CN101725259A - Modular house building structure and construction method thereof - Google Patents
Modular house building structure and construction method thereof Download PDFInfo
- Publication number
- CN101725259A CN101725259A CN200810199145A CN200810199145A CN101725259A CN 101725259 A CN101725259 A CN 101725259A CN 200810199145 A CN200810199145 A CN 200810199145A CN 200810199145 A CN200810199145 A CN 200810199145A CN 101725259 A CN101725259 A CN 101725259A
- Authority
- CN
- China
- Prior art keywords
- column
- wall
- floor
- building structure
- fixedly connected
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Load-Bearing And Curtain Walls (AREA)
Abstract
Description
技术领域technical field
本发明涉及采用模块结构的建筑结构,本发明还涉及一种通过组装这样的模块建造此类建筑物的建造方法,属于建筑技术领域。The invention relates to a building structure using a modular structure, and also relates to a construction method for building such a building by assembling such modules, which belongs to the field of building technology.
背景技术Background technique
一般的建筑结构都是通过现场浇注混凝土的方法建筑的,这样的建造方法耗时长,而且会产生大量的建筑废料,不利于环保;目前,有采用模块化建筑结构来建造房子,但是,很多这样的方法却存在着各种各样的弊端。这些弊端集中表现在:对精心制作的用来安装模块化镶板的框架体系组装的过程十分复杂;把结构化镶板连接固定在一起的紧固件数目繁多,使用起来十分不便;并且,某些模块化结构存在着不良的结构强度。如申请人BatimPro SA在法国申请的专利文件第2389724号中提出的一种模块化施工方法,该专利文件提出了一种模块化建筑结构,它使用的是带有相互毗邻纵向侧边的镶板,形状呈互补式。镶板通过螺丝连接在一起,并在连接点处用金属板加固。有关模块化建筑应用领域使用的层压式泡沫塑料板生产技术。这样的构造相对比较复杂,而且在模块组装后一般还需要对相应的模块进行装修,这样建筑时间相应也会加长,而且也会产生建筑废料,也无法在组装好的情况下就能入住。General building structures are built by pouring concrete on site. This construction method takes a long time and produces a lot of construction waste, which is not conducive to environmental protection. At present, houses are built with modular building structures, but many of them method has various disadvantages. These disadvantages are concentrated in: the process of assembling the elaborate frame system used to install the modular panels is very complicated; Some modular structures have poor structural strength. A method of modular construction as proposed by the applicant BatimPro SA in patent document No. 2389724 filed in France, which proposes a modular building structure using panels with mutually adjoining longitudinal sides , with a complementary shape. The panels are joined together by screws and reinforced with metal plates at the connection points. Technology for the production of laminated foam panels for modular building applications. Such a structure is relatively complicated, and after the modules are assembled, the corresponding modules generally need to be decorated, so that the construction time will be correspondingly longer, and construction waste will also be generated, and it is impossible to move in after the assembly is complete.
发明内容Contents of the invention
本发明的目的是为了克服现有技术中的不足之处,提供一种结构简单,装置方便的建筑结构;The purpose of the present invention is in order to overcome the weak point in the prior art, provide a kind of simple in structure, the building structure of convenient installation;
本发明的另一个目的是提供一种工艺简单、采用模块化组件、能快速建造、组装后无需重新装修就能入住的建筑结构建造方法。Another object of the present invention is to provide a building structure construction method that is simple in process, adopts modular components, can be built quickly, and can be occupied without redecoration after assembly.
为了达到上述目的,本发明采用以下方案:In order to achieve the above object, the present invention adopts the following scheme:
一种模块化房屋建筑结构,其包括多个间隔设置并分别与基础固定连接的钢筋架;及多个由模块化生产的柱体、多个由模块化生产的墙体和由模块化生产的楼板;A modular building structure, which includes a plurality of steel frames arranged at intervals and respectively fixedly connected to the foundation; and a plurality of modularly produced columns, a plurality of modularly produced walls and modularly produced floor;
所述的柱体设有可容置钢筋架的竖向通孔,在柱体上还设有连接位,所述的柱体套装在钢筋架上并能够通过向竖向通孔内浇注混凝土使柱体、墙体及钢筋架结合为整体;The column is provided with a vertical through hole that can accommodate the steel frame, and a connection position is also provided on the column. The column is set on the steel frame and can be used by pouring concrete into the vertical through hole. The column, wall and steel frame are combined into a whole;
所述的墙体固定连接在相邻柱体之间,墙体的两端设有预留连接钢筋,所述的预留连接钢筋通过柱体上的连接位与钢筋架固定连接;The wall is fixedly connected between adjacent columns, and the two ends of the wall are provided with reserved connecting reinforcement, and the reserved connecting reinforcement is fixedly connected to the reinforcement frame through the connection position on the column;
所述的楼板固定设置在墙体上。The floor slab is fixedly arranged on the wall.
如上所述的一种模块化房屋建筑结构,其中所述的柱体为一中空柱体。A modular building structure as described above, wherein the column is a hollow column.
如上所述的一种模块化房屋建筑结构,其中所述的柱体可由多片构件组成,并在多片构件组合后能形成所述的中空柱体。A modular building structure as described above, wherein the column can be composed of multiple components, and the hollow column can be formed after the multiple components are combined.
如上所述的一种模块化房屋建筑结构,其中在所述的楼板上设有接口,在所述的接口中设有连接钢筋,所述的连接钢筋可与设置在墙体顶端的预留连接钢筋固定连接,并通过向竖向接口内浇注混凝土使楼板和墙体结构为整体。A modular building structure as described above, wherein an interface is provided on the floor, and a connecting steel bar is provided in the interface, and the connecting steel bar can be connected with the reserved connection at the top of the wall The steel bars are fixedly connected, and the floor and wall structures are integrated by pouring concrete into the vertical interface.
如上所述的一种模块化房屋建筑结构,其中在所述的柱体上设有用于装配墙体时定位的限位槽,在所述的柱体和墙体相应的位置上分别设有定位孔,在所述的定位孔上设有定位连接片。A modular building structure as described above, wherein the column is provided with a limit groove for positioning when assembling the wall, and positioning slots are respectively provided at the corresponding positions of the column and the wall. holes, and positioning connecting pieces are arranged on the positioning holes.
如上所述的一种模块化房屋建筑结构,其中在所述的墙体上设有装饰层。A modular building structure as described above, wherein the wall is provided with a decorative layer.
如上所述的一种模块化房屋建筑结构,其中在所述的楼板上设有装饰层。A modular building structure as described above, wherein a decorative layer is provided on the floor.
如上所述的一种模块化房屋建筑结构,其中在所述的柱体上设有装饰层。A modular building structure as described above, wherein a decorative layer is provided on the column.
如上所述的一种模块化房屋建筑结构,其中在所述的楼板上设有用于楼板之间相互连接的预留钢筋。A modular building structure as described above, wherein the floor slabs are provided with reserved steel bars for interconnection between the slabs.
一种模块化房屋建筑结构的方法,包括以下步骤:A method for modular building structure, comprising the following steps:
a、设置钢筋架a. Set up steel frame
在基础上间隔固定设置多个钢筋架;On the foundation, a plurality of reinforcement frames are fixed at intervals;
b、定位、安装柱体b. Locate and install the column
把设有竖向通孔的柱体套装所述的钢筋架;The steel bar frame described above is set by the column body provided with the vertical through hole;
c、镶嵌墙体c. Mosaic wall
在墙体与柱体相互交接的地方涂抹密封剂,把墙体镶嵌在柱体之间并调整好固定;这时设置在墙体上的预留连接钢筋置入开设在柱体上的连接位中并与柱体中的钢筋架固定连接起来;Apply sealant at the intersection of the wall and the column, inlay the wall between the columns and adjust and fix it; and fixedly connected with the steel frame in the column;
d、安装楼板d. Install the floor
在楼板与墙体、柱体相互交接的地方涂抹密封剂,把楼板安装在墙体上,此时墙体顶端的预留连接钢筋置入开设在楼板上的接口中,并与设置接口中的连接钢筋固定连接;Apply sealant on the joints between the floor, the wall and the column, and install the floor on the wall. At this time, the reserved connecting steel bar at the top of the wall is inserted into the interface on the floor, and is connected with the setting interface. Connecting reinforcement fixed connection;
e、浇注混凝土e. Pouring concrete
向上述柱体的竖向通孔和楼板上的接口上分别浇注混凝土,使墙体、楼板、柱体之间相互结构为整体。Concrete is respectively poured into the vertical through holes of the column and the interface on the floor, so that the wall, the floor, and the column are mutually structured as a whole.
综上所述,本发明的有益效果:In summary, the beneficial effects of the present invention:
1、本发明建筑结构采用模块化组件建造,建筑结构的所有构件(除房屋地底以下基础)都可由工厂制造,并且由工厂模具生产出的柱体、墙体、楼面板等,尺寸极其标准,墙面、楼板平整光滑,柱角、角线圆滑顺直,视觉效果好;1. The building structure of the present invention is constructed by modular components, and all components of the building structure (except the foundation below the house ground) can be manufactured by the factory, and the columns, walls, floor panels, etc. produced by the factory molds are extremely standard in size, The walls and floors are flat and smooth, the column corners and corner lines are smooth and straight, and the visual effect is good;
2、本发明中由于所有墙体、楼板表面光滑,无需二次抹灰整理已可直接粘贴瓷片或上漆,减少了工序,也不会出现脱层、掉灰等质量安全问题;2. In the present invention, since the surfaces of all walls and floors are smooth, tiles or paint can be pasted directly without secondary plastering and finishing, which reduces the process and does not cause quality and safety problems such as delamination and ash falling;
3、建筑结构的所有内外装修都可在工厂完成,安装过程中不影响已有的装修。安装好房子后即可入住,也减少了建筑废料的产生;3. All interior and exterior decoration of the building structure can be completed in the factory, and the existing decoration will not be affected during the installation process. After the house is installed, you can move in, which also reduces the generation of construction waste;
4、本发明建筑结构中所有的水电管线、线盒在生产中已预先埋入墙体内,位置、尺寸准确无误,在拼装时接入即可。门、窗框架也在生产墙体时一并浇铸完成,不会发生渗水等传统房屋常出现的问题;4. All the water and electricity pipelines and wire boxes in the building structure of the present invention have been pre-embedded in the wall during production, with accurate positions and sizes, and can be connected during assembly. The door and window frames are also cast together during the production of the wall, so there will be no problems that often occur in traditional houses such as water seepage;
5、本发明中可在所有的墙体、楼板非主要受力部分采用中空或填充泡沫设计,这样可以提高墙体、楼板隔热隔音效果和减少重量;5. In the present invention, hollow or foam-filled design can be adopted in all non-main stress-bearing parts of walls and floors, which can improve the heat and sound insulation effect of walls and floors and reduce weight;
6、采用本发明方法建造的建筑结构具有快捷性:比如一间180平方米2层别墅,用这种方法可在2~3天内建好,接通水电,5天内则可入住。一幢8层高4000平方米的楼房,可在15天内建成;6. The building structure built by the method of the present invention has quickness: such as a 180 square meter villa with 2 floors, which can be built in 2 to 3 days with this method, connected to water and electricity, and can be moved in within 5 days. An 8-story building with a height of 4,000 square meters can be built within 15 days;
7、本发明建筑结构具有可变性:由于模块在工厂制造,并有多种规格及结构。在符合安全的前提下,可任意拼装,加大、加间、加层、变位等;7. The building structure of the present invention has variability: the modules are manufactured in factories and have various specifications and structures. Under the premise of safety, it can be assembled arbitrarily, enlarged, added space, added layers, changed positions, etc.;
8、本发明建筑结构具有可拆解性:只要破坏墙体、楼板、柱体之间的连接部件,就能进行拆卸和转移。8. The building structure of the present invention is detachable: it can be disassembled and transferred as long as the connecting parts between the walls, floors and columns are destroyed.
附图说明Description of drawings
图1为本发明中柱体的示意图;Fig. 1 is the schematic diagram of cylinder in the present invention;
图2为本发明中墙体的示意图;Fig. 2 is the schematic diagram of body of wall among the present invention;
图3为本发明中墙体的示意图;Fig. 3 is the schematic diagram of body of wall among the present invention;
图4为本发明中楼板的示意图;Fig. 4 is the schematic diagram of floor slab in the present invention;
图5为本发明中钢筋架在基础上的示意图;Fig. 5 is the schematic diagram on the foundation of steel frame among the present invention;
图6为本发明中柱体设置在钢筋架上的示意图;Fig. 6 is the schematic diagram that cylinder is arranged on the reinforcing bar frame among the present invention;
图7为本发明中墙体设置在柱体之间的示意图;Fig. 7 is a schematic diagram of walls arranged between columns in the present invention;
图8为图7中A处的放大图;Fig. 8 is an enlarged view of place A in Fig. 7;
图9为本发明中墙体设置在柱体之间的示意图;Fig. 9 is a schematic diagram of walls arranged between columns in the present invention;
图10为本发明中墙体设置在柱体之间后的示意图;Fig. 10 is a schematic diagram after the wall is arranged between the columns in the present invention;
图11为图10中B处的放大图;Figure 11 is an enlarged view at B in Figure 10;
图12为本发明中楼板设置在墙体上的示意图;Fig. 12 is a schematic diagram of the floor being arranged on the wall in the present invention;
图13为本发明中楼板设置在墙体上之后的示意图;Fig. 13 is a schematic diagram after the floor slab is arranged on the wall in the present invention;
图14为图13中C处的放大图;Figure 14 is an enlarged view at C in Figure 13;
图15为本发明中柱体的另一种实施方式的示意图。Fig. 15 is a schematic diagram of another embodiment of the column in the present invention.
具体实施方式Detailed ways
下面结合附图说明和具体实施方式对本发明做进一步描述:The present invention will be further described below in conjunction with accompanying drawing description and specific embodiment:
如图1至14所示的一种模块化房屋建筑结构,其包括多个间隔设置并分别与基础固定连接的钢筋架1;及多个由模块化生产的柱体4、多个由模块化生产的墙体2和由模块化生产的楼板3;A modular building structure as shown in Figures 1 to 14, it includes a plurality of
所述的柱体4设有可容置钢筋架1的竖向通孔41,在柱体4上还设有连接位5,所述的柱体4套装在钢筋架1上并能够通过向竖向通孔41内浇注混凝土使柱体4、墙体2及钢筋架1结合为整体;The
所述的墙体2固定连接在相邻柱体4之间,墙体2的两端设有预留连接钢筋6,所述的预留连接钢筋6通过柱体4上的连接位5与钢筋架1固定连接;The
所述的楼板3固定设置在墙体2上。The
本发明中所述的柱体4为一中空柱体,其由模块化生产的。在所述的柱体4上设有用于装配墙体2时定位的限位槽9,在所述的柱体4和墙体2相应的位置上分别设有定位孔10,在所述的定位孔10上设有定位连接片11。The
本发明中在所述的楼板3上设有接口7,在所述的接口7中设有连接钢筋8,所述的连接钢筋8可与设置在墙体2顶端的预留连接钢筋6固定连接,并通过向竖向接口7内浇注混凝土使楼板3和墙体2结构为整体。本发明中如果模块化房屋建筑结构占据的空间比较大,必须采用多块楼板3封顶的话,在所述的楼板3上就需要设有用于楼板之间相互连接的预留钢筋12。多块楼板3在设有预留钢筋12的地方与墙体2顶端形成一长接口,在所述长接口中浇注混凝土可使多块楼板3和墙体2之间相互结构为整体In the present invention, an interface 7 is provided on the
其中本发明模块化房屋建筑结构中采用的墙体2、楼板3和柱体4其表面光滑,无需二次抹灰整理已可直接粘贴瓷片或上漆,这样在墙体2、楼板3和柱体4其外表面上形成装饰层,在组装后无需再次装修,本发明中在墙体2上还已经开设了相应的门、窗等,这样节省了加工工序和建筑时间。Wherein the body of
图15为本发明中柱体4的另外一种实施方式为所述的柱体4可由多片构件组成,并在多片构件组合后能形成所述的中空柱体。如果使用这种柱体时,可以先固定好所有的墙体2,焊接好预留连接钢筋6与钢筋架1后,再合上柱体4。FIG. 15 shows another embodiment of the
本发明中建造上述的模块化房屋建筑结构的方法,包括以下步骤:The method for building the above-mentioned modular building structure among the present invention comprises the following steps:
a、设置钢筋架a. Set up steel frame
在基础上根据建筑设计间隔固定设置多个钢筋架1;On the basis, a plurality of reinforcement frames 1 are fixedly arranged according to architectural design intervals;
b、定位、安装柱体b. Locate and install the column
把设有竖向通孔41的柱体4套装所述的钢筋架1;Put the
c、镶嵌墙体c. Mosaic wall
在墙体2与柱体4相互交接的地方涂抹密封剂,把墙体2镶嵌在柱体4之间并调整好固定;这时设置在墙体2上的预留连接钢筋6置入开设在柱体4上的连接位中并与柱体4中的钢筋架1固定连接起来;Apply sealant on the joints between the
d、安装楼板d. Install the floor
在楼板3与墙体2、柱体4相互交接的地方涂抹密封剂,把楼板3安装在墙体2上,此时墙体2顶端的预留连接钢筋6置入开设在楼板3上的接口7中,并与设置接口7中的连接钢筋8固定连接;Apply sealant on the joints of
e、浇注混凝土e. Pouring concrete
向上述柱体4的竖向通孔41和楼板3上的接口7上分别浇注混凝土,使墙体2、楼板3、柱体4之间相互结构为整体。Concrete is respectively poured on the vertical through
本发明建筑结构采用模块化组件建造,建筑结构的所有构件(除房屋地底以下基础)都可由工厂制造,并且由工厂模具生产出的柱体、墙体、楼面板等,尺寸极其标准,墙面、楼板平整光滑,柱角、角线圆滑顺直,视觉效果好;本发明中由于所有墙体、楼板表面光滑,无需二次抹灰整理已可直接粘贴瓷片或上漆,减少了工序,也不会出现脱层、掉灰等质量安全问题;建筑结构的所有内外装修都可在工厂完成,安装过程中不影响已有的装修。安装好房子后即可入住,也减少了建筑废料的产生;本发明建筑结构中所有的水电管线、线盒在生产中已预先埋入墙体内,位置、尺寸准确无误,在拼装时接入即可。门、窗框架也在生产墙体时一并浇铸完成,不会发生渗水等传统房屋常出现的问题;本发明中可在所有的墙体、楼板非主要受力部分采用中空或填充泡沫设计,这样可以提高墙体、楼板隔热隔音效果和减少重量;采用本发明方法建造的建筑结构具有快捷性:比如一间180平方米2层别墅,用这种方法可在2~3天内建好,接通水电,5天内则可入住。一幢8层高4000平方米的楼房,可在15天内建成;本发明建筑结构具有可变性:由于模块在工厂制造,并有多种规格及结构。在符合安全的前提下,可任意拼装,加大、加间、加层、变位等;本发明建筑结构具有可拆解性:只要破坏墙体、楼板、柱体之间的连接部件,就能进行拆卸和转移。The building structure of the present invention is built with modular components, and all components of the building structure (except the foundation below the house) can be manufactured by the factory, and the columns, walls, floor panels, etc. produced by the factory molds are extremely standard in size. 1. The floor is flat and smooth, the column corners and corner lines are smooth and straight, and the visual effect is good; in the present invention, since all the walls and floors are smooth, tiles or paint can be directly pasted without secondary plastering and finishing, which reduces the process. There will be no quality and safety problems such as delamination and ash falling; all interior and exterior decoration of the building structure can be completed in the factory, and the existing decoration will not be affected during the installation process. After the house is installed, you can move in, which also reduces the generation of construction waste; all the water and electricity pipelines and wire boxes in the building structure of the present invention have been embedded in the wall in advance, and the position and size are accurate. That's it. The door and window frames are also casted together when the walls are produced, so there will be no problems that often occur in traditional houses such as water seepage; in the present invention, hollow or foam-filled designs can be used for all non-main stress-bearing parts of walls and floors. Can improve body of wall, floor slab heat and sound insulation effect and reduce weight like this; The building structure that adopts the inventive method to build has rapidity: such as a 180 square meter 2-story villa, can be built in 2~3 days with this method, Connected to water and electricity, you can move in within 5 days. An 8-story building with a height of 4,000 square meters can be built within 15 days; the building structure of the present invention has variability: because the modules are manufactured in a factory, and have various specifications and structures. Under the premise of safety, it can be assembled arbitrarily, enlarged, added space, added layers, shifted, etc.; Can be disassembled and transferred.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2008101991453A CN101725259B (en) | 2008-10-11 | 2008-10-11 | A modular building structure and its construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2008101991453A CN101725259B (en) | 2008-10-11 | 2008-10-11 | A modular building structure and its construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN101725259A true CN101725259A (en) | 2010-06-09 |
| CN101725259B CN101725259B (en) | 2011-10-26 |
Family
ID=42446750
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2008101991453A Expired - Fee Related CN101725259B (en) | 2008-10-11 | 2008-10-11 | A modular building structure and its construction method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN101725259B (en) |
Cited By (14)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101914949A (en) * | 2010-08-20 | 2010-12-15 | 黄坚强 | Assembled housing and manufacturing method thereof |
| CN102261189A (en) * | 2011-04-08 | 2011-11-30 | 应惠清 | Assembly-cast-in-situ type close column structure used in residential building with shear wall system |
| CN103233513A (en) * | 2013-04-24 | 2013-08-07 | 河南天丰节能板材科技股份有限公司 | Connecting structure for wall body and roof, roof connecting beam and modular integral house |
| CN103993654A (en) * | 2014-04-09 | 2014-08-20 | 北京工业大学 | Modularized assembly type steel structure house building system |
| CN104110070A (en) * | 2013-04-22 | 2014-10-22 | 吴庆元 | Modularized house |
| CN104120792A (en) * | 2013-04-24 | 2014-10-29 | 河南天丰节能板材科技股份有限公司 | Modularized integrated house |
| CN106522372A (en) * | 2016-09-20 | 2017-03-22 | 上海迅铸建筑科技有限公司 | Mixed type integrated house and construction method |
| CN106677372A (en) * | 2017-01-26 | 2017-05-17 | 杨玉明 | Sectional material structure for sectional material house building and house building method |
| CN108277917A (en) * | 2018-01-12 | 2018-07-13 | 赵志平 | A kind of sustainable full module-assembled building system of green and construction method |
| CN109079969A (en) * | 2018-09-19 | 2018-12-25 | 枣庄启程机械科技有限公司 | The novel wall for being embedded with door and window generates system and generation method |
| CN109214767A (en) * | 2017-07-07 | 2019-01-15 | 中联天盛防水科技股份有限公司 | A kind of roof waterproof renovation project Quality Process supervising platform |
| CN112012345A (en) * | 2020-07-27 | 2020-12-01 | 广东锦恒建筑有限公司 | Prefabricated building and construction method thereof |
| CN115680136A (en) * | 2022-11-06 | 2023-02-03 | 广州城建职业学院 | Modular green building construction method |
| CN116556547A (en) * | 2023-06-09 | 2023-08-08 | 河南迅隆实业有限公司 | Assembled building structure assembly and assembling method |
Family Cites Families (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5065558A (en) * | 1989-01-23 | 1991-11-19 | Gibraltar World International, Ltd. | Prefabricated modular building construction system |
| JP2953333B2 (en) | 1994-12-26 | 1999-09-27 | 三協アルミニウム工業株式会社 | Member connection structure |
| US6178714B1 (en) * | 1999-07-06 | 2001-01-30 | Robert S. Carney, Jr. | Modular temporary building |
| CN1125218C (en) * | 2000-06-15 | 2003-10-22 | 王永利 | Assembled arthitecutral structure |
| CN101058999A (en) * | 2007-06-01 | 2007-10-24 | 泰安市泰山区正发建材有限公司 | Energy-saving type module house |
-
2008
- 2008-10-11 CN CN2008101991453A patent/CN101725259B/en not_active Expired - Fee Related
Cited By (22)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101914949A (en) * | 2010-08-20 | 2010-12-15 | 黄坚强 | Assembled housing and manufacturing method thereof |
| CN101914949B (en) * | 2010-08-20 | 2012-07-04 | 黄坚强 | Assembled housing and manufacturing method thereof |
| CN102261189A (en) * | 2011-04-08 | 2011-11-30 | 应惠清 | Assembly-cast-in-situ type close column structure used in residential building with shear wall system |
| CN104110070A (en) * | 2013-04-22 | 2014-10-22 | 吴庆元 | Modularized house |
| CN104110070B (en) * | 2013-04-22 | 2016-06-22 | 吴庆元 | Modularized house |
| CN103233513A (en) * | 2013-04-24 | 2013-08-07 | 河南天丰节能板材科技股份有限公司 | Connecting structure for wall body and roof, roof connecting beam and modular integral house |
| CN104120792A (en) * | 2013-04-24 | 2014-10-29 | 河南天丰节能板材科技股份有限公司 | Modularized integrated house |
| CN103233513B (en) * | 2013-04-24 | 2015-07-15 | 河南天丰节能板材科技股份有限公司 | Connecting structure for wall body and roof, roof connecting beam and modular integral house |
| CN104120792B (en) * | 2013-04-24 | 2016-06-01 | 河南天丰节能板材科技股份有限公司 | Modularization integrated house |
| CN103993654A (en) * | 2014-04-09 | 2014-08-20 | 北京工业大学 | Modularized assembly type steel structure house building system |
| CN106522372A (en) * | 2016-09-20 | 2017-03-22 | 上海迅铸建筑科技有限公司 | Mixed type integrated house and construction method |
| CN106522372B (en) * | 2016-09-20 | 2019-01-15 | 上海迅铸建筑科技有限公司 | A kind of hybrid integrated house and construction method |
| CN106677372A (en) * | 2017-01-26 | 2017-05-17 | 杨玉明 | Sectional material structure for sectional material house building and house building method |
| CN109214767A (en) * | 2017-07-07 | 2019-01-15 | 中联天盛防水科技股份有限公司 | A kind of roof waterproof renovation project Quality Process supervising platform |
| CN109214767B (en) * | 2017-07-07 | 2021-07-06 | 中联天盛防水科技股份有限公司 | Roofing waterproof repair engineering quality process supervision platform |
| CN108277917A (en) * | 2018-01-12 | 2018-07-13 | 赵志平 | A kind of sustainable full module-assembled building system of green and construction method |
| CN109079969A (en) * | 2018-09-19 | 2018-12-25 | 枣庄启程机械科技有限公司 | The novel wall for being embedded with door and window generates system and generation method |
| CN112012345A (en) * | 2020-07-27 | 2020-12-01 | 广东锦恒建筑有限公司 | Prefabricated building and construction method thereof |
| CN112012345B (en) * | 2020-07-27 | 2021-10-01 | 广东锦恒建筑有限公司 | Prefabricated building and construction method thereof |
| CN115680136A (en) * | 2022-11-06 | 2023-02-03 | 广州城建职业学院 | Modular green building construction method |
| CN115680136B (en) * | 2022-11-06 | 2024-03-29 | 广州城建职业学院 | Modularized green building construction method |
| CN116556547A (en) * | 2023-06-09 | 2023-08-08 | 河南迅隆实业有限公司 | Assembled building structure assembly and assembling method |
Also Published As
| Publication number | Publication date |
|---|---|
| CN101725259B (en) | 2011-10-26 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101725259A (en) | Modular house building structure and construction method thereof | |
| CN101368428B (en) | Prefabricated component house and its construction method | |
| CN110359601A (en) | A kind of one-time formed energy saving form walls of one-piece casting and construction method | |
| CN102561513A (en) | Unit cabin type building system | |
| CN106522406A (en) | Assembly type cast-in-place concrete exterior thermal insulation wall steel skeleton framework system and connecting piece | |
| CN106930431A (en) | A kind of combined type cavity EPS modules | |
| CN108301531A (en) | Assembled built-in heat insulation layer concrete composite wall-light steel frame-floor connecting node | |
| CN107989238A (en) | A kind of cast-in-place sandwiched heat-preservation shear wall structure, assembled architecture and engineering method | |
| CN102433958A (en) | Prefabricated wall board construction member | |
| CN107060104B (en) | A prefabricated steel frame concrete box unit structure system and its construction method | |
| CN201850647U (en) | Modular assembly house | |
| CN103362235B (en) | Integrally-poured building house with wallboards integrating thermal insulating and templates | |
| CN201377121Y (en) | A monolithic poured concrete house | |
| WO2023099942A1 (en) | Walls, blocks and prefabricated double-sided slabs for use in vandad landscape | |
| CN203320695U (en) | Integrated house | |
| CN103074954B (en) | Ceramic brick components and their preparation molds, ceramic brick stone walls and insulation units for ceramic brick components | |
| CN110374241B (en) | Floor bottom module, floor and method for constructing floor | |
| CN203412312U (en) | Thermal-insulating integrated template wallboard construction building | |
| CN201326219Y (en) | Modular building structure | |
| CN210369497U (en) | Floor bottom die block and floor | |
| CN214302529U (en) | Sandwich wallboard with embedded part truss connection | |
| CN107044167A (en) | A kind of assembled steel framework composite lightweight wall building construction | |
| CN108643439A (en) | Extremely frigid zones assembled architecture heat preservation and soundproof hollow filling wall module and construction | |
| CN107775781A (en) | A kind of assembly concrete beam mould | |
| CN102011440B (en) | A thermal insulation building element integrating moldboard, interior wall and outer wall |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20170714 Address after: 528400 No. 2, Guanghui Road, outer sand village, God bay, Zhongshan, Guangdong Patentee after: GUANGDONG LEERJU BUILDING TECHNOLOGY CO.,LTD. Address before: 528000 No. 5 middle Dongxing Road, Guzhen Town, Guangdong, Zhongshan Patentee before: Huang Kun |
|
| TR01 | Transfer of patent right | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20111026 Termination date: 20211011 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |