloses a construction method of a stacked shield tunnel. The construction steps include: excavation and construction of a downward shield tunnel, and the tunnel structure adopts a reinforced segment; the downward tunnel passes through a secondary grouting hole. The grouting pipe is used for grouting the sandwiched soil between the upward tunnel and the downward tunnel; before the construction of the upward tunnel, a trolley support system is set in the downward tunnel to protect the downward tunnel; during the construction of the upward shield tunnel, the downward tunnel is constructed during the construction. The supporting trolley keeps following up with the tunnel excavation; the ascending tunnel is grouted to the sandwiched soil between the ascending tunnel and the descending tunnel through the grouting pipe in the secondary grouting hole.

例如,中国专利文献CN105332710 A公开了一种适用于软弱地质下小净间距长距离的上下重叠隧道施工方法,所述的上下重叠隧道包括隧道直径相同、隧道长度大致相等的上洞隧道和下洞隧道,上洞隧道和下洞隧道均分别均是以管片形成隧道结构,上洞隧道和下洞隧道之间的垂直净间距小于0.7D(盾构直径),隧道长度大于1000m,其盾构施工方法是按常规盾构施工方法完成下洞隧道后,通过盾构高空始发平台、上下隧道夹层土体深孔注浆加固、下洞隧道支撑钢环加固、盾构高空接收平台等措施,来减少上洞隧道的盾构施工对成型下洞隧道的影响和重叠隧道沉降二次叠加效应,确保下洞隧道变形和地面沉降可控。For example, Chinese patent document CN105332710 A discloses a construction method for upper and lower overlapping tunnels with small clear spacing and long distances in soft geology. The tunnel, the upper tunnel and the lower tunnel are all formed by segmented tunnel structures respectively. The vertical clear distance between the upper tunnel and the lower tunnel is less than 0.7D (shield diameter), and the length of the tunnel is greater than 1000m. The construction method is to complete the lower tunnel according to the conventional shield construction method, through the shield high-altitude starting platform, the upper and lower tunnel interlayer soil deep hole grouting reinforcement, the lower tunnel supporting steel ring reinforcement, the shield high-altitude receiving platform and other measures. To reduce the impact of the shield construction of the upper tunnel on the forming of the lower tunnel and the secondary superposition effect of the overlapping tunnel settlement, to ensure that the deformation and ground settlement of the lower tunnel are controllable.

上述现有技术均没有涉及完全叠落段的监测点埋设的问题,因此也没有解决本发明提出的问题:如何监测并减少叠落隧道施工的振动影响。None of the above-mentioned prior art involves the problem of burying the monitoring points of the completely overlapping section, and therefore does not solve the problem proposed by the present invention: how to monitor and reduce the vibration influence of the construction of the overlapping tunnel.

此外,一方面由于对本领域技术人员的理解存在差异;另一方面由于申请人做出本发明时研究了大量文献和专利,但篇幅所限并未详细罗列所有的细节与内容,然而这绝非本发明不具备这些现有技术的特征,相反本发明已经具备现有技术的所有特征,而且申请人保留在背景技术中增加相关现有技术之权利。In addition, on the one hand, there are differences in the understanding of those skilled in the art; on the other hand, because the applicant has studied a large number of documents and patents when making the present invention, but due to space limitations, all details and contents are not listed in detail, but this is by no means The present invention does not possess the features of the prior art, on the contrary, the present invention already possesses all the features of the prior art, and the applicant reserves the right to add relevant prior art to the background art.

发明内容SUMMARY OF THE INVENTION

针对现有技术之不足,本发明提供了一种上下叠落式隧道完全叠落段监测方法,基于叠落式隧道之间的叠落度选取与叠落式隧道的轴线垂直的至少一个竖直面作为叠落式隧道的监测断面,基于与所述监测断面对应的叠落式隧道之间的净间距和/或角度确定设置于该监测断面的监测点的数量,,基于所述监测点发送的沉降数据进行沉降数据处理与分析。In view of the deficiencies of the prior art, the present invention provides a method for monitoring the complete overlapping section of an upper and lower overlapping tunnel. Based on the overlapping degree between the overlapping tunnels, at least one vertical axis perpendicular to the axis of the overlapping tunnel is selected. As the monitoring section of the stacked tunnel, the number of monitoring points set on the monitoring section is determined based on the clear distance and/or angle between the stacked tunnels corresponding to the monitoring section, and based on the monitoring points sent The settlement data are processed and analyzed.

本发明全程监测叠落式隧道施工过程中造成的地表沉降影响,不仅可以收集先始发隧道造成的地表沉降数据,同样可以监测后始发隧道对先始发隧道以及地表沉降的影响。通过监测断面的选取和监测点的布置,可以收集到一个监测断面到另一个监测断面的横向的沉降数据和沿监测断面布置的监测点的纵向监测数据,形成立体式的监测,检测结果更加准确。The present invention monitors the influence of the surface subsidence caused by the construction of the stacked-drop tunnel in the whole process, and not only can collect the data of the surface subsidence caused by the first-start tunnel, but also can monitor the influence of the latter-start tunnel on the first-start tunnel and the surface settlement. Through the selection of monitoring sections and the arrangement of monitoring points, the lateral settlement data from one monitoring section to another monitoring section and the longitudinal monitoring data of monitoring points arranged along the monitoring section can be collected to form a three-dimensional monitoring, and the detection results are more accurate. .

优选地,所述叠落度与至少两个隧道之间的隧道轴线的水平距离、垂直距离和半径相关,S=(L,H,R1,R2),其中,S表示叠落度,L表示隧道轴线的水平距离,H表示隧道轴线的垂直距离,R1表示第一隧道的半径,R2表示第二隧道的半径。Preferably, the stacking degree is related to the horizontal distance, vertical distance and radius of the tunnel axis between at least two tunnels, S=(L, H, R 1 , R 2 ), wherein S represents the stacking degree, L represents the horizontal distance of the tunnel axis, H represents the vertical distance of the tunnel axis, R 1 represents the radius of the first tunnel, and R 2 represents the radius of the second tunnel.

优选地,所述叠落式隧道之间的净间距和/或角度与最大沉降值相关,Preferably, the clear spacing and/or angle between the stacked tunnels is related to the maximum settlement value,

基于隧道之间的净间距和/或角度与最大沉降值的相关关联来设置监测点的数量以及分布范围。The number and distribution of monitoring points are set based on the correlation between the clear spacing and/or angle between the tunnels and the maximum settlement value.

优选地,所述方法还包括:基于掘进面与所述监测断面的第一和/或第二距离的变化调节沉降数据的收集频率。Preferably, the method further comprises: adjusting the frequency of collection of settlement data based on changes in the first and/or second distances between the driving face and the monitoring section.

优选地,在掘进面与所述监测断面的第一和/或第二距离不大于第一阈值时,沉降数据的收集频率为第一频率;在掘进面与所述监测断面的第一和/或第二距离大于第一阈值且不大于第二阈值时,沉降数据的收集频率为第二频率;在掘进面与所述监测断面的第一和/或第二距离大于第二阈值时,沉降数据的收集频率为第三频率。Preferably, when the first and/or second distances between the driving face and the monitoring section are not greater than the first threshold, the collection frequency of the settlement data is the first frequency; when the first and/or second distances between the driving face and the monitoring section are Or when the second distance is greater than the first threshold and not greater than the second threshold, the collection frequency of the settlement data is the second frequency; when the first and/or second distance between the driving surface and the monitoring section is greater than the second threshold, the settlement is The frequency of data collection is the third frequency.

优选地,所述方法还包括:在地表沉降稳定的情况下,调节沉降数据的收集频率为第四频率。Preferably, the method further comprises: adjusting the collection frequency of the subsidence data to a fourth frequency under the condition that the surface subsidence is stable.

优选地,所述方法还包括:在地表沉降出现异常的情况下,沉降数据的收集频率增大。Preferably, the method further comprises: in the case of abnormal ground subsidence, increasing the frequency of collecting subsidence data.

本发明基于掘进面的变化动态调节各个监测断面的数据收集频率,提高数据的有效利用,减少对于数据分析作用较小的数据的采集。The invention dynamically adjusts the data collection frequency of each monitoring section based on the change of the excavation surface, improves the effective utilization of the data, and reduces the collection of data that has little effect on data analysis.

优选地,所述方法还包括:基于地表沉降的沉降—时间的分布拟合曲线预测最大沉降量。Preferably, the method further comprises: predicting the maximum subsidence amount based on a subsidence-time distribution fitting curve of surface subsidence.

优选地,所述地表沉降达到稳定的条件至少包括:Preferably, the conditions for the surface subsidence to be stable at least include:

道路及地表沉降速度有明显减缓趋势;The subsidence speed of road and surface has a clear trend of slowing down;

道路及地表沉降收敛速度小于0.01~0.04mm/天;The convergence speed of road and surface subsidence is less than 0.01~0.04mm/day;

收敛量达到总收敛量的80%及以上。The amount of convergence reaches 80% and above of the total amount of convergence.

通过预测最大沉降量,本发明能够在沉降较大的部位进行加固,以保证盾构施工过程的正常进行,防止对周边建筑物产生较大的影响。本发明在整个施工过程中,可以全程进行监测,以较小的资金投入,避免施工过程中出现较大的施工隐患。By predicting the maximum settlement amount, the present invention can reinforce the parts with large settlement, so as to ensure the normal progress of the shield construction process and prevent the surrounding buildings from being greatly affected. The present invention can monitor the whole process in the whole construction process, and can avoid large construction hidden dangers in the construction process with small capital investment.

本发明还提供一种上下叠落式隧道完全叠落段监测装置,至少包若干监测单元,所述监测单元在埋入地下后形成监测地表沉降的监测点,监测点所在的监测断面是基于叠落式隧道之间的叠落度选取的与叠落式隧道的轴线垂直的至少一个竖直面,所述监测断面内的所述监测点的数量是基于与所述监测断面对应的叠落式隧道之间的净间距和/或角度确定的。其中监测单元为能够监测地表沉降的传感器。The present invention also provides a monitoring device for a complete stacking section of an upper and lower stacking tunnel, which includes at least a number of monitoring units, the monitoring units are buried underground to form monitoring points for monitoring surface subsidence, and the monitoring sections where the monitoring points are located are based on stacking. At least one vertical plane perpendicular to the axis of the stacked tunnel is selected for the overlapping degree between the drop tunnels, and the number of the monitoring points in the monitoring section is based on the stacked drop corresponding to the monitoring section. Clear spacing and/or angle between tunnels. The monitoring unit is a sensor capable of monitoring surface subsidence.

本发明的监测装置仅需埋设一次监测点,便可监测先后始发隧道造成的地表沉降情况,形成立体监测,并通过对数据的处理与分析,结合具体的施工情况,可判断造成地表沉降的原因,并采取相关的措施,减小地表沉降,同时可以做到全程监测,进一步增强信息化施工的效果,为施工与监理单位提供沟通渠道,评估土体的安全状况,提出合理化的施工建议措施,以保障地铁项目的安全建设。The monitoring device of the present invention only needs to bury the monitoring point once, and can monitor the surface subsidence caused by successively starting tunnels, forming a three-dimensional monitoring, and through the processing and analysis of the data, combined with the specific construction situation, can determine the cause of the surface subsidence. and take relevant measures to reduce the surface subsidence, and at the same time, it can monitor the whole process, further enhance the effect of informatization construction, provide communication channels for construction and supervision units, evaluate the safety status of the soil, and put forward reasonable construction suggestions and measures , in order to ensure the safe construction of the subway project.

本发明还提供一种基于叠落式隧道之间的角度的监测点设置方法,所述方法至少包括:基于与所述监测断面对应的叠落式隧道之间的净间距和/或角度确定设置于所述监测断面的监测点的数量以及分布范围,其中,在两叠落隧道之间的角度在40°~60°这一区间时,若两隧道的净间距固定,随着两叠落隧道之间的角度的减小,在沉降影响的范围内设置更多的监测点,并且加大检测频率。The present invention also provides a method for setting monitoring points based on the angle between the stacked tunnels, the method at least comprising: determining the setting based on the clear distance and/or the angle between the stacked tunnels corresponding to the monitoring sections The number and distribution range of the monitoring points on the monitoring section, wherein, when the angle between the two stacking tunnels is in the range of 40° to 60°, if the clear distance between the two tunnels is fixed, with the two stacking falling tunnels. The angle between them is reduced, more monitoring points are set up within the range affected by the settlement, and the detection frequency is increased.

优选地,所述方法还包括:在两叠落隧道之间的角度在40°~60°这一区间时,若两隧道的角度不变,随着净间距的增大设置更多的监测点,所述监测点设置的密度和检测频率相应减少。Preferably, the method further includes: when the angle between the two stacked tunnels is in the range of 40° to 60°, if the angle of the two tunnels remains unchanged, setting more monitoring points as the clear distance increases , the density and detection frequency of the monitoring points are correspondingly reduced.

优选地,所述方法还包括:在两叠落隧道之间的角度为0°的第一监测断面,所述第一监测断面设置两个或四个监测点。Preferably, the method further includes: setting a first monitoring section with an angle of 0° between the two stacked tunnels, and setting two or four monitoring points on the first monitoring section.

优选地,所述方法还包括:监测先始发隧道在盾构过程中造成的地表沉降并收集地表沉降的相关数据;监测后始发隧道盾构过程中造成的二次振动影响并收集地表沉降的相关数据;基于掘进面与监测断面的第一和/或第二距离的变化调节沉降数据的收集频率。Preferably, the method further includes: monitoring the surface subsidence caused by the first-start tunnel during the shield tunneling process and collecting relevant data of the surface subsidence; monitoring the secondary vibration effect caused by the second-start tunnel during the shield tunneling process and collecting the surface subsidence The frequency of collection of settlement data is adjusted based on changes in the first and/or second distances between the driving face and the monitoring section.

优选地,所述方法还包括:在掘进面与监测断面的第一和/或第二距离不大于第一阈值时,沉降数据的收集频率为第一频率;在掘进面与所述监测断面的第一和/或第二距离大于第一阈值且不大于第二阈值时,沉降数据的收集频率为第二频率;在掘进面与所述监测断面的第一和/或第二距离大于第二阈值时,沉降数据的收集频率为第三频率。Preferably, the method further includes: when the first and/or second distances between the driving surface and the monitoring section are not greater than a first threshold, the collection frequency of the settlement data is the first frequency; When the first and/or second distances are greater than the first threshold and not greater than the second threshold, the collection frequency of the settlement data is the second frequency; the first and/or second distances between the driving surface and the monitoring section are greater than the second At the threshold, the collection frequency of sedimentation data is the third frequency.

优选地,所述方法还包括:在地表沉降稳定的情况下,调节沉降数据的收集频率为第四频率;第四频率为每月一次。Preferably, the method further includes: when the surface subsidence is stable, adjusting the collection frequency of the subsidence data to a fourth frequency; the fourth frequency is once a month.

优选地,所述方法还包括:基于地表沉降的沉降—时间的分布拟合曲线预测最大沉降量,在地表沉降出现异常的情况下,沉降数据的收集频率增大。Preferably, the method further comprises: predicting the maximum subsidence amount based on the subsidence-time distribution fitting curve of the surface subsidence, and in the case of abnormal surface subsidence, the collection frequency of the subsidence data is increased.

优选地,所述方法还包括:所述地表沉降达到稳定的条件至少包括:Preferably, the method further includes: the conditions for the surface subsidence to be stable at least include:

道路及地表沉降速度有明显减缓趋势;道路及地表沉降收敛速度小于0.01~0.04mm/天;收敛量达到总收敛量的80%及以上。The subsidence speed of road and surface has a clear trend of slowing down; the convergence speed of road and surface subsidence is less than 0.01-0.04mm/day; the convergence amount reaches 80% and above of the total convergence amount.

优选地,所述第一阈值为20m,所述第一频率为每天一次;所述第二阈值为50m,所述第二频率为两天一次;所述第三频率为每周一次。Preferably, the first threshold is 20m, and the first frequency is once a day; the second threshold is 50m, and the second frequency is once every two days; and the third frequency is once a week.

优选地,在叠落段共设置6个监测断面;第一监测断面设置有四个监测点,第二监测断面设置有十二个监测点,第三监测断面设置有两个监测点,第四监测断面设置有十四个监测点,第五监测断面设置有两个监测点,第六监测断面设置有两个监测点。Preferably, a total of 6 monitoring sections are set in the stacking section; the first monitoring section is set with four monitoring points, the second monitoring section is set with twelve monitoring points, the third monitoring section is set with two monitoring points, and the fourth monitoring section is set with two monitoring points. Fourteen monitoring points are set on the monitoring section, two monitoring points are set on the fifth monitoring section, and two monitoring points are set on the sixth monitoring section.

附图说明Description of drawings

图1是本发明提供的叠落段地表沉降监测点的布置示意图;Fig. 1 is a schematic diagram of the layout of the monitoring points of surface subsidence in the stacking section provided by the present invention;

图2是本发明提供的基准点的埋设示意图;Fig. 2 is the buried schematic diagram of the reference point provided by the present invention;

图3是本发明提供的监测工作基点的放大示意图;Fig. 3 is the enlarged schematic diagram of the monitoring work base point provided by the present invention;

图4是本发明提供的叠落度划分要素的示意图;Fig. 4 is a schematic diagram of a stacking degree dividing element provided by the present invention;

图5是本发明提供的各个监测断面的沉降量曲线的示意图;Fig. 5 is the schematic diagram of the settlement curve of each monitoring section provided by the present invention;

图6是本发明提供的第一隧道施工D1断面纵向沉降示意图;6 is a schematic diagram of the longitudinal settlement of the first tunnel construction D1 section provided by the present invention;

图7是本发明提供的第一隧道施工D2断面纵向沉降示意图;7 is a schematic diagram of the longitudinal settlement of the first tunnel construction D2 section provided by the present invention;

图8是本发明提供的第一隧道施工D3断面纵向沉降示意图;8 is a schematic diagram of the longitudinal settlement of the first tunnel construction D3 section provided by the present invention;

图9是本发明提供的第一隧道施工D4断面纵向沉降示意图;9 is a schematic diagram of the longitudinal settlement of the first tunnel construction D4 section provided by the present invention;

图10是本发明提供的第一隧道施工D5断面纵向沉降示意图;10 is a schematic diagram of the longitudinal settlement of the first tunnel construction D5 section provided by the present invention;

图11是本发明提供的第一隧道施工D6断面纵向沉降示意图。Figure 11 is a schematic diagram of the longitudinal settlement of the first tunnel construction D6 section provided by the present invention.

附图标记列表List of reference signs

1:第一隧道;2:第二隧道;101:保护管;102:外管;103:悬空卡子;104:标杆;105:钻孔;106:基点底座;DB1-1:第一监测断面第一监测点;DB1-4:第一监测断面第四监测点;DB2-1:第二监测断面第一监测点;DB2-12:第二监测断面第十二监测点;DB3-1:第三监测断面第一监测点;DB3-2:第三监测断面第二监测点;DB4-1:第四监测断面第一监测点;DB4-14:第四监测断面第十四监测点;DB5-1:第五监测断面第一监测点;DB5-2:第五监测断面第二监测点;DB6-1:第六监测断面第一监测点;DB6-2:第六监测断面第二监测点。1: The first tunnel; 2: The second tunnel; 101: Protection pipe; 102: Outer pipe; 103: Hanging clip; 104: Benchmark; 105: Drill hole; 106: Base point; One monitoring point; DB1-4: the fourth monitoring point of the first monitoring section; DB2-1: the first monitoring point of the second monitoring section; DB2-12: the twelfth monitoring point of the second monitoring section; DB3-1: the third monitoring point The first monitoring point of the monitoring section; DB3-2: the second monitoring point of the third monitoring section; DB4-1: the first monitoring point of the fourth monitoring section; DB4-14: the fourteenth monitoring point of the fourth monitoring section; DB5-1 : the first monitoring point of the fifth monitoring section; DB5-2: the second monitoring point of the fifth monitoring section; DB6-1: the first monitoring point of the sixth monitoring section; DB6-2: the second monitoring point of the sixth monitoring section.

具体实施方式Detailed ways

下面结合附图进行详细说明。The following detailed description is given in conjunction with the accompanying drawings.

基于现有技术的不足,本发明提供一种上下叠落式隧道完全叠落段监测方法及装置。本发明还能够提供一种叠落式隧道完全叠落段的动态立体监测方法及装置。Based on the deficiencies of the prior art, the present invention provides a method and device for monitoring the complete overlapping section of an upper and lower overlapping tunnel. The present invention can also provide a dynamic three-dimensional monitoring method and device for a fully stacked section of a stacked tunnel.

本发明的上下叠落式隧道完全叠落段监测方法,至少包括:基于叠落式隧道之间的叠落度选取与叠落式隧道的轴线垂直的至少一个竖直面作为叠落式隧道的监测断面,基于与所述监测断面对应的叠落式隧道之间的净间距和/或角度确定设置于该监测断面的监测点的数量,基于监测点发送的沉降数据进行沉降数据处理与分析。The method for monitoring the complete overlapping section of the upper and lower stacked tunnels of the present invention at least includes: selecting at least one vertical plane perpendicular to the axis of the stacked tunnel based on the stacking degree between the stacked tunnels as the vertical plane of the stacked tunnel. For the monitoring section, the number of monitoring points set on the monitoring section is determined based on the clear spacing and/or angle between the stacked tunnels corresponding to the monitoring section, and settlement data processing and analysis are performed based on the settlement data sent by the monitoring points.

监测点所在的监测断面是根据工程实际需要确定的。The monitoring section where the monitoring point is located is determined according to the actual needs of the project.

叠落度与至少两个隧道之间的隧道轴线的水平距离、垂直距离和半径相关。如图4所示,S=(L,H,R1,R2),其中,S表示叠落度,L表示隧道轴线的水平距离,H表示隧道轴线的垂直距离,R1表示第一隧道的半径,R2表示第二隧道的半径。The degree of stacking is related to the horizontal distance, vertical distance and radius of the tunnel axis between at least two tunnels. As shown in Figure 4, S=(L, H, R 1 , R 2 ), where S represents the stacking degree, L represents the horizontal distance of the tunnel axis, H represents the vertical distance of the tunnel axis, and R 1 represents the first tunnel , and R2 represents the radius of the second tunnel.

监测断面设置的监测点的数量是基于叠落式隧道之间的净间距和/或角度确定的。The number of monitoring points set on the monitoring section is determined based on the clear spacing and/or angle between the stacked tunnels.

叠落式隧道之间的净间距和/或角度与最大沉降值相关。因此基于隧道之间的净间距和/或角度与最大沉降值的相关关联来设置监测点的数量以及分布范围。The clear spacing and/or angle between stacked tunnels is related to the maximum settlement value. The number and distribution of monitoring points are therefore set based on the correlation between the clear spacing and/or angle between the tunnels and the maximum settlement value.

具体地,按照以下的净间距和/或角度情况设置监测断面的监测点的数量。本发明中,隧道直径设置为D,

Figure BDA0003755017660000061
为2m。净间距指两个隧道横断面隧道中心连线的长度减去一个隧道直径的长度。Specifically, the number of monitoring points of the monitoring section is set according to the following clear distances and/or angles. In the present invention, the tunnel diameter is set to D,
Figure BDA0003755017660000061
is 2m. The clear distance refers to the length of the line connecting the center of the two tunnel cross-sections minus the length of one tunnel diameter.

当浅埋双孔隧道水平布置时,两隧道之间的净间距较小时,二者之间的相互影响特别大。When the shallow-buried double-hole tunnels are arranged horizontally and the clear distance between the two tunnels is small, the mutual influence between them is particularly great.

当净间距小于

Figure BDA0003755017660000062
时,地表沉降最大值会突降很多,此时隧道的设计施工将会冒很大风险,应避免设计如此小间距工况。When the clear spacing is less than
Figure BDA0003755017660000062
At this time, the maximum surface settlement will suddenly drop a lot. At this time, the design and construction of the tunnel will take great risks, and the design of such small spacing conditions should be avoided.

当净间距大于

Figure BDA0003755017660000071
时,随着净间距的增大,地表沉降最大值逐渐降低。When the clear spacing is greater than
Figure BDA0003755017660000071
, with the increase of the net distance, the maximum surface subsidence decreases gradually.

当两隧道为小间距时,随着角度增大,地表沉降最大值快速减小,在净间距为9~15m这一区域段对布置角度的改变不太敏感。When the distance between the two tunnels is small, as the angle increases, the maximum surface subsidence decreases rapidly, and it is less sensitive to the change of the arrangement angle in the area where the clear distance is 9-15m.

在净间距为

Figure BDA0003755017660000072
这一区间内,地表沉降最大值对布置角度的改变特别敏感,应尽量避免在此区域内改变两隧道的布置角度。The clear spacing is
Figure BDA0003755017660000072
In this interval, the maximum surface settlement is particularly sensitive to the change of the arrangement angle, and it should be avoided as much as possible to change the arrangement angle of the two tunnels in this area.

当净间距小于D时,地表沉降最大值对角度比较敏感。随着净间距的增大,角度对两隧道的相互影响逐渐减小。When the net distance is less than D, the maximum surface subsidence is sensitive to the angle. With the increase of the clear distance, the mutual influence of the angle on the two tunnels gradually decreases.

在角度40°~60°这一区间对双孔隧道之间相互影响比较大,特别是小间距双孔隧道。In the range of angle 40°~60°, the mutual influence between double-hole tunnels is relatively large, especially for small-spacing double-hole tunnels.

若两隧道的净间距固定,随着两隧道之间角度的减小,沉降最大值会逐渐加大,但沉降影响的范围较小,因此可以在小范围内设置更多的监测点,并且加大检测频率。If the clear distance between the two tunnels is fixed, as the angle between the two tunnels decreases, the maximum settlement value will gradually increase, but the range of settlement influence is small, so more monitoring points can be set up in a small range, and additional High detection frequency.

相应的,若两隧道的角度不变,随着净间距的增大,沉降会相应有所降低,但受施工影响的范围广,需设置更多的监测点,监测点设置的密度和检测频率也可相应减少。Correspondingly, if the angle of the two tunnels remains unchanged, with the increase of the clear distance, the settlement will be reduced accordingly, but the scope affected by the construction is wide, and more monitoring points need to be set up. The density and detection frequency of the monitoring points are set. can also be reduced accordingly.

在两个隧道同时具有净间距较小和两隧道角度在40-60之间两个因素时,此时不仅需在较小范围内设置多个监测点,并且需加大检测频率。When the clear distance between the two tunnels is small and the angle between the two tunnels is between 40-60, it is not only necessary to set up multiple monitoring points in a small range, but also to increase the detection frequency.

如图1所示,某城市地铁区间隧道第一线、第二线采用叠落式布置方式,盾构法施工。第二隧道位于下方,叠落段穿越土层主要为砂卵石层,埋深21.5~23.7m,地下水主要为层间潜水和承压水。第一隧道位于上方,主要穿越土层为粉质粘土层。第一隧道埋深13.8~15.3m。地下水主要为潜水和层间潜水。叠落段隧道垂直距离为1.95~3.3m。As shown in Figure 1, the first and second lines of a subway tunnel in a certain city are arranged in a stacked arrangement and constructed by the shield method. The second tunnel is located below, and the soil layer passing through the stacking section is mainly sand and pebble layer, with a buried depth of 21.5-23.7m, and the groundwater is mainly interlayer phreatic water and confined water. The first tunnel is located above, mainly through the soil layer of silty clay layer. The buried depth of the first tunnel is 13.8-15.3m. The groundwater is mainly phreatic and interlayer phreatic. The vertical distance of the tunnel in the stacking section is 1.95-3.3m.

盾构区间完全叠落段地表共布设36个沉降监测点。第一线叠落段穿越粉质粘土段共布设18个监测点,第二线叠落段穿越砂卵石段共布设18个监测点,监测精度为1.0mm。A total of 36 settlement monitoring points are set up on the surface of the fully overlapping section of the shield tunnel. There are a total of 18 monitoring points in the first line of the Dieluo section crossing the silty clay section, and a total of 18 monitoring points in the second line's Dieluo section crossing the sand and pebble section, with a monitoring accuracy of 1.0mm.

叠落段共设置6个监测断面。从图1的右侧至左侧依次是第一监测断面、第二监测断面、第三监测断面、第四监测断面、第五监测断面置和第六监测断面。There are 6 monitoring sections in the stacking section. From the right to the left of FIG. 1 are the first monitoring section, the second monitoring section, the third monitoring section, the fourth monitoring section, the fifth monitoring section and the sixth monitoring section.

第一监测断面设置有四个监测点,包括第一监测断面第一监测点DB1-1~DB-1-4。图1中仅标记出第一监测断面第一监测点DB1-1和第一监测断面第四监测点DB-1-4。The first monitoring section is provided with four monitoring points, including first monitoring points DB1-1 to DB-1-4 on the first monitoring section. In FIG. 1, only the first monitoring point DB1-1 of the first monitoring section and the fourth monitoring point DB-1-4 of the first monitoring section are marked.

第二监测断面设置有十二个监测点,如图1和图7所示,包括第二监测断面第一监测点DB2-1至DB2-12。图1中仅标记出第二监测断面第一监测点DB2-1和第二监测断面第十二监测点DB2-12。The second monitoring section is provided with twelve monitoring points, as shown in FIG. 1 and FIG. 7 , including the first monitoring points DB2-1 to DB2-12 on the second monitoring section. In FIG. 1, only the first monitoring point DB2-1 of the second monitoring section and the twelfth monitoring point DB2-12 of the second monitoring section are marked.

第三监测断面设置有两个监测点,如图1和图8所示,包括第三监测断面第一监测点DB3-1~第三监测断面第二监测点DB3-2。The third monitoring section is provided with two monitoring points, as shown in FIG. 1 and FIG. 8 , including the first monitoring point DB3-1 of the third monitoring section to the second monitoring point DB3-2 of the third monitoring section.

第四监测断面设置有十四个监测点,如图1和图9所示,包括第四监测断面第一监测点DB4-1~DB4-14。图1中仅标示出第四监测断面第一监测点DB4-1和第四监测断面第十四监测点DB4-14。The fourth monitoring section is provided with fourteen monitoring points, as shown in Figures 1 and 9, including the first monitoring points DB4-1 to DB4-14 on the fourth monitoring section. Only the first monitoring point DB4-1 of the fourth monitoring section and the fourteenth monitoring point DB4-14 of the fourth monitoring section are marked in FIG. 1 .

第五监测断面设置有两个监测点,如图1和图10所示,包括第五监测断面第一监测点DB5-1和第五监测断面第二监测点DB5-2。The fifth monitoring section is provided with two monitoring points, as shown in FIG. 1 and FIG. 10 , including the first monitoring point DB5-1 of the fifth monitoring section and the second monitoring point DB5-2 of the fifth monitoring section.

第六监测断面设置有两个监测点,包括第六监测断面第一监测点DB6-1和第六监测断面第二监测点DB6-2。The sixth monitoring section is provided with two monitoring points, including the first monitoring point DB6-1 of the sixth monitoring section and the second monitoring point DB6-2 of the sixth monitoring section.

例如,在第一监测断面,两隧道的角度为0,施工造成的最终沉降较大,但上下布置比左右布置跨度小,受施工影响的范围小,并且两隧道的净间距较大。此外,第一监测断面位于文物保护区,不允许设置检测点,因此在此监测断面设置两个监测点。在监测时检测频率适当增加。For example, in the first monitoring section, the angle of the two tunnels is 0, and the final settlement caused by the construction is large, but the upper and lower arrangement has a smaller span than the left and right arrangement, the scope affected by the construction is small, and the clear distance between the two tunnels is large. In addition, the first monitoring section is located in the cultural relics protection zone, and it is not allowed to set detection points, so two monitoring points are set up on this monitoring section. The frequency of detection is appropriately increased during monitoring.

在第四监测断面,两隧道的角度在较为敏感的范围,并且两隧道的净间距较小,因此在第四监测断面需要多设置几个监测点。本发明设置14个监测点,并且检测频率要增加。In the fourth monitoring section, the angle of the two tunnels is in a relatively sensitive range, and the clear distance between the two tunnels is small, so it is necessary to set up several more monitoring points in the fourth monitoring section. The present invention sets 14 monitoring points, and the detection frequency needs to be increased.

在同一监测断面的监测点,其埋设的深度是相同的。In the monitoring points of the same monitoring section, the buried depth is the same.

基准点必须埋设在施工影响范围(50m)以外,基准点埋设于由施工造成的土体沉降影响深度以下的地层中。如图3所示,工作基准点采用强制归心的水泥观测墩,每测区不少于3个,以便相互校核。The reference point must be buried outside the construction influence area (50m), and the reference point must be buried in the stratum below the influence depth of the soil settlement caused by the construction. As shown in Figure 3, the work reference point adopts the cement observation pier with forced centering, and each survey area is not less than 3, so as to check each other.

本发明中,基准点为高程已知的标准水准点。监测时通过测得各监测点与水准点(基点)的高程差,可得到各监测点的标准高程,然后与上次测得高程进行比较,差值即为该测点的沉降值。In the present invention, the reference point is a standard reference point whose elevation is known. During monitoring, by measuring the elevation difference between each monitoring point and the benchmarking point (base point), the standard elevation of each monitoring point can be obtained, and then compared with the last measured elevation, the difference is the settlement value of the measuring point.

图2示出了本发明的监测的基准点的埋设示意图。如图2所示,基准点的埋设方式包括:用钻机开凿Φ200mm的钻孔105,在完全清孔后下入保护管101。在钻孔105内设置外管102和标杆104。在保护管101与外管102的壁间回填粘土。在保护管101内摄入基准点保护底座106和标杆104。保护底座106用水泥浇筑。顶部做成圆球状,并做好测点的保护盖。FIG. 2 shows a schematic diagram of the burial of the monitored reference points of the present invention. As shown in FIG. 2 , the way of burying the reference point includes: excavating a hole 105 with a diameter of 200 mm with a drilling machine, and then lowering the protection pipe 101 after the hole is completely cleared. An outer tube 102 and a post 104 are provided within the bore hole 105 . Clay is backfilled between the walls of the protective tube 101 and the outer tube 102 . The reference point protection base 106 and the pole 104 are taken into the protection tube 101 . The protective base 106 is cemented. The top is made into a spherical shape, and the protective cover of the measuring point is made.

叠落隧道的叠落段的地表沉降的监测工作的成效性与选用的监测方法和测点的布置有直接关系。监测工作以满足现场安全管理和监控为前提,布点位置及数量应结合地质条件、地层性质、施工工艺、地表周边环境以及监测费用等因素综合考虑。地表监测点的位置首先应能保证良好地反映地表的变形特征,而且要便于仪器观测,还要尽量避免外界因素对监测点的破坏。The effectiveness of monitoring the surface subsidence of the Die-luo section of the Die-luo tunnel is directly related to the selected monitoring method and the arrangement of the measuring points. The monitoring work is based on the premise of on-site safety management and monitoring. The location and number of points should be comprehensively considered in combination with factors such as geological conditions, stratum properties, construction technology, surface surrounding environment and monitoring costs. The location of the surface monitoring points should firstly ensure that the deformation characteristics of the surface are well reflected, and it should be convenient for instrument observation, and the damage of the monitoring points should be avoided as much as possible by external factors.

因此,监测点埋设应采用标准方法和浅层设点方法。监测点用于采集地表沉降的沉降数据。Therefore, the burying of monitoring points should adopt the standard method and the shallow setting method. Monitoring points are used to collect subsidence data of surface subsidence.

标准埋设方法:首先在地面开Φ100mm的孔,打入顶部磨成椭圆形的Φ22mm螺纹钢筋。然后,在标志钢筋周围填入细砂夯实,最后在监测点上部做上铁盖加以保护。对预先探测到地中存在空洞和施工中发生塌陷的地段,采用标准方法进行地表沉降观测点埋设。Standard burying method: first, open a hole of Φ100mm on the ground, and drive in the Φ22mm threaded steel bar ground into an oval at the top. Then, fill in fine sand around the marking steel bars to tamp, and finally make an iron cover on the upper part of the monitoring point to protect it. For the sections where the existence of voids in the ground and the subsidence during construction are detected in advance, standard methods are used to bury the surface subsidence observation points.

浅层设点方法为:首先在地面用冲击钻钻出深约20cm直径12cm的孔,然后把顶部带有凸球面的φ8mm圆钢放入孔中,缝隙采用锚固剂填充。The shallow setting method is as follows: first, drill a hole with a depth of about 20cm and a diameter of 12cm with an impact drill on the ground, then put a φ8mm round steel with a convex spherical surface on the top into the hole, and fill the gap with an anchoring agent.

地表沉降控制指标为变形控制指标,监测控制标准为:最大允许沉降值为30mm,最大允许变形速率为4mm/d,地表隆起控制值为10mm。道路、地表沉降监测测点应埋设平整,防止由于高低不平影响人员及车辆通行,同时监测点埋设稳固,做好清晰标记,方便保存。The surface subsidence control index is the deformation control index. The monitoring and control standards are: the maximum allowable settlement value is 30mm, the maximum allowable deformation rate is 4mm/d, and the surface uplift control value is 10mm. Road and surface settlement monitoring and measurement points should be buried flat to prevent people and vehicles from being affected by unevenness. At the same time, the monitoring points should be firmly buried and clearly marked for easy storage.

在设置好监测点后,本发明开始在施工过程中监测地表沉降的情况。先始发隧道为第二隧道2,后始发隧道为第一隧道1。第一距离为盾构的掘进面与位于盾构前方的监测断面之间的距离。第二距离为盾构的掘进面与位于盾构后方的监测断面之间的距离。After the monitoring points are set, the present invention starts to monitor the ground subsidence during the construction process. The first originating tunnel is the second tunnel 2 , and the latter originating tunnel is the first tunnel 1 . The first distance is the distance between the driving face of the shield and the monitoring section located in front of the shield. The second distance is the distance between the driving face of the shield and the monitoring section behind the shield.

第一,监测先始发隧道在盾构过程中造成的地表沉降,收集地表沉降的相关数据。First, monitor the surface subsidence caused by the first-start tunnel during the shield tunneling process, and collect relevant data on surface subsidence.

第二,监测后始发隧道盾构过程中造成的二次振动影响,收集地表沉降的相关数据。Second, monitor the impact of secondary vibration caused by the shielding process of the initial tunnel, and collect relevant data on surface subsidence.

基于掘进面与监测断面的第一和/或第二距离的变化调节沉降数据的收集频率。The frequency of collection of settlement data is adjusted based on changes in the first and/or second distances of the advancing face and the monitoring section.

具体地,在掘进面与监测断面的第一和/或第二距离不大于第一阈值时,该监测断面的沉降数据的收集频率为第一频率。第一阈值为20m,第一频率为每天一次。Specifically, when the first and/or second distances between the driving surface and the monitoring section are not greater than the first threshold, the collection frequency of the settlement data of the monitoring section is the first frequency. The first threshold is 20m and the first frequency is once a day.

在掘进面与监测断面的第一和/或第二距离大于第一阈值且不大于第二阈值时,该监测断面的沉降数据的收集频率为第二频率。第二阈值为50m,第二频率为两天一次。When the first and/or second distance between the driving face and the monitoring section is greater than the first threshold and not greater than the second threshold, the collection frequency of the settlement data of the monitoring section is the second frequency. The second threshold is 50m and the second frequency is once every two days.

在掘进面与监测断面的第一和/或第二距离大于第二阈值时,该监测断面的沉降数据的收集频率为第三频率。第三频率为每周一次。When the first and/or second distances between the driving face and the monitoring section are greater than the second threshold, the collection frequency of the settlement data of the monitoring section is the third frequency. The third frequency is once a week.

即随着盾构的挖掘面的变化,各个监测断面的沉降数据的收集频率也随之变化,并且各个监测断面的监测点的收集频率不同。相比于现有技术中的各个监测点以相同频率采集沉降数据的方式,本发明的沉降数据的收集频率变化的调节方式,能够减少大量无效数据的采集和储存。That is, with the change of the excavation surface of the shield, the collection frequency of the settlement data of each monitoring section also changes, and the collection frequency of the monitoring points of each monitoring section is different. Compared with the method of collecting sedimentation data at the same frequency at each monitoring point in the prior art, the method of adjusting the frequency of collecting sedimentation data of the present invention can reduce the collection and storage of a large amount of invalid data.

优选地,根据数据分析沉降情况。在地表沉降稳定的情况下,调节沉降数据的收集频率为第四频率。第四频率为每月一次。Preferably, the sedimentation is analyzed from the data. When the surface subsidence is stable, the collection frequency of subsidence data is adjusted to be the fourth frequency. The fourth frequency is monthly.

地表沉降达到稳定的条件至少包括:The conditions for surface subsidence to stabilize include at least:

道路及地表沉降速度有明显减缓趋势;The subsidence speed of road and surface has a clear trend of slowing down;

道路及地表沉降收敛速度小于0.01~0.04mm/天;The convergence speed of road and surface subsidence is less than 0.01~0.04mm/day;

收敛量达到总收敛量的80%及以上。The amount of convergence reaches 80% and above of the total amount of convergence.

在地表沉降出现异常的情况下,沉降数据的收集频率增大。In the case of abnormal surface subsidence, the frequency of collection of subsidence data increases.

优选地,在每次现场监测工作实施时,同时进行现场安全巡视,并且保证每天巡视一次,特殊情况应增大巡视频率。Preferably, each time the on-site monitoring work is carried out, on-site safety inspections are carried out at the same time, and inspections are guaranteed once a day, and the inspection video rate should be increased in special circumstances.

现场测量所得到的原始数据具有一定的离散性,包含偶然误差的影响,因此本发明选用沉降—时间曲线的离散图进行处理。在采集到地表沉降的数据后,本发明基于地表沉降的沉降—时间的分布拟合曲线进行数据的分析,预测最大沉降量。The original data obtained by on-site measurement has a certain discreteness, including the influence of accidental errors, so the present invention selects the discrete graph of the settlement-time curve for processing. After collecting the data of the surface subsidence, the present invention analyzes the data based on the subsidence-time distribution fitting curve of the surface subsidence, and predicts the maximum subsidence amount.

根据所测道路及地表下沉值,本发明判断道路及地表沉降是否超过安全控制标准以及采用的工程措施的可靠性。将阶段变形速率、变形量与控制标准进行比较,判断监测点预警状态,如数据显示达到警戒标准,分析确认有异常情况时,应当加密检测频率,并且及时做相关处理。According to the measured road and ground subsidence values, the present invention judges whether the road and ground subsidence exceeds the safety control standard and the reliability of the adopted engineering measures. Compare the stage deformation rate and deformation amount with the control standard, and judge the early warning status of the monitoring point. If the data shows that the warning standard is met, and the analysis confirms that there is an abnormal situation, the detection frequency should be encrypted, and relevant processing should be done in time.

本发明通过对数据的处理与分析,结合具体的施工情况,能够判断造成地表沉降的原因,并采取相关的措施,减小地表沉降。不仅如此,本发明同时能够做到全程监测,进一步增强信息化施工的效果。Through the processing and analysis of the data, the present invention can judge the cause of the surface subsidence and take relevant measures to reduce the surface subsidence in combination with the specific construction situation. Not only that, the present invention can monitor the whole process at the same time, and further enhance the effect of informatization construction.

具体地,本发明的监测数据的处理和分析如下。Specifically, the processing and analysis of the monitoring data of the present invention are as follows.

监测先始发隧道在盾构过程中造成的地表沉降,收集地表沉降的相关数据并且进行分析,其沉降-时间的分布拟合曲线如图5所示。The surface subsidence caused by the first-initiated tunnel during the shield tunneling process was monitored, and the relevant data of the surface subsidence were collected and analyzed. The fitting curve of the subsidence-time distribution is shown in Figure 5.

第一隧道的盾构正在进行施工前的准备工作,同时第二隧道已施工至348环,此时由第二线盾构施工引起的叠落段地表变形已基本结束,对第一至第六监测断面进行连续监测,直至沉降基本稳定。The shield of the first tunnel is being prepared before construction, and the second tunnel has been constructed to the 348th ring. At this time, the surface deformation of the stacking section caused by the construction of the second line of shields has basically ended. Monitoring the first to sixth The section is continuously monitored until the settlement is basically stable.

如图5所示,第二监测断面处最大沉降为5.93mm,相对于其他监测断面沉降值略小。这是由于第二监测断面处于盾构始发阶段,盾构推进速度较慢,始发端头加固效果良好等原因。As shown in Figure 5, the maximum settlement at the second monitoring section is 5.93mm, which is slightly smaller than that of other monitoring sections. This is due to the fact that the second monitoring section is in the shield initiation stage, the shield advancement speed is slow, and the reinforcement effect of the initiation end is good.

由图5可以看出,第一、第二两个监测断面处沉降曲线沿隧道中心不对称分布,每个监测断面的最大沉降发生在隧道中线上,沿隧道横向逐渐减小,离轴线较远的区域地表有较小隆起,平均不到2mm。It can be seen from Figure 5 that the settlement curves of the first and second monitoring sections are distributed asymmetrically along the center of the tunnel. The maximum settlement of each monitoring section occurs on the tunnel centerline, and gradually decreases along the lateral direction of the tunnel and is far from the axis. There are small uplifts on the surface of the area, with an average of less than 2mm.

根据上述监测结果,上覆土为粉质粘土的第一、第二监测断面沉降值整体小于上覆土为砂卵石地层的第三、第四、第五、第六监测断面。第一、第二监测断面处的平均沉降值为7mm左右。另外四个监测断面的平均沉降值为12mm左右。在相同施工条件情况下,上覆土为粉质粘土的地表沉降略小于上覆土为砂卵石层的地表沉降。According to the above monitoring results, the settlement value of the first and second monitoring sections whose overlying soil is silty clay is generally lower than that of the third, fourth, fifth and sixth monitoring sections whose overlying soil is sand and pebble strata. The average settlement value at the first and second monitoring sections is about 7mm. The average settlement value of the other four monitoring sections is about 12mm. Under the same construction conditions, the surface subsidence of the overlying soil is silty clay is slightly smaller than that of the sand-cobble layer.

根据图5的监测结果可知,第三、第五、第六监测断面穿越土层及上覆土性质基本一致的情况下,平均沉降依次增大,这是由于隧道埋深沿着隧道掘进方向不断减小所致。According to the monitoring results in Figure 5, when the third, fifth, and sixth monitoring sections pass through the soil layer and the properties of the overlying soil are basically the same, the average settlement increases sequentially. This is because the buried depth of the tunnel keeps decreasing along the tunneling direction due to small.

从图5中看到,第四监测断面的第43、44沉降监测点起伏较大,可能由于施工或监测点破坏等原因。It can be seen from Figure 5 that the settlement monitoring points 43 and 44 of the fourth monitoring section have large fluctuations, which may be due to construction or damage to the monitoring points.

整体监测结果显示,叠落段最大沉降量出现在第四监测断面,最大沉降为19.08mm。在设计允许范围内,其他各监测断面沉降量均小于15.00mm。在现场巡视过程中,盾构各施工参数适当,盾构姿态良好,未出现需要进行较大纠偏等情况,叠落段下线隧道整体施工情况良好。The overall monitoring results show that the maximum subsidence of the stacking section occurs in the fourth monitoring section, and the maximum subsidence is 19.08mm. Within the design allowable range, the settlement of other monitoring sections is less than 15.00mm. During the on-site inspection process, the construction parameters of the shield were appropriate, the posture of the shield was good, and there was no need for major deviation correction.

监测后始发隧道盾构过程中造成的二次振动影响,收集地表沉降的相关数据,其沉降-时间的分布拟合曲线如图6和图7所示。After monitoring the impact of secondary vibration caused by the shielding process of the initial tunnel, the relevant data of the surface subsidence was collected.

第一隧道1施工对地层产生了二次扰动,引起地表的二次沉降,再对第一至第六的六个监测断面进行监测,直至地表沉降基本稳定。The construction of the first tunnel 1 produced secondary disturbance to the stratum, causing secondary subsidence of the surface, and then the six monitoring sections from the first to the sixth were monitored until the surface subsidence was basically stable.

根据图6和图7可以看出,第一隧道施工使地表产生先隆起后沉降的趋势,这是由于第二隧道加固效果良好,盾构到达监测点之前对前方土体的挤压使地表有向上隆起的趋势。当盾体通过监测点时,周边土体失去盾构外壳的支撑,代之以未凝固或未完全凝固的浆液做支撑,地表产生沉降的趋势。在盾构通过后及时进行二次补浆,地表沉降渐趋稳定。由图2和图3可知,第一监测断面的最大沉降值为8.45mm,第二监测断面的最大沉降值为12.35mm,对地表沉降的控制效果较好。According to Figure 6 and Figure 7, it can be seen that the construction of the first tunnel causes the surface to rise first and then settle. This is due to the good reinforcement effect of the second tunnel. Upward bulge trend. When the shield passes through the monitoring point, the surrounding soil loses the support of the shield shell, and is replaced by the unsolidified or incompletely solidified slurry, and the surface tends to settle. After the shield passes through, the secondary slurry replenishment is carried out in time, and the surface settlement is gradually stabilized. It can be seen from Figure 2 and Figure 3 that the maximum subsidence value of the first monitoring section is 8.45mm, and the maximum subsidence value of the second monitoring section is 12.35mm, which has a better control effect on the surface subsidence.

如8和图9指示,第三监测断面的沉降规律与第二监测断面的沉降规律不相同。第三监测断面在第一隧道施工时不但没有隆起的趋势,而且沉降在盾构到达监测点时已经开始。在盾构的推进过程中,第三监测断面的沉降量不断增大,沉降速率较大,地表沉降明显有超过规定值30mm的趋势。在10月15日,同步将注浆浆液更换为水泥~水玻璃液浆,对沉降速率过大的区域及时用双液浆进行二次补浆,基本控制了沉降速率过大问题,但是第三监测断面的最大沉降量仍然达到34.26mm。As indicated in 8 and 9, the settlement law of the third monitoring section is different from the settlement law of the second monitoring section. During the construction of the first tunnel, the third monitoring section had no tendency to bulge, and the subsidence started when the shield reached the monitoring point. During the advancement of the shield, the subsidence of the third monitoring section continued to increase, the subsidence rate was relatively large, and the surface subsidence obviously had a tendency to exceed the specified value of 30mm. On October 15th, the grouting slurry was simultaneously replaced with cement-water glass slurry, and the double-liquid slurry was used for secondary slurry replenishment in time for the areas with excessive settlement rate, which basically controlled the problem of excessive settlement rate, but the third The maximum settlement of the monitoring section still reaches 34.26mm.

第三监测断面的地表沉降量超出第二监测断面的地表沉降量较多。在总结分析后得出,第三监测断面沉降过大的原因是:由于第三监测断面处于第一与第二隧道之间的层间土未进行加固,从而导致沉降过大。第二监测断面未进行层间土加固且未出现较大沉降,是由于第二监测断面穿越土层主要为粉质粘土层,穿越粉质粘土层不需要层间土加固。但是,第三监测断面穿越土层主要为砂卵石层,砂卵石层需要进行层间土加固,应当对即将穿越的砂卵石层土体进行层间土加固。The surface subsidence of the third monitoring section exceeds the surface subsidence of the second monitoring section by a large amount. After summarizing the analysis, it is concluded that the reason for the excessive settlement of the third monitoring section is that the interlayer soil between the first and second tunnels in the third monitoring section is not reinforced, resulting in excessive settlement. The second monitoring section was not reinforced with interlayer soil and did not experience large settlement, because the second monitoring section passed through the soil layer mainly silty clay layer, and no interlayer soil reinforcement was required when crossing the silty clay layer. However, the third monitoring section crosses the soil layer mainly with sand and pebble layers, and the sand and pebble layers need to be reinforced with interlayer soil.

由图9可知,第四监测断面的最大沉降量为23.22mm,相对来说地表沉降控制效果良好,并且推进中有先隆起后沉降的趋势,这和第二监测断面沉降规律类似。第四监测断面的地表沉降控制比第三监测断面控制效果良好,是由于对上下洞层间土体加固的原因。可见,在盾构穿越土层为粉质粘土层时不需要对层间土进行加固,在盾构穿越土层为砂卵石层时需要对层间土进行加固。It can be seen from Fig. 9 that the maximum subsidence of the fourth monitoring section is 23.22mm, relatively speaking, the surface subsidence control effect is good, and there is a tendency of uplift and then subsidence in the advance, which is similar to the subsidence law of the second monitoring section. The control effect of the surface settlement of the fourth monitoring section is better than that of the third monitoring section, which is due to the reinforcement of the soil between the upper and lower caverns. It can be seen that the interlayer soil does not need to be reinforced when the shield tunneling soil is a silty clay layer, and the interlayer soil needs to be reinforced when the shield tunneling soil is a sandy pebble layer.

由图10可知,在盾构推进过程中,地表有先隆起的趋势,但是从10月26日至10月28日地表沉降速率过大,最大沉降速率达到4mm/天。从10月29日起,地表沉降速率减小,地表沉降趋于稳定。经现场踏勘发现,在10月26日至10月28日期间,由于盾构出现故障,停止推进,在10月29日盾构恢复正常推进。在盾构停止推进前,虽然有减小出土量,继续推进使土舱内土压略大于设定土压,但是停机时间较长,并未采取其他防止盾构后退的措施,导致在停机期间,地表沉降速率过大。It can be seen from Figure 10 that in the process of shield tunneling, the surface has a tendency to uplift first, but from October 26 to October 28, the surface subsidence rate was too large, and the maximum subsidence rate reached 4 mm/day. From October 29, the surface subsidence rate decreased and the surface subsidence tended to be stable. The site survey found that from October 26th to October 28th, due to the failure of the shield machine, the advance was stopped, and on October 29th the shield machine resumed normal advance. Before the shield machine stopped advancing, although the excavation volume was reduced and the earth pressure in the soil tank was slightly larger than the set earth pressure, the downtime was long, and no other measures were taken to prevent the shield from retreating, resulting in the downtime during the downtime. , the surface subsidence rate is too high.

由图11可知,第六监测断面地表的最大沉降量为17.81mm,相对来说地表沉降控制效果良好,并且推进中有先隆起后沉降的趋势,与第二、第四监测断面沉降规律类似。It can be seen from Figure 11 that the maximum subsidence of the surface of the sixth monitoring section is 17.81mm, relatively speaking, the surface subsidence control effect is good, and there is a trend of first uplift and then subsidence in the advance, which is similar to the subsidence law of the second and fourth monitoring sections.

由第二、第四、第六监测断面的沉降图可知:叠落段后行盾构推进对地表影响有先隆起后沉降的趋势,在各种控制沉降措施效果良好的情况下,后沉降值不大,均在地表沉降允许值范围内。From the subsidence maps of the second, fourth, and sixth monitoring sections, it can be seen that the impact of shield tunnel advancement on the surface of the stacking section has a tendency of uplift and then subsidence. Not big, all within the allowable range of surface subsidence.

由第二、第四、第六监测断面地表的沉降图得出,由下洞隧道推进引起的地表沉降量占最总沉降的76.65%,由上洞隧道推进引起的地表沉降占总沉降的23.35%。由第三、第五监测断面地表的沉降图得出,由下洞隧道推进引起的地表沉降量占最总沉降的34.78%,由上洞隧道推进引起的地表沉降占总沉降的65.22%。According to the subsidence maps of the second, fourth and sixth monitoring sections, the surface subsidence caused by the advancement of the lower tunnel accounts for 76.65% of the total settlement, and the surface subsidence caused by the advancement of the upper tunnel accounts for 23.35% of the total settlement. %. From the subsidence maps of the third and fifth monitoring sections, the surface subsidence caused by the advancement of the lower tunnel accounts for 34.78% of the total settlement, and the surface subsidence caused by the advancement of the upper tunnel accounts for 65.22% of the total subsidence.

可见在上洞隧道地表沉降控制良好的情况下,引起地表沉降最主要原因是下洞隧道的推进,而上洞隧道地表沉降控制不理想的情况下,引起地表沉降的主要原因为上洞隧道的推进。所以,在叠落式隧道后行盾构推进中,应加强地表沉降控制措施,尽量减小后行盾构推进引起的地表二次扰动。It can be seen that when the surface settlement of the upper tunnel is well controlled, the main cause of the surface subsidence is the advancement of the lower tunnel, while when the surface settlement control of the upper tunnel is not ideal, the main cause of the surface subsidence is the lower tunnel. advance. Therefore, in the advancement of the backward shield tunnel in the stacked-drop tunnel, the control measures of surface subsidence should be strengthened to minimize the secondary disturbance of the surface caused by the backward shield advancement.

需要注意的是,上述具体实施例是示例性的,本领域技术人员可以在本发明公开内容的启发下想出各种解决方案,而这些解决方案也都属于本发明的公开范围并落入本发明的保护范围之内。本领域技术人员应该明白,本发明说明书及其附图均为说明性而并非构成对权利要求的限制。本发明的保护范围由权利要求及其等同物限定。本发明说明书包含多项发明构思,诸如“优选地”、“根据一个优选实施方式”或“可选地”均表示相应段落公开了一个独立的构思,申请人保留根据每项发明构思提出分案申请的权利。It should be noted that the above-mentioned specific embodiments are exemplary, and those skilled in the art can come up with various solutions inspired by the disclosure of the present invention, and these solutions also belong to the disclosure scope of the present invention and fall within the scope of the present invention. within the scope of protection of the invention. It should be understood by those skilled in the art that the description of the present invention and the accompanying drawings are illustrative rather than limiting to the claims. The protection scope of the present invention is defined by the claims and their equivalents. The description of the present invention contains multiple inventive concepts, such as "preferably", "according to a preferred embodiment" or "optionally" all indicate that the corresponding paragraph discloses a separate concept, and the applicant reserves the right to propose divisions according to each inventive concept the right to apply.

Claims (10)

1.一种基于叠落式隧道之间的角度的监测点设置方法,其特征在于,所述方法至少包括:1. a monitoring point setting method based on the angle between the stacked tunnels, is characterized in that, the method at least comprises: 基于与所述监测断面对应的叠落式隧道之间的净间距和/或角度确定设置于所述监测断面的监测点的数量以及分布范围,其中,The number and distribution range of monitoring points arranged on the monitoring section are determined based on the clear distance and/or angle between the stacked tunnels corresponding to the monitoring section, wherein, 在两叠落隧道之间的角度在40°~60°这一区间时,若两隧道的净间距固定,随着两叠落隧道之间的角度的减小,在沉降影响的范围内设置更多的监测点,并且加大检测频率。When the angle between the two stacked tunnels is in the range of 40° to 60°, if the clear distance between the two tunnels is fixed, as the angle between the two stacked tunnels decreases, a more More monitoring points, and increase the detection frequency. 2.根据权利要求1所述的基于叠落式隧道之间的角度的监测点设置方法,其特征在于,所述方法还包括:2. The monitoring point setting method based on the angle between the stacked tunnels according to claim 1, wherein the method further comprises: 在两叠落隧道之间的角度在40°~60°这一区间时,若两隧道的角度不变,随着净间距的增大设置更多的监测点,所述监测点设置的密度和检测频率相应减少。When the angle between the two stacked tunnels is in the range of 40° to 60°, if the angle of the two tunnels remains unchanged, more monitoring points are set with the increase of the clear distance, and the density and The detection frequency is reduced accordingly. 3.根据权利要求2所述的基于叠落式隧道之间的角度的监测点设置方法,其特征在于,所述方法还包括:3. The monitoring point setting method based on the angle between the stacked tunnels according to claim 2, wherein the method further comprises: 在两叠落隧道之间的角度为0°的第一监测断面,所述第一监测断面设置两个或四个监测点。A first monitoring section with an angle of 0° between the two stacked tunnels is provided with two or four monitoring points. 4.根据权利要求1至3任一项所述的基于叠落式隧道之间的角度的监测点设置方法,其特征在于,所述方法还包括:4. The monitoring point setting method based on the angle between the stacked tunnels according to any one of claims 1 to 3, wherein the method further comprises: 监测先始发隧道在盾构过程中造成的地表沉降并收集地表沉降的相关数据;Monitor the ground subsidence caused by the first-start tunnel during the shield tunneling process and collect relevant data on the ground subsidence; 监测后始发隧道盾构过程中造成的二次振动影响并收集地表沉降的相关数据;Monitor the secondary vibration effects caused by the shielding process of the initial tunnel and collect relevant data on surface subsidence; 基于掘进面与监测断面的第一和/或第二距离的变化调节沉降数据的收集频率。The frequency of collection of settlement data is adjusted based on changes in the first and/or second distances of the advancing face and the monitoring section. 5.根据权利要求4所述的基于叠落式隧道之间的角度的监测点设置方法,其特征在于,所述方法还包括:5. The monitoring point setting method based on the angle between the stacked tunnels according to claim 4, wherein the method further comprises: 在掘进面与监测断面的第一和/或第二距离不大于第一阈值时,沉降数据的收集频率为第一频率;When the first and/or second distance between the driving face and the monitoring section is not greater than the first threshold, the collection frequency of the settlement data is the first frequency; 在掘进面与所述监测断面的第一和/或第二距离大于第一阈值且不大于第二阈值时,沉降数据的收集频率为第二频率;When the first and/or second distance between the driving surface and the monitoring section is greater than the first threshold and not greater than the second threshold, the collection frequency of the settlement data is the second frequency; 在掘进面与所述监测断面的第一和/或第二距离大于第二阈值时,沉降数据的收集频率为第三频率。When the first and/or second distances between the driving face and the monitoring section are greater than the second threshold, the frequency of collecting the settlement data is the third frequency. 6.根据权利要求5所述的基于叠落式隧道之间的角度的监测点设置方法,其特征在于,所述方法还包括:6. The monitoring point setting method based on the angle between the stacked tunnels according to claim 5, wherein the method further comprises: 在地表沉降稳定的情况下,调节沉降数据的收集频率为第四频率;第四频率为每月一次。In the case of stable surface subsidence, the collection frequency of subsidence data is adjusted to be the fourth frequency; the fourth frequency is once a month. 7.根据权利要求5所述的基于叠落式隧道之间的角度的监测点设置方法,其特征在于,所述方法还包括:7. The monitoring point setting method based on the angle between the stacked tunnels according to claim 5, wherein the method further comprises: 基于地表沉降的沉降—时间的分布拟合曲线预测最大沉降量,The maximum subsidence is predicted based on the subsidence-time distribution fitting curve of surface subsidence, 在地表沉降出现异常的情况下,沉降数据的收集频率增大。In the case of abnormal surface subsidence, the frequency of collection of subsidence data increases. 8.根据权利要求5所述的基于叠落式隧道之间的角度的监测点设置方法,其特征在于,所述方法还包括:8. The monitoring point setting method based on the angle between the stacked tunnels according to claim 5, wherein the method further comprises: 所述地表沉降达到稳定的条件至少包括:The conditions for the surface subsidence to be stable at least include: 道路及地表沉降速度有明显减缓趋势;The subsidence speed of road and surface has a clear trend of slowing down; 道路及地表沉降收敛速度小于0.01~0.04mm/天;The convergence speed of road and surface subsidence is less than 0.01~0.04mm/day; 收敛量达到总收敛量的80%及以上。The amount of convergence reaches 80% and above of the total amount of convergence. 9.根据权利要求5所述的基于叠落式隧道之间的角度的监测点设置方法,其特征在于,9. The monitoring point setting method based on the angle between the stacked tunnels according to claim 5, is characterized in that, 所述第一阈值为20m,所述第一频率为每天一次;The first threshold is 20m, and the first frequency is once a day; 所述第二阈值为50m,所述第二频率为两天一次;The second threshold is 50m, and the second frequency is once every two days; 所述第三频率为每周一次。The third frequency is once a week. 10.根据权利要求5所述的基于叠落式隧道之间的角度的监测点设置方法,其特征在于,10. The monitoring point setting method based on the angle between the stacked tunnels according to claim 5, characterized in that, 在叠落段共设置6个监测断面;第一监测断面设置有四个监测点,第二监测断面设置有十二个监测点,第三监测断面设置有两个监测点,第四监测断面设置有十四个监测点,第五监测断面设置有两个监测点,第六监测断面设置有两个监测点。A total of 6 monitoring sections are set in the stacking section; the first monitoring section is set with four monitoring points, the second monitoring section is set with twelve monitoring points, the third monitoring section is set with two monitoring points, and the fourth monitoring section is set with There are fourteen monitoring points, the fifth monitoring section has two monitoring points, and the sixth monitoring section has two monitoring points.
CN202210859704.9A 2022-03-31 2022-03-31 A monitoring point setting method based on the angle between stacked tunnels Active CN115235417B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210859704.9A CN115235417B (en) 2022-03-31 2022-03-31 A monitoring point setting method based on the angle between stacked tunnels

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202210859704.9A CN115235417B (en) 2022-03-31 2022-03-31 A monitoring point setting method based on the angle between stacked tunnels
CN202210327480.7A CN114413839B (en) 2022-03-31 2022-03-31 Device and method for monitoring complete stacking section of up-down stacking type tunnel

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN202210327480.7A Division CN114413839B (en) 2022-03-31 2022-03-31 Device and method for monitoring complete stacking section of up-down stacking type tunnel

Publications (2)

Publication Number Publication Date
CN115235417A true CN115235417A (en) 2022-10-25
CN115235417B CN115235417B (en) 2023-07-25

Family

ID=81263638

Family Applications (3)

Application Number Title Priority Date Filing Date
CN202210327480.7A Active CN114413839B (en) 2022-03-31 2022-03-31 Device and method for monitoring complete stacking section of up-down stacking type tunnel
CN202210859704.9A Active CN115235417B (en) 2022-03-31 2022-03-31 A monitoring point setting method based on the angle between stacked tunnels
CN202210861484.3A Active CN115655207B (en) 2022-03-31 2022-03-31 A method for adjusting the frequency of settlement data collection in a fully overlapping section of an overlapping tunnel

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN202210327480.7A Active CN114413839B (en) 2022-03-31 2022-03-31 Device and method for monitoring complete stacking section of up-down stacking type tunnel

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN202210861484.3A Active CN115655207B (en) 2022-03-31 2022-03-31 A method for adjusting the frequency of settlement data collection in a fully overlapping section of an overlapping tunnel

Country Status (1)

Country Link
CN (3) CN114413839B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116678377A (en) * 2023-08-03 2023-09-01 中国水利水电第七工程局有限公司 Tunnel clearance automatic detection method based on automatic total station
CN117213443A (en) * 2023-11-07 2023-12-12 江苏省地质调查研究院 Construction and updating method of ground settlement monitoring network with integration of heaves, earth and depth

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118008480B (en) * 2024-03-12 2024-10-29 济南市交通工程质量与安全中心 Automatic monitoring equipment for shield earth surface subsidence

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109611156A (en) * 2018-12-28 2019-04-12 中铁隧道集团三处有限公司 A kind of monitoring method of overlapping tunnel information-aided construction
CN110952987A (en) * 2019-12-03 2020-04-03 济南轨道交通集团有限公司 Construction method for side-through bridge pile of stacked porous subway tunnel
CN111998825A (en) * 2020-08-17 2020-11-27 中铁十九局集团第二工程有限公司 Monitoring and measuring method for shallow buried section of tunnel
CN112343626A (en) * 2020-10-19 2021-02-09 中铁十八局集团有限公司 Shield tunnel construction and reinforcement method for penetrating existing tunnel under upper soft and lower hard stratum
CN112862790A (en) * 2021-02-18 2021-05-28 中国矿业大学(北京) Subway tunnel crack positioning device and method based on linear array camera
CN113217021A (en) * 2021-04-30 2021-08-06 中铁十六局集团有限公司 Underground space close-range disturbance construction method and equipment

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108825304B (en) * 2018-06-19 2020-12-18 中铁十四局集团有限公司 A shield tunnel formation stability and long-term health monitoring system of tunnel structure
CN109736894B (en) * 2018-11-27 2020-07-03 中国矿业大学 Monitoring system, monitoring method and early warning method for coal mine roadway surrounding rock disasters
CN109900210A (en) * 2019-03-22 2019-06-18 贵州大学 A kind of monitoring of tunnel rock displacement and Data Post Processing System and method
CN110631560B (en) * 2019-08-13 2021-11-26 中铁上海工程局集团有限公司 Underground excavation interval monitoring and measuring method for subway station in dense building area
CN111473734B (en) * 2020-04-29 2021-12-07 同济大学 System and method for monitoring stability of clamped rock in small-clear-distance tunnel
CN111859728A (en) * 2020-06-04 2020-10-30 河北建筑工程学院 Surface Deformation Calculation Method and Settlement Fit Analysis Method for Shield Tunneling
CN112832806A (en) * 2021-01-28 2021-05-25 西安理工大学 A kind of segment breaking and formation anti-collapse construction method of shield first and then well
CN112948931B (en) * 2021-03-03 2023-04-07 河南大学 Method for determining reasonable included angle and clear distance of shield construction under double-line overlapping working condition of new construction and existing subway tunnel
CN113107600B (en) * 2021-05-19 2022-06-14 青岛理工大学 Method for determining tunnel monitoring point data weight
CN114017037A (en) * 2021-11-01 2022-02-08 中铁一局集团第二工程有限公司 A construction method of shield tunnel crossing municipal bridge area at close range

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109611156A (en) * 2018-12-28 2019-04-12 中铁隧道集团三处有限公司 A kind of monitoring method of overlapping tunnel information-aided construction
CN110952987A (en) * 2019-12-03 2020-04-03 济南轨道交通集团有限公司 Construction method for side-through bridge pile of stacked porous subway tunnel
CN111998825A (en) * 2020-08-17 2020-11-27 中铁十九局集团第二工程有限公司 Monitoring and measuring method for shallow buried section of tunnel
CN112343626A (en) * 2020-10-19 2021-02-09 中铁十八局集团有限公司 Shield tunnel construction and reinforcement method for penetrating existing tunnel under upper soft and lower hard stratum
CN112862790A (en) * 2021-02-18 2021-05-28 中国矿业大学(北京) Subway tunnel crack positioning device and method based on linear array camera
CN113217021A (en) * 2021-04-30 2021-08-06 中铁十六局集团有限公司 Underground space close-range disturbance construction method and equipment

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
台启民: "暗挖交叠隧道地表沉降实测分析" *
张青: "新建隧道近距离小角度斜下穿既有隧道稳定性分析——以青岛地铁8号线隧道工程为例" *
李兆平: "盾构隧道近距离小角度上穿已建暗挖隧道方案" *
靳晓光: "地铁区间小净距上叠风道施工力学效应研究" *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116678377A (en) * 2023-08-03 2023-09-01 中国水利水电第七工程局有限公司 Tunnel clearance automatic detection method based on automatic total station
CN116678377B (en) * 2023-08-03 2023-11-03 中国水利水电第七工程局有限公司 Tunnel clearance automatic detection method based on automatic total station
CN117213443A (en) * 2023-11-07 2023-12-12 江苏省地质调查研究院 Construction and updating method of ground settlement monitoring network with integration of heaves, earth and depth
CN117213443B (en) * 2023-11-07 2024-03-19 江苏省地质调查研究院 Construction and updating method of ground settlement monitoring network with integration of heaves, earth and depth

Also Published As

Publication number Publication date
CN115655207B (en) 2025-06-20
CN115235417B (en) 2023-07-25
CN114413839A (en) 2022-04-29
CN115655207A (en) 2023-01-31
CN114413839B (en) 2022-07-15

Similar Documents

Publication Publication Date Title
CN114413839B (en) Device and method for monitoring complete stacking section of up-down stacking type tunnel
CN111058855B (en) Deformation control method and evaluation system for shield underpassing structure
CN101761346B (en) Method for constructing metamorphic rock confined water tunnel
CN106089217B (en) Major long tunnel rapid constructing method under complex geological condition
CN101608548B (en) Method for protecting underground structure of single round shield side face construction in close distance
CN104965994A (en) Method for measuring and estimating characteristic parameters of surface subsidence caused by subway tunnel construction
CN103471647B (en) A kind of shield tunnel remote automation monitoring method
CN113944481A (en) A kind of treatment method of tunnel vault filled karst cave in karst karst area
CN106949877A (en) The monitoring method of ground settlement above a kind of various dimensions shield tunnel
CN111594190A (en) Method for controlling shield tunneling parameters when shield passes through different risk sources
CN108520350A (en) Risk assessment method for super-large diameter shield tunneling through buildings continuously
CN115126441B (en) Vertical deep drilling grouting technology
CN115949451A (en) Multi-disaster collaborative management method in the triangle area of coal mining face based on directional drilling
CN117034399A (en) Shield tunnel soil pressure calculation method based on stratum deformation characteristics
CN114753851A (en) Settlement control method and system for close-range penetration of shield through sensitive building group
CN104389613B (en) Slurry balance shield passes through the construction method of jeopardously underground pipelines
CN112131628B (en) Tunnel crossing water-rich fault water bursting prevention minimum safe thickness calculation method
CN106096162A (en) A kind of method determining shield support pressure and mathematical model thereof and construction method
CN111611708A (en) A Calculation Method of Existing Tunnel Displacement Under the Action of Supporting Trolleys in Overlapping Tunnels
CN114483068B (en) Double-hole overlapped shield tunnel construction control method
CN118997773A (en) Tunnel excavation supporting construction measure and method for underpass river channel
CN112855171B (en) Tunnel construction method for deep-excavation backfill area
Hu et al. Improved protodyakonov’s method of the tunnel surrounding rock pressure under the seepage condition of weak interlayer
Xu et al. Numerical simulation analysis of controlling settlement by water-resisting curtain combined with recharge in deep foundation pit
CN213175636U (en) Construction Monitoring System for Shallow Buried Deep Tunnels Passing Down Existing Railway Lines

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant