CN115012815A - Vertical shaft blasting presplitting grouting method - Google Patents
Vertical shaft blasting presplitting grouting method Download PDFInfo
- Publication number
- CN115012815A CN115012815A CN202210796202.6A CN202210796202A CN115012815A CN 115012815 A CN115012815 A CN 115012815A CN 202210796202 A CN202210796202 A CN 202210796202A CN 115012815 A CN115012815 A CN 115012815A
- Authority
- CN
- China
- Prior art keywords
- blasting
- grouting
- vertical shaft
- steel
- borehole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
- E21B7/007—Drilling by use of explosives
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/10—Sealing or packing boreholes or wells in the borehole
- E21B33/13—Methods or devices for cementing, for plugging holes, crevices or the like
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Drilling And Exploitation, And Mining Machines And Methods (AREA)
Abstract
本发明提供了一种立井爆破预裂注浆方法,包括:围绕立井底壁的周缘钻多个爆破组,每个爆破组中包括多个钻孔;在需要爆破的钻孔中装炸药;将颗粒状封堵物装入装炸药后的钻孔内;采用钢构件封堵装炸药后的钻孔的开口;在钢构件上堆积重物;起爆并检查爆破质量;对爆破后的钻孔注浆。采用该方案,通过设置多个爆破组,且每个爆破组中包括多个钻孔,这样能够为需要爆破的钻孔提供足够的自由面,从而减弱了在钻孔轴向上的爆破威力;同时,首先采用颗粒状封堵物对钻孔进行封堵,随后采用钢构件对钻孔的开口再次进行封堵,且在钢构件上堆积重物,这样进一步保证了封堵效果。采用这种方法,有效解决了现有技术中爆破效果差的问题。
The invention provides a pre-split grouting method for vertical well blasting, comprising: drilling a plurality of blasting groups around the periphery of the bottom wall of the vertical well, each blasting group including a plurality of boreholes; loading explosives in the boreholes to be blasted; The granular plugging material is put into the drill hole after the explosive is loaded; the opening of the drill hole after the explosive is filled with steel components; the heavy objects are piled on the steel component; pulp. By adopting this solution, by setting up multiple blasting groups, and each blasting group includes multiple drilling holes, sufficient free surfaces can be provided for the drilling holes that need to be blasted, thereby reducing the blasting power in the axial direction of the drilling holes; At the same time, the drilled hole is first blocked with granular plugging materials, and then the opening of the drilled hole is blocked again with steel components, and heavy objects are stacked on the steel components, which further ensures the blocking effect. By adopting this method, the problem of poor blasting effect in the prior art is effectively solved.
Description
技术领域technical field
本发明涉及立井开拓技术领域,具体而言,涉及一种立井爆破预裂注浆方法。The invention relates to the technical field of vertical well development, in particular to a vertical well blasting pre-split grouting method.
背景技术Background technique
目前,立井开拓为常采用的爆破方法,其中,立井在开拓的过程中经常遇到出水的情况,钻孔出水可达几十立方米每小时。因此,在立井在开拓的过程中需对工作面进行探水预注浆施工。在进行探水预注浆施工时需要进行爆破预裂,抑制涌水情况,在井筒开拓范围外形成稳定区域,从而实现更加良好的注浆效果。一般情况下,乳化炸药随着水深的增加爆破威力逐渐减少,现有技术中在进行爆破预裂时,由于缺少足够的自由面,容易造成冲孔的现象,注浆量不能满足要求,难以实现预期的爆破效果。At present, vertical well development is a commonly used blasting method. In the process of vertical well development, water is often encountered, and the water output from the borehole can reach tens of cubic meters per hour. Therefore, in the process of vertical well development, it is necessary to carry out water exploration and pre-grouting construction on the working face. During the water exploration pre-grouting construction, blasting and pre-splitting should be carried out to suppress the water influx and form a stable area outside the wellbore development range, so as to achieve a better grouting effect. Under normal circumstances, the blasting power of emulsion explosives gradually decreases with the increase of water depth. In the prior art, during blasting pre-splitting, due to the lack of sufficient free surfaces, it is easy to cause punching, and the amount of grouting cannot meet the requirements, which is difficult to achieve. Expected blasting effect.
发明内容SUMMARY OF THE INVENTION
本发明提供了一种立井爆破预裂注浆方法,以解决现有技术中爆破效果差的问题。The invention provides a pre-split grouting method for vertical well blasting, so as to solve the problem of poor blasting effect in the prior art.
为了解决上述问题,本发明提供了一种立井爆破预裂注浆方法,包括:围绕立井底壁的周缘钻多个爆破组,每个爆破组中包括多个钻孔;在需要爆破的钻孔中装炸药;将颗粒状封堵物装入装炸药后的钻孔内;采用钢构件封堵装炸药后的钻孔的开口;在钢构件上堆积重物;起爆并检查爆破质量;对爆破后的钻孔注浆。In order to solve the above problems, the present invention provides a method for pre-splitting and grouting in vertical shaft blasting, including: drilling a plurality of blasting groups around the periphery of the bottom wall of the vertical shaft, each blasting group including a plurality of boreholes; Loading explosives in the middle; putting granular plugs into the drilled holes after the explosives are loaded; using steel components to block the openings of the drilled holes after loading the explosives; stacking heavy objects on the steel components; detonating and checking the blasting quality; Post-drilling grouting.
进一步地,爆破组中的多个钻孔均平行。Further, the plurality of boreholes in the blasting group are all parallel.
进一步地,钻孔的直径为75mm至90mm,钻孔的深度大于30m。Further, the diameter of the borehole is 75mm to 90mm, and the depth of the borehole is greater than 30m.
进一步地,在需要爆破的钻孔中装炸药包括:将炸药与导爆索、细长支撑物连接;在细长支撑物的下端连接配重块;将配重块、炸药、导爆索和细长支撑物伸入钻孔内。Further, loading explosives in the borehole that needs to be blasted includes: connecting the explosives with the detonating cord and the elongated support; connecting a counterweight at the lower end of the elongated support; connecting the counterweight, the explosive, the detonating cord and the elongated support. An elongated support extends into the borehole.
进一步地,细长支撑物为绳索或刚性管,导爆索为多根。Further, the elongated supports are ropes or rigid pipes, and the detonating cords are multiple.
进一步地,颗粒状封堵物包括土壤、沙子、碎石中的至少一种,重物为沙袋。Further, the granular plugging material includes at least one of soil, sand and gravel, and the heavy material is a sandbag.
进一步地,钢构件包括相互连接的钢杆和钢板,钢杆插入钻孔内,钢板封堵钻孔的开口。Further, the steel member includes a steel rod and a steel plate which are connected to each other, the steel rod is inserted into the drilled hole, and the steel plate blocks the opening of the drilled hole.
进一步地,钢杆的长度不小于钻孔深度的20%。Further, the length of the steel rod is not less than 20% of the drilling depth.
进一步地,钢构件具有贯穿钢杆和钢板的通孔。Further, the steel member has through holes penetrating the steel rod and the steel plate.
进一步地,钢板为圆形板,钢板的直径为1000mm至1200mm,钢杆的外径为74mm至89mm。Further, the steel plate is a circular plate, the diameter of the steel plate is 1000mm to 1200mm, and the outer diameter of the steel rod is 74mm to 89mm.
应用本发明的技术方案,提供了一种立井爆破预裂注浆方法,包括:围绕立井底壁的周缘钻多个爆破组,每个爆破组中包括多个钻孔;在需要爆破的钻孔中装炸药;将颗粒状封堵物装入装炸药后的钻孔内;采用钢构件封堵装炸药后的钻孔的开口;在钢构件上堆积重物;起爆并检查爆破质量;对爆破后的钻孔注浆。采用该方案,通过设置多个爆破组,且每个爆破组中包括多个钻孔,这样能够为需要爆破的钻孔提供足够的自由面,从而减弱了在钻孔轴向上的爆破威力;同时,首先采用颗粒状封堵物对钻孔进行封堵,随后采用钢构件对钻孔的开口再次进行封堵,且在钢构件上堆积重物,这样进一步保证了封堵效果。利用本方案的立井爆破预裂注浆方法,首先在立井底壁周缘钻多个爆破组,其中,多个爆破组中包括多个钻孔,在需要爆破的钻孔中装炸药,随后将颗粒状封堵物装入装完炸药的钻孔中进行封堵;然后采用钢构件对装炸药后的钻孔的开口进行封堵,并在钢构件上堆积重物以提高封堵效果,最后进行起爆,检查爆破质量后对爆破后的钻孔注浆。采用这种方法,提高了爆破效果,从而进一步提高了钻孔的注浆量,并且减少了钻孔的涌水量。By applying the technical solution of the present invention, a method for pre-splitting and grouting in vertical shaft blasting is provided, which includes: drilling a plurality of blasting groups around the periphery of the bottom wall of the vertical shaft, each blasting group includes a plurality of boreholes; Loading explosives in the middle; putting granular plugs into the drilled holes after the explosives are loaded; using steel components to block the openings of the drilled holes after loading the explosives; stacking heavy objects on the steel components; detonating and checking the blasting quality; Post-drilling grouting. By adopting this solution, by setting up multiple blasting groups, and each blasting group includes multiple drilling holes, sufficient free surfaces can be provided for the drilling holes that need to be blasted, thereby reducing the blasting power in the axial direction of the drilling holes; At the same time, the drilled hole is first blocked with granular plugging materials, and then the opening of the drilled hole is blocked again with steel components, and heavy objects are stacked on the steel components, which further ensures the blocking effect. Using the vertical well blasting pre-split grouting method of this scheme, firstly drill multiple blasting groups on the periphery of the bottom wall of the vertical well, wherein the multiple blasting groups include multiple boreholes, and explosives are charged in the boreholes that need to be blasted, and then the particles are blasted. Then, the opening of the drilled hole filled with explosives is blocked with steel components, and heavy objects are stacked on the steel components to improve the blocking effect. After blasting, check the blasting quality and grouting the blasted borehole. By adopting this method, the blasting effect is improved, thereby further increasing the amount of grouting in the borehole, and reducing the amount of water inflow in the borehole.
附图说明Description of drawings
构成本申请的一部分的说明书附图用来提供对本发明的进一步理解,本发明的示意性实施例及其说明用于解释本发明,并不构成对本发明的不当限定。在附图中:The accompanying drawings forming a part of the present application are used to provide further understanding of the present invention, and the exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the attached image:
图1示出了本发明的实施例提供的立井爆破预裂注浆方法的流程图;Fig. 1 shows the flow chart of the vertical shaft blasting pre-split grouting method provided by an embodiment of the present invention;
图2示出了使用图1中立井爆破预裂注浆方法的工作区域示意图。FIG. 2 shows a schematic diagram of the working area using the blasting pre-split grouting method of the vertical well shown in FIG. 1 .
其中,上述附图包括以下附图标记:Wherein, the above-mentioned drawings include the following reference signs:
10、钻孔;20、颗粒状封堵物;30、钢构件;31、钢杆;32、钢板;33、通孔;40、重物;50、配重块;60、炸药。10. Drilling holes; 20. Granular plugs; 30. Steel components; 31. Steel rods; 32. Steel plates; 33. Through holes; 40. Heavy objects; 50. Counterweights; 60. Explosives.
具体实施方式Detailed ways
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述。显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。以下对至少一个示例性实施例的描述实际上仅仅是说明性的,决不作为对本发明及其应用或使用的任何限制。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, but not all, embodiments of the present invention. The following description of at least one exemplary embodiment is merely illustrative in nature and is in no way intended to limit the invention, its application, or uses. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.
如图1和图2所示,本发明的实施例提供了一种立井爆破预裂注浆方法,包括:围绕立井底壁的周缘钻多个爆破组,每个爆破组中包括多个钻孔10;在需要爆破的钻孔10中装炸药60;将颗粒状封堵物20装入装炸药60后的钻孔10内;采用钢构件30封堵装炸药60后的钻孔10的开口;在钢构件30上堆积重物40;起爆并检查爆破质量;对爆破后的钻孔10注浆。As shown in FIG. 1 and FIG. 2 , an embodiment of the present invention provides a method for pre-splitting and grouting in vertical well blasting, including: drilling a plurality of blasting groups around the periphery of the bottom wall of the vertical well, and each blasting group includes a plurality of
采用该方案,通过设置多个爆破组,且每个爆破组中包括多个钻孔10,这样能够为需要爆破的钻孔10提供足够的自由面,从而减弱了在钻孔10轴向上的爆破威力;同时,首先采用颗粒状封堵物20对钻孔10进行封堵,随后采用钢构件30对钻孔10的开口再次进行封堵,且在钢构件30上堆积重物,这样进一步保证了封堵效果。利用本方案的立井爆破预裂注浆方法,首先在立井底壁周缘钻多个爆破组,其中,多个爆破组中包括多个钻孔10,在需要爆破的钻孔10中装炸药60,随后将颗粒状封堵物20装入装完炸药60的钻孔10中进行封堵;然后采用钢构件30对装炸药60后的钻孔10的开口进行封堵,并在钢构件30上堆积重物40以提高封堵效果,最后进行起爆,检查爆破质量后对爆破后的钻孔10注浆。采用这种方法,提高了爆破效果,从而进一步提高了钻孔10的注浆量,并且减少了钻孔10的涌水量。With this solution, by arranging multiple blasting groups, and each blasting group includes
其中,爆破组中的多个钻孔10均平行。将多个钻孔10平行设置,这样相邻的钻孔10能够为需要爆破的钻孔10提供足够的自由面,使得爆破威力向径向扩展,有效减小了轴向冲击。Wherein, the plurality of
在本实施例中,钻孔10的直径为75mm至90mm,钻孔10的深度大于30m。将钻孔10的直径设置成75mm至90mm,且钻孔10的深度大于30m,这样钻孔10的直径可根据现场实际的需求做出调整,从而提高了通用性。In this embodiment, the diameter of the
具体地,在需要爆破的钻孔10中装炸药60包括:将炸药60与导爆索、细长支撑物连接;在细长支撑物的下端连接配重块50;将配重块50、炸药60、导爆索和细长支撑物伸入钻孔10内。由于在进行爆破预裂时,钻孔10内一般充满水,甚至以较大流量往出喷水,水压较大,这就导致炸药难以沉底,采用上述设置方式,将细长支撑物的下端连接配重块50,且炸药与导爆索、细长支撑物连接,这样即可确保炸药能够沉底,以保证爆破效果。Specifically, loading the explosive 60 in the
其中,细长支撑物为绳索或刚性管,导爆索为多根。将细长支撑物设置成绳索或刚性管,这样增大了重量,能够进一步确保炸药60能够沉底,以保证爆破效果;将导爆索设置成多根,这样能够确保炸药60能够被引爆,同时也可以增强爆破效果。Among them, the slender supports are ropes or rigid pipes, and the detonating cords are multiple. The slender supports are arranged as ropes or rigid pipes, which increases the weight, and can further ensure that the explosive 60 can sink to the bottom to ensure the blasting effect; It can also enhance the blasting effect.
具体地,颗粒状封堵物20包括土壤、沙子、碎石中的至少一种,重物40为沙袋。将颗粒状封堵物20包括土壤、沙子、碎石中的至少一种,这样即可确保能够将炸药60压紧,提高了封堵效果;将重物40设置成沙袋,进一步提高了封堵效果。Specifically, the
在本实施例中,钢构件30包括相互连接的钢杆31和钢板32,钢杆31插入钻孔10内,钢板32封堵钻孔10的开口。通过上述设置方式,将钢杆31插入钻孔10内,且利用钢板32封堵钻孔10的开口,这样进一步保证了封堵效果,提高了爆破效果。In this embodiment, the steel member 30 includes a steel rod 31 and a steel plate 32 which are connected to each other. The steel rod 31 is inserted into the
其中,钢杆31的长度不小于钻孔10深度的20%。将钢杆31的长度设置成不小于钻孔10深度的20%,这样能够保证钢杆31能够放入钻孔10,其钢杆31的具体长度可根据现场实际调整,从而提高了钢构件30的通用性。Wherein, the length of the steel rod 31 is not less than 20% of the depth of the drilled
进一步地,钢构件30具有贯穿钢杆31和钢板32的通孔33。通过设置通孔33,便于导爆索和细长支撑物穿过。Further, the steel member 30 has a through hole 33 penetrating the steel rod 31 and the steel plate 32 . By arranging the through hole 33, it is convenient for the detonating cord and the elongated support to pass through.
具体地,钢板32为圆形板,钢板32的直径为1000mm至1200mm,钢杆31的外径为74mm至89mm。将钢板32的直径设置成1000mm至1200mm,钢杆31的外径设置成74mm至89mm,这样可根据现场实际的尺寸做出相应的调整,从而提高了钢构件30的通用性。Specifically, the steel plate 32 is a circular plate, the diameter of the steel plate 32 is 1000 mm to 1200 mm, and the outer diameter of the steel rod 31 is 74 mm to 89 mm. The diameter of the steel plate 32 is set to 1000mm to 1200mm, and the outer diameter of the steel rod 31 is set to 74mm to 89mm, so that corresponding adjustments can be made according to the actual size on site, thereby improving the versatility of the steel member 30 .
本方案的具体实施例如下:Specific examples of this scheme are as follows:
以某煤矿立井开拓为例:该立井净径为7m,荒径为8m,设计深度为800m。施工至550m左右时,实测涌水量最少为2-4m3/h,最大超过30m3/h,需要爆破预裂进行注浆,减少涌水量,保证开拓安全,采用常规爆破方法冲孔现象比较严重,注浆效果不佳,采用本方案进行注浆,步骤如下:Take the development of a coal mine shaft as an example: the shaft has a clear diameter of 7m, a barren diameter of 8m, and a design depth of 800m. When the construction reaches about 550m, the measured water inflow is at least 2-4m 3 /h, and the maximum exceeds 30m 3 /h. It is necessary to blast pre-splitting for grouting to reduce the amount of water inflow and ensure the safety of development. The phenomenon of punching holes by conventional blasting methods is relatively serious. , the grouting effect is not good, this scheme is used for grouting, and the steps are as follows:
1、钻孔:钻孔直径为90mm,深度为30m~50m,钻孔位置为沿直径7.5m处,沿井筒周长共设计26个钻孔,两个钻孔为一组,尽量保证二者平行,钻孔外倾角度不大于5度;1. Drilling hole: The diameter of the drilling hole is 90mm, the depth is 30m-50m, and the drilling position is along the diameter of 7.5m. A total of 26 drilling holes are designed along the circumference of the wellbore. Parallel, the camber angle of the drill hole is not more than 5 degrees;
2、装药:按照设计方案,用胶带将药卷和固定在绳索和双股导爆索之上,同时采用导爆索与炸药有助于抵消深水条件下炸药威力减弱的影响,在绳索末端施加适当的配重,保证装药到位,绳索与导爆索要留足长度;2. Charge: According to the design plan, use tape to fix the coil on the rope and the double-strand detonating cord. At the same time, the detonating cord and explosive are used to help offset the impact of the weakening of the explosive in deep water conditions. At the end of the rope Appropriate counterweight should be applied to ensure that the charge is in place, and the rope and detonating cable should be kept in sufficient length;
3、封孔:堵塞长度不小于孔长的20%,首先采用黄土、沙子、碎石等进行分级堵塞,孔口处预留出孔口堵塞钢构件安装空间;安装孔口堵塞钢构件,注意将导爆索及绳索从钢构件中的通孔穿出;在钢构件上堆积足够沙袋,确保封堵质量;3. Hole sealing: The blocking length is not less than 20% of the hole length. First, use loess, sand, gravel, etc. for graded blocking, and reserve the outlet at the orifice to block the installation space of the steel components; Pass the detonating cord and rope through the through hole in the steel member; stack enough sandbags on the steel member to ensure the blocking quality;
4、起爆:将雷管与导爆索相连,在井上进行起爆;4. Detonation: connect the detonator to the detonating cord and detonate on the well;
5、检查爆破质量:起爆后,进入工作面检查爆破质量,并未发生冲孔现象;5. Check the blasting quality: After detonation, enter the working face to check the blasting quality, and there is no punching phenomenon;
6、注浆:爆破后进行注浆,注浆量较未采用此方法爆破前大幅增加,说明此方法爆破预裂效果良好。注浆后涌水量大幅减少,同时也保证了继续掘进的安全。该段累计注浆量超出了260t。6. Grouting: grouting is carried out after blasting, and the amount of grouting is greatly increased compared with that before blasting without this method, indicating that this method has a good blasting pre-splitting effect. After grouting, the water inflow is greatly reduced, and the safety of continuous excavation is also ensured. The cumulative amount of grouting in this section exceeded 260t.
上述表格为采用本方法进行爆破的数据值,由上表可知,通过本次注浆施工,该段单孔涌水量均不大于2m3/h,基本不出水或出水量较小。The above table is the data value of blasting by this method. It can be seen from the above table that through this grouting construction, the single hole water inflow in this section is not more than 2m 3 /h, basically no water or a small amount of water.
需要注意的是,这里所使用的术语仅是为了描述具体实施方式,而非意图限制根据本申请的示例性实施方式。如在这里所使用的,除非上下文另外明确指出,否则单数形式也意图包括复数形式,此外,还应当理解的是,当在本说明书中使用术语“包含”和/或“包括”时,其指明存在特征、步骤、操作、器件、组件和/或它们的组合。It should be noted that the terminology used herein is for the purpose of describing specific embodiments only, and is not intended to limit the exemplary embodiments according to the present application. As used herein, unless the context clearly dictates otherwise, the singular is intended to include the plural as well, furthermore, it is to be understood that when the terms "comprising" and/or "including" are used in this specification, it indicates that There are features, steps, operations, devices, components and/or combinations thereof.
除非另外具体说明,否则在这些实施例中阐述的部件和步骤的相对布置、数字表达式和数值不限制本发明的范围。同时,应当明白,为了便于描述,附图中所示出的各个部分的尺寸并不是按照实际的比例关系绘制的。对于相关领域普通技术人员已知的技术、方法和设备可能不作详细讨论,但在适当情况下,所述技术、方法和设备应当被视为授权说明书的一部分。在这里示出和讨论的所有示例中,任何具体值应被解释为仅仅是示例性的,而不是作为限制。因此,示例性实施例的其它示例可以具有不同的值。应注意到:相似的标号和字母在下面的附图中表示类似项,因此,一旦某一项在一个附图中被定义,则在随后的附图中不需要对其进行进一步讨论。The relative arrangement of the components and steps, the numerical expressions and numerical values set forth in these embodiments do not limit the scope of the invention unless specifically stated otherwise. Meanwhile, it should be understood that, for the convenience of description, the dimensions of various parts shown in the accompanying drawings are not drawn in an actual proportional relationship. Techniques, methods, and devices known to those of ordinary skill in the relevant art may not be discussed in detail, but where appropriate, such techniques, methods, and devices should be considered part of the authorized description. In all examples shown and discussed herein, any specific value should be construed as illustrative only and not as limiting. Accordingly, other examples of exemplary embodiments may have different values. It should be noted that like numerals and letters refer to like items in the following figures, so once an item is defined in one figure, it does not require further discussion in subsequent figures.
在本发明的描述中,需要理解的是,方位词如“前、后、上、下、左、右”、“横向、竖向、垂直、水平”和“顶、底”等所指示的方位或位置关系通常是基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,在未作相反说明的情况下,这些方位词并不指示和暗示所指的装置或元件必须具有特定的方位或者以特定的方位构造和操作,因此不能理解为对本发明保护范围的限制;方位词“内、外”是指相对于各部件本身的轮廓的内外。In the description of the present invention, it should be understood that the orientations indicated by orientation words such as "front, rear, top, bottom, left, right", "horizontal, vertical, vertical, horizontal" and "top, bottom" etc. Or the positional relationship is usually based on the orientation or positional relationship shown in the drawings, which is only for the convenience of describing the present invention and simplifying the description, and these orientation words do not indicate or imply the indicated device or element unless otherwise stated. It must have a specific orientation or be constructed and operated in a specific orientation, so it cannot be construed as a limitation on the protection scope of the present invention; the orientation words "inside and outside" refer to the inside and outside relative to the outline of each component itself.
为了便于描述,在这里可以使用空间相对术语,如“在……之上”、“在……上方”、“在……上表面”、“上面的”等,用来描述如在图中所示的一个器件或特征与其他器件或特征的空间位置关系。应当理解的是,空间相对术语旨在包含除了器件在图中所描述的方位之外的在使用或操作中的不同方位。例如,如果附图中的器件被倒置,则描述为“在其他器件或构造上方”或“在其他器件或构造之上”的器件之后将被定位为“在其他器件或构造下方”或“在其他器件或构造之下”。因而,示例性术语“在……上方”可以包括“在……上方”和“在……下方”两种方位。该器件也可以其他不同方式定位(旋转90度或处于其他方位),并且对这里所使用的空间相对描述作出相应解释。For ease of description, spatially relative terms, such as "on", "over", "on the surface", "above", etc., may be used herein to describe what is shown in the figures. The spatial positional relationship of one device or feature shown to other devices or features. It should be understood that spatially relative terms are intended to encompass different orientations of the device in use or operation in addition to the orientation depicted in the figures. For example, if the device in the figures is turned over, elements described as "above" or "over" other devices or features would then be oriented "below" or "over" the other devices or features under other devices or constructions". Thus, the exemplary term "above" can encompass both an orientation of "above" and "below." The device may also be otherwise oriented (rotated 90 degrees or at other orientations) and the spatially relative descriptions used herein interpreted accordingly.
此外,需要说明的是,使用“第一”、“第二”等词语来限定零部件,仅仅是为了便于对相应零部件进行区别,如没有另行声明,上述词语并没有特殊含义,因此不能理解为对本发明保护范围的限制。In addition, it should be noted that the use of words such as "first" and "second" to define components is only for the convenience of distinguishing corresponding components. Unless otherwise stated, the above words have no special meaning and therefore cannot be understood to limit the scope of protection of the present invention.
以上所述仅为本发明的优选实施例而已,并不用于限制本发明,对于本领域的技术人员来说,本发明可以有各种更改和变化。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210796202.6A CN115012815A (en) | 2022-07-07 | 2022-07-07 | Vertical shaft blasting presplitting grouting method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210796202.6A CN115012815A (en) | 2022-07-07 | 2022-07-07 | Vertical shaft blasting presplitting grouting method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN115012815A true CN115012815A (en) | 2022-09-06 |
Family
ID=83078566
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202210796202.6A Pending CN115012815A (en) | 2022-07-07 | 2022-07-07 | Vertical shaft blasting presplitting grouting method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115012815A (en) |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP0109067A1 (en) * | 1982-11-13 | 1984-05-23 | Fried. Krupp Gesellschaft mit beschränkter Haftung | Process and apparatus for breaking up hard compact material |
| CN1338038A (en) * | 1998-12-14 | 2002-02-27 | 洛克泰克有限公司 | Method and apparatus for charging a hole |
| CN102817633A (en) * | 2012-09-13 | 2012-12-12 | 广东宏大爆破股份有限公司 | Device for draining gas by deep hole crack control blasting and precracking method |
| CN102878874A (en) * | 2012-10-09 | 2013-01-16 | 北京科技大学 | Deep-hole pre-splitting blasting grouting method |
| CN107436114A (en) * | 2017-09-06 | 2017-12-05 | 中钢集团马鞍山矿山研究院有限公司 | A kind of charge system suitable for water bearing blasthole explosion |
| CN111780637A (en) * | 2020-07-20 | 2020-10-16 | 湖南海螺水泥有限公司 | A kind of deep water blast hole charging device and charging method thereof |
| CN112432569A (en) * | 2020-11-03 | 2021-03-02 | 中建海峡建设发展有限公司 | Hole forming method for punching cast-in-place pile by water bag blasting |
-
2022
- 2022-07-07 CN CN202210796202.6A patent/CN115012815A/en active Pending
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP0109067A1 (en) * | 1982-11-13 | 1984-05-23 | Fried. Krupp Gesellschaft mit beschränkter Haftung | Process and apparatus for breaking up hard compact material |
| CN1338038A (en) * | 1998-12-14 | 2002-02-27 | 洛克泰克有限公司 | Method and apparatus for charging a hole |
| CN102817633A (en) * | 2012-09-13 | 2012-12-12 | 广东宏大爆破股份有限公司 | Device for draining gas by deep hole crack control blasting and precracking method |
| CN102878874A (en) * | 2012-10-09 | 2013-01-16 | 北京科技大学 | Deep-hole pre-splitting blasting grouting method |
| CN107436114A (en) * | 2017-09-06 | 2017-12-05 | 中钢集团马鞍山矿山研究院有限公司 | A kind of charge system suitable for water bearing blasthole explosion |
| CN111780637A (en) * | 2020-07-20 | 2020-10-16 | 湖南海螺水泥有限公司 | A kind of deep water blast hole charging device and charging method thereof |
| CN112432569A (en) * | 2020-11-03 | 2021-03-02 | 中建海峡建设发展有限公司 | Hole forming method for punching cast-in-place pile by water bag blasting |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP6634375B2 (en) | Explosive tube tube having air gap and rock blasting method using the same | |
| CN111720139B (en) | Roadway impact ground pressure structure cooperative prevention and control method influenced by repeated mining | |
| CN106014473B (en) | A kind of cross borehole constrained expansion explosion network permeability-increasing gas drainage method | |
| CN107165638A (en) | A kind of deep tunnel rock burst active preventing control method | |
| CN110260731B (en) | A kind of well-forming construction method for sliding well and cutting well | |
| CN106767212B (en) | A kind of two-region undercut blast hole arrangement and its explosion well completion method of application | |
| CN112161534B (en) | A one-step recovery controlled blasting method for underground mine upward approach | |
| CN109211043B (en) | Water-spaced charging method for peripheral holes of smooth blasting of tunnel | |
| CN102817633B (en) | The device drawing out methane and the pre-splitting method of the controlled blasting of deep hole crack | |
| CN113404498A (en) | VCR mining method adopting novel blasting mode | |
| CN109973114B (en) | Comprehensive control method for surrounding rock of gob-side entry retaining without filling in deep part | |
| CN110307762B (en) | Quick well forming method for courtyard based on deep hole-by-hole detonation technology | |
| CN101487376A (en) | One-time excavation construction method for large-diameter large-depth pressure regulating well pilot shaft | |
| CN109974545A (en) | A Method for Suspended Roof Treatment of Medium and Deep Hole Blasting in Subsection Caving Method | |
| CN205245910U (en) | Shallow hole blasting structure | |
| CN112414237B (en) | A kind of natural caving Faraday over-hard surrounding rock treatment method | |
| JP5407142B2 (en) | Smooth blasting method | |
| CN115012815A (en) | Vertical shaft blasting presplitting grouting method | |
| CN112595192B (en) | A variable-diameter cutting structure and method for roadway excavation | |
| CN111486759B (en) | One-time controlled blasting demolition method for elevator shaft outside dam body | |
| CN108061491A (en) | A kind of Pile Diameter is the bridge cylinder pile foundation blasting method of 1.4-1.6m | |
| CN113700016B (en) | Ground water plugging method for extremely strong flowing water passing channel of underground mine | |
| CN108061492A (en) | A kind of Pile Diameter is the bridge cylinder pile foundation blasting method of 0.8-1m | |
| CN219328376U (en) | Deep hole directional blasting charging structure | |
| CN116164600A (en) | Simple low-consumption smooth blasting method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20220906 |