[go: up one dir, main page]

CN108824601A - A kind of floor drain attachment device and its construction method - Google Patents

A kind of floor drain attachment device and its construction method Download PDF

Info

Publication number
CN108824601A
CN108824601A CN201810798831.6A CN201810798831A CN108824601A CN 108824601 A CN108824601 A CN 108824601A CN 201810798831 A CN201810798831 A CN 201810798831A CN 108824601 A CN108824601 A CN 108824601A
Authority
CN
China
Prior art keywords
floor drain
waterstop joint
floor
drainpipe
ontology
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810798831.6A
Other languages
Chinese (zh)
Inventor
李华磊
高扬
袁坤
史岐山
刘海兰
宫收强
孙凤丽
华瑾
邹燕燕
孙宇航
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG PINGAN CONSTRUCTION GROUP CO Ltd
Original Assignee
SHANDONG PINGAN CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG PINGAN CONSTRUCTION GROUP CO Ltd filed Critical SHANDONG PINGAN CONSTRUCTION GROUP CO Ltd
Priority to CN201810798831.6A priority Critical patent/CN108824601A/en
Publication of CN108824601A publication Critical patent/CN108824601A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/04Gullies inlets, road sinks, floor drains with or without odour seals or sediment traps
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Sink And Installation For Waste Water (AREA)

Abstract

The invention discloses a kind of floor drain attachment device and its construction methods, belong to floor drain construction technical field, including the waterstop joint for being fixed in template and being poured together with template and floor bar frame, waterstop joint passes through floor, the top of waterstop joint is connected to drainpipe, and the top of drainpipe is connect with floor drain ontology;Construction procedure is (1) positioning;(2) waterstop joint is buried;(3) drainpipe is installed;(4) water-proofing treatment;(5) it is laid with ground;(6) floor drain is installed;(7) downpipe is installed;(8) it tests.The present invention can reduce construction cost, shorten the construction period, reduce human input of inspecting for acceptance, and reduce the control difficulty of impression quality and using effect.

Description

A kind of floor drain attachment device and its construction method
Technical field
The present invention relates to floor drain construction technical fields, and in particular to a kind of floor drain attachment device and its construction method.
Background technique
The mounting means of floor drain, the prior art include built-in fitting reserved opening;Reserved opening through cleaning reservation member and dabbing, Floor drain connecting pipe is installed, pipeline wears housing seal ring at top plate.After stringent floor drain absolute altitude calculates, drain to installation Position;Hole to be provided carry out it is secondary pours, it is secondary pour the phase it is forward and backward be both needed to review floor drain absolute altitude, hang it is stifled after check and hang stifled quality And carry out waterproofing step;Later period carries out installation floor drain.
Problem of the existing technology is as follows:
1, construction cost is higher:Because the prior art need in engineering previous structure using it is pre-buried at punch die, it is secondary The material cost height for hanging stifled mold, floor drain body assembly when pouring.
2, the construction period is long:Because need to be arranged in the prior art hole to be provided, cleaning hole to be provided and it is secondary pour, this The waiting time is long between three steps, is the part of consuming time at most in total body construction, and during second pouring Absolute altitude is repeatedly verified, so that prior art floor drain set-up time span is big, the construction period is long.
3, human input of inspecting for acceptance is big:In prior art floor drain construction, each step in construction requires to carry out It inspects for acceptance, this just needs to waste more manpower and goes to complete to check work, increases the human resources of this part.
4, impression quality and using effect are difficult to control:Because in the floor drain construction of the prior art, needing in setting hole to be provided To hanging in this part steps of mould, absolute altitude is repeatedly verified repeatedly, once a level measurement is wrong, will directly affect impression quality; Moreover, floor drain construction step is too many, it will work antiseep and impact if thering is a step to deal with improperly.
Summary of the invention
The present invention In view of the above shortcomings of the prior art, proposes a kind of floor drain attachment device and its construction method, this Invention can reduce construction cost, shorten the construction period, reduce human input of inspecting for acceptance, and reduce impression quality and using effect Control difficulty.
The present invention solve technical problem technical solution be:
A kind of floor drain attachment device, including the sealing for being fixed in template and being poured together with template and floor bar frame Section, waterstop joint pass through floor, and the top of waterstop joint is connected to drainpipe, and the top of drainpipe is connect with floor drain ontology.
Further, the top of the drainpipe is connect by seal gasket with floor drain ontology.
Further, the lower part of the waterstop joint and drop leg.
Further, by sealing glue connection, waterstop joint passes through sealing glue connection with downpipe for the waterstop joint and drainpipe It connects.
Further, the waterstop joint includes the ontology of tubular, and the ontology includes the upper body and lower body of connection, on Ontology is connect by middle ontology with lower body, and middle ontology is inversed taper platform shape, is cased with seal ring, the upper end of seal ring on the outside of upper body Face is equipped with water stopping trough, and boss is cased with outside the bottom of lower body, ribs is equipped with below the conical surface of middle ontology, ribs is equipped with more It is a, and be uniformly distributed along the conical surface of middle ontology.
A kind of construction method of floor drain attachment device, includes the following steps:
(1) it positions:After lifting template, the installation site of waterstop joint is marked in template;
(2) waterstop joint is buried:At the position for marking waterstop joint in template, waterstop joint is fixed in template and binds building Template, waterstop joint and floor bar frame are poured into together after the binding of floor bar frame with concrete by plate steel bar framework, Form reinforced concrete floor;
(3) drainpipe is installed:After waterstop joint top is cleaned out, drainpipe is connect with waterstop joint top;
(4) water-proofing treatment:It is laid with waterproof layer above reinforced concrete floor, then carry out waterproof test and closes water examination It tests;
(5) it is laid with ground:Floor leveling is carried out, ground is laid with;
(6) floor drain is installed:The height of drainpipe is cut to the height of code requirement, seal gasket is placed on floor drain ontology Outside, and the floor drain ontology for being cased with seal gasket is placed in drainpipe;
(7) downpipe is installed:After having cleared up waterstop joint lower part, the lower part of downpipe and waterstop joint is connected;
(8) it tests:Carry out closed-water test.
Further, it is intended to be checked after the step (1), (3), (6) and (7).
The device have the advantages that:
1, by the way that the waterstop joint for being fixed in template and pouring together with template and floor bar frame, and sealing is arranged Section can reduce prior art floor drain construction step across floor, and specific the step of reducing has:Hole to be provided is set;Using pre-buried At punch die hole to be provided, and pour for the first time, checks hole to be provided;Clear up hole to be provided;Remove pre-buried at punch die, cleaning is pre- The dabbing of box out checks that hole to be provided clears up situation;Floor drain connecting pipe is installed:After verifying floor drain absolute altitude, installed at hole to be provided Floor drain connecting pipe, housing seal ring at floor drain connecting pipe through-flooring, and check;It hangs stifled:Using stifled mold is hung, concrete is used Second pouring is carried out, checks floor drain absolute altitude, and check and hang stifled quality;It is levelling:Stifled mold is hung in dismounting, and reserved opening progress is levelling simultaneously It checks.This part prior art floor drain construction step is reduced, has been had the advantage that:First, save construction cost:Because being not necessarily to Using prior art floor drain construction using it is pre-buried at punch die, it is secondary pour when hang stifled mold, reduce and use floor drain ontology The material of component;Second, shorten the construction period:Because being not necessarily to the setting hole to be provided for carrying out prior art floor drain construction, cleaning in advance Box out and it is secondary pour these three steps, and the waiting time is long between these three steps, is to expend the time in total body construction Part at most, furthermore multiple verification absolute altitude during second pouring, so that prior art floor drain set-up time span is big, Construction period is long;Third reduces manpower of inspecting for acceptance:Because reducing prior art floor drain construction step, without carrying out Inspecting for acceptance in this part steps also just goes to complete to check work, reduces this part without wasting more manpower The waste of human resources;4th, reduce the control difficulty of impression quality and using effect:Because reducing prior art floor drain to apply Work step is rapid, so without, to hanging in this part steps of mould, repeatedly verifying absolute altitude repeatedly in setting hole to be provided, also just reducing measurement The risk of fault so can be improved impression quality, while also reducing the risk dealt with improperly in construction procedure, and reducing makes With the control difficulty of effect.
It is connected to by the top in waterstop joint with drainpipe, is able to extend the upper height of waterstop joint, avoids subsequent When the engineerings such as waterproof construction, cushion construction and resident's paving ceramic tile, because the upper height of waterstop joint fixes, after being above-mentioned Continuous engineering brings puzzlement, or even the problem of can not be constructed;It is connected to by the top in waterstop joint with drainpipe, to extend only The upper height of water section reserves size for successive projects, avoids that high expense is spent to extend stopping for upper height to customize Water section reserves the waterstop joint of size for successive projects in this regard, inventor knows through inquiry, is only opened an expense cost nearly 100,000 Member, price is very high, so the behave being connected to by the top in waterstop joint with drainpipe, has saved great number cost.
2, by allowing the top of drainpipe to connect by seal gasket with floor drain ontology, can not only realize floor drain ontology and The connection of drainpipe;And cost has been saved, because the specification of common floor drain ontology and the specification of drainpipe are not on the market Match, need to spend high die sinking expense, comes custom-made drainpipe or floor drain ontology, and by making the top of drainpipe logical It crosses seal gasket to connect with floor drain ontology, saves the cost of customization drainpipe or floor drain ontology;In addition, seal gasket is with close The effect of envelope, avoid between floor drain ontology and drainpipe there is a situation where reveal or blocking;Furthermore connected by seal gasket Ground connection leakage and the continuous pipe fitting in top, have universal adaptability, can promote to use.
3, by allow waterstop joint lower part and drop leg, the sewage of waterstop joint can be flowed through below waterstop joint Downpipe outflow, into subsequent pipeline, downpipe plays the role of linking.
4, because allowing waterstop joint and drainpipe by sealing glue connection, waterstop joint and downpipe also by sealing glue connection, So can not only realize the connection of waterstop joint and drainpipe, the connection of waterstop joint and downpipe, and have Packed effect, Connection type is simple, easy to operate, while sealant is generally sold in the market, facilitates the selection of construction personnel, reduces cost, It is suitble to large-scale use.
5, by allowing upper body to connect by middle ontology with lower body, and middle ontology is inversed taper platform shape, can be in sewage When flowing through lower body from upper body, make the buffering from the sewage of upper body vertical drop by the conical surface of middle ontology, sewage passes through Enter back into what lower body, impact of the reduction to lower body, and then reduction were connect with lower body lower end after the buffering of middle body cone The impact of downpipe extends the service life of entire waterstop joint, saves later maintenance cost.By being cased with only on the outside of upper body Water ring, seal ring upper surface are equipped with water stopping trough, are cased with boss outside the bottom of lower body, on the one hand, convenient for embedded waterstop joint, because Boss increases the area of lower body bottom end, so on the other hand can stablize waterstop joint by boss can be arranged boss The contact area of floorslab concrete and waterstop joint is increased, the bond strength of waterstop joint and floorslab concrete is improved.By in Multiple ribs are evenly distributed with below the conical surface of ontology, the impact force of water suffered by middle ontology is on the one hand can reduce, mentions The stress-bearing capability of senior middle school's ontology extends the service life of waterstop joint, reduces the cost of follow-up maintenance, on the other hand, because of sealing Section is embedded in floor, and multiple ribs are arranged, moreover it is possible to increase the contact area of waterstop joint and floorslab concrete, to mention High waterstop joint and floorslab concrete are firmly combined intensity.
6, by constructing according to a kind of construction method of floor drain attachment device, can standard construction step, reduction applies Work fault, improves floor drain installation quality.Specifically, step (1) positions, can be pre-positioned in the position for needing to be laid with floor drain, Build floor is poured convenient for subsequent;Step (2) buries waterstop joint, can reduce prior art floor drain construction step, the step for it is specific Advantage is described in detail in beneficial effect 1, and details are not described herein, and the effect that furthermore this step also has is spread for subsequent step Pad;Step (3) installs drainpipe, is able to extend the upper height of waterstop joint, reserves size for successive projects;Step (4) waterproof Processing can prevent from revealing and preventing damage floor;Step (5) ground construction can lay ground convenient for user;Step (6) Floor drain is installed, it being capable of odor-proof, anti-clogging, cockroach proof, anti-virus, anti-effect returning water.
7, by being checked after the step (1), (3), (6) and (7), it can be improved integral construction quality, into One step improves aesthetic quality and using effect.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram of floor drain attachment device;
Fig. 2 is a kind of partial cutaway schematic of floor drain attachment device;
Fig. 3 is the main view of waterstop joint;
Fig. 4 is the schematic perspective view of waterstop joint.
Description of symbols:1- waterstop joint, 101- upper body, 102- seal ring, 103- water stopping trough, 104- ribs, 105- boss, 106- lower body, ontology in 107-, 2- drainpipe, 3- seal gasket, 4- floor drain ontology, 5- downpipe, 6- blowdown Pipeline, 7- reinforced concrete floor, 8- pea gravel concreten bed course, 9- waterproof layer, 10- pea gravel concreten protective layer, 11- cement are husky Starch levelling sloping layer, 12- ship-and-galley tile.
It is worth noting that, in the description of the present invention, term " center ", "upper", "lower", "left", "right", "vertical", The orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" be based on the orientation or positional relationship shown in the drawings, merely to Convenient for description the present invention and simplify description, rather than the device or element of indication or suggestion meaning must have a particular orientation, It is constructed and operated in a specific orientation, therefore is not considered as limiting the invention.
Specific embodiment
For a better understanding of the present invention, the present invention will be further elaborated with reference to the accompanying drawing.
Embodiment 1:
Floor drain is installed in the prior art, is included the following steps:
(1) it positions:After lifting template, the installation site of floor drain is marked in template, and checks whether positioning is accurate;
(2) hole to be provided:The position that floor drain is marked in template, nails in template pre-buried at punch die, together When bind floor bar frame, reinforcing bar binding after, with concrete by template, it is pre-buried be poured into together at punch die and reinforcing bar, shape At reinforced concrete floor 7, hole to be provided is checked;
(3) hole to be provided is cleared up:After the molding of reinforced concrete floor 7, removes pre-buried at punch die, clear up hole to be provided Dabbing checks that hole to be provided clears up situation;
(4) floor drain connecting pipe is installed:After verifying floor drain absolute altitude, floor drain connecting pipe is installed at hole to be provided, floor drain connects Housing seal ring at adapter tube road through-flooring, and check;
(5) it hangs stifled:Using stifled mold is hung, second pouring is carried out with concrete, checks floor drain absolute altitude, and check and hang stifled matter Amount;
(6) levelling:Stifled mold is hung in dismounting, and reserved opening is carried out levelling and checked;
(7) water-proofing treatment:Pea gravel concreten bed course 8 is laid on reinforced concrete floor 7, in pea gravel concreten bed course 8 Top is laid with waterproof layer 9, then carries out waterproof test and closed-water test;
(8) it is laid with ground:After waterproof test and closed-water test pass through, pea gravel concreten guarantor is successively laid on waterproof layer 9 Sheath 10 is laid with the levelling sloping layer 11 of cement mortar, in the levelling sloping layer 11 of cement mortar on pea gravel concreten protective layer 10 Upper berth sets ship-and-galley tile 12;
(9) floor drain is installed:Floor drain ontology 4 and floor drain body housing are installed on the top of floor drain connecting pipe, and check ground Leak installation situation;
(10) downpipe is installed:After having cleared up floor drain connecting pipe lower part, downpipe 5 is accessed into floor drain connecting pipe In lower part, downpipe 5 and floor drain connecting pipe are adhesively fixed with sealant, and check fixing situation.After errorless on inspection, The lower part of downpipe 5 is installed by blow-off line 6.
(11) it tests:Carry out closed-water test.
Embodiment 2:
A kind of floor drain attachment device, as depicted in figs. 1 and 2, including be fixed in template and with template and floor bar frame The waterstop joint 1 that frame pours together, waterstop joint 1 pass through floor, and the top of waterstop joint 1 is connected to drainpipe 2, the top of drainpipe 2 It is connect with floor drain ontology 4.Floor is to be lifted in engineering according to design drawing, and floor is used for locating water-stopping section 1.
Further, the top of the drainpipe 2 is connect by seal gasket 3 with floor drain ontology 4, specifically, sealant Pad 3 is ring-shaped rubber pad.
Further, the lower part of the waterstop joint 1 is connected to downpipe 5.
Further, for the waterstop joint 1 with drainpipe 2 by sealing glue connection, waterstop joint 1 and downpipe 5 pass through sealing Glue connection.
Further, as shown in Figure 3 and Figure 4, the waterstop joint 1 includes the ontology of tubular, and the ontology includes connection Upper body 101 and lower body 106, upper body 101 are connect by middle ontology 107 with lower body 106, and middle ontology 107 is inversed taper platform Shape, is cased with seal ring 102 on the outside of upper body 101, and 102 upper surface of seal ring is equipped with water stopping trough 103, outside the bottom of lower body 106 Be cased with round ring boss, be equipped with ribs 104 below the conical surface of middle ontology 107, ribs 104 be equipped with it is multiple, and along middle ontology 107 conical surface is uniformly distributed.Specifically, upper body 101, middle ontology 107 and lower body 106 and drainpipe 2 and downpipe 5 are all On same axis, the upper end of ribs 104 is connect with middle ontology 107, outside the side of ribs 104 and lower body 106 Connection, the lower end of ribs 104 is connect with 105 top of boss.
A kind of floor drain attachment device construction method, includes the following steps:
(1) it positions:Template is lifted according to drawing of engineering design, after lifting template, the peace of waterstop joint 1 is marked in template Holding position, and check whether positioning is accurate, after determining that waterstop joint accurate positioning is errorless, carry out step (2);
(2) waterstop joint is buried:The position that waterstop joint 1 is marked in template, nails DN100*50 waterstop joint 1 In template, while floor bar frame is bound, after the binding of floor bar frame, with concrete by template, waterstop joint and floor steel Muscle frame is poured into together, forms reinforced concrete floor 7;
(3) drainpipe is installed:After the molding of reinforced concrete floor 7, and after 1 top of waterstop joint is cleaned out, DN100 drainpipe 2 connects on 1 top of waterstop joint, and DN100 drainpipe 2 and waterstop joint 1 are adhesively fixed with sealant, and checks solid Pledge love condition, check it is errorless after carry out step (4);
(4) water-proofing treatment:After installing drainpipe 2, pea gravel concreten bed course 8 is laid on reinforced concrete floor 7, It is laid with waterproof layer 9 above pea gravel concreten bed course 8, then carries out waterproof test and closed-water test;
(5) it is laid with ground:After waterproof test and closed-water test pass through, pea gravel concreten guarantor is successively laid on waterproof layer 9 Sheath 10 is laid with the levelling sloping layer 11 of cement mortar, in the levelling sloping layer 11 of cement mortar on pea gravel concreten protective layer 10 Upper berth sets ship-and-galley tile 12;
(6) floor drain is installed:The height of drainpipe 2 is cut to the height of code requirement, seal gasket 3 is placed on floor drain sheet The outside of body 4, and the floor drain ontology 4 for being cased with seal gasket 3 is placed in drainpipe 2, and check floor drain installation situation, floor drain Errorless rear progress step (7) is installed;
(7) downpipe 5 is installed:After having cleared up 1 lower part of waterstop joint, DN50 downpipe 5 is accessed to the lower part of waterstop joint 1 It is interior, downpipe 5 and waterstop joint 1 are adhesively fixed with sealant, and check fixing situation.Check it is errorless after, under downpipe 5 Blow-off line 6 after portion's installation.
(8) it tests:Carry out closed-water test.
Specifically, DN100*50 waterstop joint 1 refers to that the nominal diameter of the upper body 101 of waterstop joint 1 is 100 millimeters, lower The nominal diameter of body 106 is 50 millimeters, and DN100 drainpipe 2 is the drainpipe 2 that nominal diameter is 100 millimeters, DN50 downpipe 5 The downpipe 5 for being 50 millimeters for nominal diameter.
Embodiment 3:
The comparative situation of embodiment 1 and embodiment 2 in terms of process, time, cost, perception and using effect such as table 1:
The contrast table of table 1 embodiment 1 and embodiment 2
According to upper table, make a concrete analysis of as follows:
First, the time saves aspect:
Embodiment 2 has saved the setting hole to be provided of embodiment 1, cleaning hole to be provided, installation floor drain connecting pipe, has hung stifled and look for Put down the time of this five steps.When implementing this five steps in embodiment 1, consuming is of long duration, extends the duration.Through counting, Embodiment 2 saves total construction period about 5 days than embodiment 1.
Second, cost savings aspect:
The cost of embodiment 1 is as shown in table 2,
The cost situation table of 2 embodiment 1 of table
Serial number Process Cost
1 Hole to be provided reserves, it is stifled to hang 30 yuan/place
2 Floor drain ontology, floor drain body housing 28 yuan/
It is total 58 yuan/place
The cost of embodiment 2 is as shown in table 3,
The cost situation table of 3 embodiment 2 of table
Serial number Process Cost
1 Waterstop joint 1 is installed 5 yuan/
2 Seal gasket 3 0.6 yuan/
3 Floor drain ontology 4 20 yuan/set
4 Drainpipe 2 2 yuan/section
It is total 27.6 yuan/place
Drainpipe 2 in embodiment 2 is made using pipeline trash, not only save the cost, but also recycles pipeline trash, It realizes being used for multiple times for resource, economizes on resources.Floor drain construction at total statement of account, embodiment 2 save 58-27.6=than embodiment 1 30.4 yuan/place, nearly 1.7 ten thousand yuan of every building save the cost.In engineering, simulation is calculated, according to the construction method ratio in embodiment 2 13.6 ten thousand yuan of 1 save the cost of embodiment.
Third, personnel save aspect:
Through rough Statistics, the use of Novel drain form of construction work is saved while hang stifled time, water-proofing time, is saved The relevant workload for checking inspection personnel.
4th, in terms of perception and using effect:
Comparative example 1, embodiment 2 reduce step (2)-(6) in embodiment 1, it is not necessary to repeatedly absolute altitude is verified repeatedly, Reduce the number for verifying absolute altitude, and then reduce the risk of measurement fault, so can be improved impression quality;
And the step of embodiment 2 than embodiment 1 the step of it is few, the risk of construction wrong is decreased, by full building Closed-water test test, the qualification rate using 2 construction method of embodiment reach 100%, comply fully with the requirement of antiseep.

Claims (7)

1. a kind of floor drain attachment device, which is characterized in that including being fixed in template and together with template and floor bar frame The waterstop joint poured, waterstop joint pass through floor, and the top of waterstop joint is connected to drainpipe, and the top of drainpipe and floor drain ontology connect It connects.
2. a kind of floor drain attachment device according to claim 1, which is characterized in that the top of the drainpipe passes through sealing Rubber mat is connect with floor drain ontology.
3. a kind of floor drain attachment device according to claim 1, which is characterized in that the lower part of the waterstop joint and downpipe Connection.
4. a kind of floor drain attachment device according to claim 3, which is characterized in that the waterstop joint passes through close with drainpipe Sealing connection, waterstop joint and downpipe pass through sealing glue connection.
5. a kind of floor drain attachment device according to claim 1, which is characterized in that the waterstop joint includes the sheet of tubular Body, ontology include the upper body and lower body of connection, and upper body is connect by middle ontology with lower body, and middle ontology is inversed taper platform Shape is cased with seal ring on the outside of upper body, and the upper surface of seal ring is equipped with water stopping trough, is cased with boss outside the bottom of lower body, and middle It is equipped with ribs below the conical surface of body, ribs is equipped with multiple, and is uniformly distributed along the conical surface of middle ontology.
6. a kind of construction method of floor drain attachment device, which is characterized in that include the following steps:
(1) it positions:After lifting template, the installation site of waterstop joint is marked in template;
(2) waterstop joint is buried:At the position for marking waterstop joint in template, waterstop joint is fixed in template and binds floor steel Template, waterstop joint and floor bar frame are poured into together with concrete, form reinforced concrete floor by muscle frame;
(3) drainpipe is installed:After waterstop joint top is cleaned out, drainpipe is connect with waterstop joint top;
(4) water-proofing treatment:It is laid with waterproof layer above reinforced concrete floor, carries out waterproof test and closed-water test;
(5) it is laid with ground:Floor leveling is carried out, ground is laid with;
(6) floor drain is installed:The height of drainpipe is cut to the height of code requirement, seal gasket is placed on the outer of floor drain ontology Portion, and the floor drain ontology for being cased with seal gasket is placed in drainpipe;
(7) downpipe is installed:After having cleared up waterstop joint lower part, the lower part of downpipe and waterstop joint is connected;
(8) it tests:Carry out closed-water test.
7. a kind of construction method of floor drain attachment device according to claim 6, which is characterized in that the step (1), (3), it is intended to be checked after (6) and (7).
CN201810798831.6A 2018-07-19 2018-07-19 A kind of floor drain attachment device and its construction method Pending CN108824601A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810798831.6A CN108824601A (en) 2018-07-19 2018-07-19 A kind of floor drain attachment device and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810798831.6A CN108824601A (en) 2018-07-19 2018-07-19 A kind of floor drain attachment device and its construction method

Publications (1)

Publication Number Publication Date
CN108824601A true CN108824601A (en) 2018-11-16

Family

ID=64140945

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810798831.6A Pending CN108824601A (en) 2018-07-19 2018-07-19 A kind of floor drain attachment device and its construction method

Country Status (1)

Country Link
CN (1) CN108824601A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236394A (en) * 2020-01-06 2020-06-05 三箭建设工程集团有限公司 Floor drain construction connecting piece and construction method thereof
CN114197866A (en) * 2021-12-16 2022-03-18 中铁建设集团华东工程有限公司 Construction method for reserved hole of drainage vertical pipe
CN117090289A (en) * 2023-09-28 2023-11-21 宁波世诺卫浴有限公司 Floor drain with vertical wing ring

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2863923Y (en) * 2006-03-31 2007-01-31 陈伟明 Waterproof leakage connector
CN101666110A (en) * 2009-09-25 2010-03-10 陈伟明 Waterproof leak receiver
CN102095033A (en) * 2010-12-15 2011-06-15 成都市第四建筑工程公司 One-time embedded water-stop section for construction engineering drainage and construction method thereof
CN102261123A (en) * 2011-05-27 2011-11-30 北京市日盛达建筑企业集团 Novel anti-seepage floor drain system and construction method thereof
CN202073170U (en) * 2011-05-27 2011-12-14 北京市朝阳城市建设综合开发公司 Convenient-to-replace floor drain system
CN202530518U (en) * 2012-04-24 2012-11-14 中天建设集团有限公司 Embedded device at sewer line in toilet
CN205134502U (en) * 2015-11-30 2016-04-06 陈敏 Adjustable pre -buried floor drain
CN105650357A (en) * 2016-03-25 2016-06-08 陆荣臻 Disposable embedded water stop joint for constructional engineering drainage and construction method thereof
CN207092237U (en) * 2017-07-21 2018-03-13 深圳市永高塑业发展有限公司 Pre-buried deodorization washing machine floor drain
DE202017100626U1 (en) * 2017-02-07 2018-05-08 Wiedemann Gmbh System consisting of an odor trap and a receiving body as well as an odor trap

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2863923Y (en) * 2006-03-31 2007-01-31 陈伟明 Waterproof leakage connector
CN101666110A (en) * 2009-09-25 2010-03-10 陈伟明 Waterproof leak receiver
CN102095033A (en) * 2010-12-15 2011-06-15 成都市第四建筑工程公司 One-time embedded water-stop section for construction engineering drainage and construction method thereof
CN102261123A (en) * 2011-05-27 2011-11-30 北京市日盛达建筑企业集团 Novel anti-seepage floor drain system and construction method thereof
CN202073170U (en) * 2011-05-27 2011-12-14 北京市朝阳城市建设综合开发公司 Convenient-to-replace floor drain system
CN202530518U (en) * 2012-04-24 2012-11-14 中天建设集团有限公司 Embedded device at sewer line in toilet
CN205134502U (en) * 2015-11-30 2016-04-06 陈敏 Adjustable pre -buried floor drain
CN105650357A (en) * 2016-03-25 2016-06-08 陆荣臻 Disposable embedded water stop joint for constructional engineering drainage and construction method thereof
DE202017100626U1 (en) * 2017-02-07 2018-05-08 Wiedemann Gmbh System consisting of an odor trap and a receiving body as well as an odor trap
CN207092237U (en) * 2017-07-21 2018-03-13 深圳市永高塑业发展有限公司 Pre-buried deodorization washing machine floor drain

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236394A (en) * 2020-01-06 2020-06-05 三箭建设工程集团有限公司 Floor drain construction connecting piece and construction method thereof
CN114197866A (en) * 2021-12-16 2022-03-18 中铁建设集团华东工程有限公司 Construction method for reserved hole of drainage vertical pipe
CN117090289A (en) * 2023-09-28 2023-11-21 宁波世诺卫浴有限公司 Floor drain with vertical wing ring

Similar Documents

Publication Publication Date Title
CN106013471B (en) A kind of construction method of expansion joint antiseep
CN108824601A (en) A kind of floor drain attachment device and its construction method
CN111456088A (en) Superimposed assembly structure subway station and assembly construction method
CN107476812A (en) A kind of assembled inverted arch and preparation method thereof
CN108301466B (en) Integral prefabricated bathroom caisson, bathroom caisson structure and construction method thereof
CN206625428U (en) Pipe shaft post-cast floor slab closed system
CN106759474A (en) Construction method of flexible socket common pipe trench
CN106958313A (en) Pipe well post-cast floor slab closed system and construction method thereof
CN110985052A (en) Self-compacting concrete pouring construction process method
CN207469307U (en) A kind of gang form structure of the inspection shaft cast-in-place construction of town road pipeline
CN103835421B (en) Leakage-proof floor and anti-seepage construction method
CN209323688U (en) Prefabricated reinforced concrete column splicing joint structure
CN207499880U (en) A kind of assembled inverted arch
CN203113788U (en) Adjustable reserved sleeve capable of penetrating floorslab
CN112504840A (en) Assembled type building sleeve grouting quality detection device and construction method thereof
CN217580245U (en) Foundation ditch drainage system for construction
CN211646670U (en) Floor drain waterproof structure
CN207268010U (en) Drainpipe leakage-resistant device
CN110700297A (en) A kind of sump stereotyped combined steel formwork and installation method thereof
CN211118029U (en) Structure suitable for embedded sleeve behind existing pool wall
CN104455757A (en) Downcomer assembly and installation method thereof
CN210003941U (en) Detachable anti-seepage sleeve assembly
CN215635439U (en) Drain pipe pre-embedding device with telescopic and waterproof functions
CN208074294U (en) Side-type direct-burried part
CN112982623A (en) Assembly type construction method for drainage pipeline of high-rise building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181116

RJ01 Rejection of invention patent application after publication