CN108817271A CN201810461268.3A CN201810461268A CN108817271A CN 108817271 A CN108817271 A CN 108817271A CN 201810461268 A CN201810461268 A CN 201810461268A CN 108817271 A CN108817271 A CN 108817271A
Authority
CN
China
Prior art keywords
cable wire
wire
steel
tempering
tension
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810461268.3A
Other languages
Chinese (zh)
Inventor
廖东帆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Mainuo Industrial Technology Co Ltd
Original Assignee
Guangdong Mainuo Industrial Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Mainuo Industrial Technology Co Ltd filed Critical Guangdong Mainuo Industrial Technology Co Ltd
Priority to CN201810461268.3A priority Critical patent/CN108817271A/en
Publication of CN108817271A publication Critical patent/CN108817271A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21FWORKING OR PROCESSING OF METAL WIRE
    • B21F7/00Twisting wire; Twisting wire together
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21CMANUFACTURE OF METAL SHEETS, WIRE, RODS, TUBES, PROFILES OR LIKE SEMI-MANUFACTURED PRODUCTS OTHERWISE THAN BY ROLLING; AUXILIARY OPERATIONS USED IN CONNECTION WITH METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL
    • B21C37/00Manufacture of metal sheets, rods, wire, tubes, profiles or like semi-manufactured products, not otherwise provided for; Manufacture of tubes of special shape
    • B21C37/04Manufacture of metal sheets, rods, wire, tubes, profiles or like semi-manufactured products, not otherwise provided for; Manufacture of tubes of special shape of rods or wire
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21FWORKING OR PROCESSING OF METAL WIRE
    • B21F99/00Subject matter not provided for in other groups of this subclass
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D1/00General methods or devices for heat treatment, e.g. annealing, hardening, quenching or tempering
    • C21D1/18Hardening; Quenching with or without subsequent tempering
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D8/00Modifying the physical properties by deformation combined with, or followed by, heat treatment
    • C21D8/06Modifying the physical properties by deformation combined with, or followed by, heat treatment during manufacturing of rods or wires
    • C21D8/065Modifying the physical properties by deformation combined with, or followed by, heat treatment during manufacturing of rods or wires of ferrous alloys
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D9/00Heat treatment, e.g. annealing, hardening, quenching or tempering, adapted for particular articles; Furnaces therefor
    • C21D9/52Heat treatment, e.g. annealing, hardening, quenching or tempering, adapted for particular articles; Furnaces therefor for wires; for strips ; for rods of unlimited length
    • C21D9/525Heat treatment, e.g. annealing, hardening, quenching or tempering, adapted for particular articles; Furnaces therefor for wires; for strips ; for rods of unlimited length for wire, for rods

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Crystallography & Structural Chemistry (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Manufacturing & Machinery (AREA)
  • Ropes Or Cables (AREA)

Abstract

The invention discloses a kind of preparation methods of closed cable wire of high intensity, include the following steps:Pretreatment;High-tensile steel wires drawing;Tempering;Steel spool, the large-scale stranding machine of feeding on steel wire coil;Before steel wire twines into one, toward steel wire on pour leaching lubricant;The steel wire for twining into one imports punch die, forms cable wire;Cable wire passes through a succession of straightener, the pressure at right angle applied by straightener;Cable wire carries out 2 pre- tensioning;Stabilization processes are tempered, under the tension for granting cable wire 40%-50% minimum breaking load, carry out 360-375 DEG C of tempering;To cable wire coating.It is an advantage of the invention that:2 pre- tensioning processing extend steel cable structure effectively, and cable wire stress can be reduced by improving steel cable structure high intensity and stability, tempering, help improve wirerope intensity.

Description

A kind of preparation method of the closed cable wire of high intensity
Technical field
The present invention relates to a kind of manufacturing technology fields of closed cable wire of high intensity.
Background technique
Cable wire is referred to as with parallel wire unit, steel strand wires or the wirerope that high tensile steel wire forms.Cable wire is in building structure work The industry fields such as journey, mechanical lifting, elevator play an important role.Previous cable wire needs more steel wire to twist to reach high-intensitive System, leads to cable wire preponderance itself, causes construction weight load.Therefore, it produces a kind of closed cable wire of high intensity and weight is negative The small cable wire of lotus is market trend.
Summary of the invention
The purpose of the present invention is to provide a kind of preparation methods of closed cable wire of high intensity.
The present invention adopts the following technical scheme that in order to achieve the above object:
A kind of preparation method of the closed cable wire of high intensity, includes the following steps:
(1) pretreatment;
(2) high-tensile steel wires drawing;
(3) tempering;
(4) steel spool, the large-scale stranding machine of feeding on steel wire coil;
(5) before steel wire twines into one, toward steel wire on pour leaching lubricant;
(6) steel wire for twining into one imports punch die, forms cable wire;
(7) cable wire passes through a succession of straightener, by the pressure at right angle that straightener applies, effectively eliminates steel wire before winding By the memory of volume upper bobbin, prevent steel wire from scattering;
(8) cable wire carries out 2 pre- tensioning, and pre- tensioning for the first time is cable wire minimum breaking force to the tension that cable wire applies 40-50% keeps 50-60min, then relaxes 10-15 minutes, and second of pre- tensioning applies tension to cable wire and breaks for cable wire minimum The 30-45% of disconnected tension, keeps 80-100min, then gradually relaxes;
(9) stabilization processes are tempered, under the tension for granting cable wire 40%-50% minimum breaking load, carry out 360-375 DEG C Tempering;
(10) to cable wire coating.
Further, the pretreatment of the step (1) includes pickling, phosphatization.
Further, the concrete operations of the step (3) are:Steel wire is carried out simultaneously to apply tension and tempering, Power is the 25-30% of its rupture pull force, and tempering temperature is 360-375 DEG C.
Further, step (3) tempering is divided into 2 stages, and the first stage is 360-370 DEG C, second stage It is 370-375 DEG C.
The advantage of the invention is that:2 pre- tensioning processing extends steel cable structure effectively, improve steel cable structure high intensity and Stability, tempering can reduce cable wire stress, help improve wirerope intensity.
Specific embodiment
Below in conjunction with specific embodiment, the present invention will be described in detail, herein with illustrative examples and explanation of the invention For explaining the present invention, but it is not as a limitation of the invention.
Embodiment one
A kind of preparation method of the closed cable wire of high intensity, includes the following steps:
(1) pretreatment:Pickling, phosphatization;
(2) high-tensile steel wires drawing;
(3) tempering simultaneously carries out steel wire applying tension and tempering, and tension is the 25- of its rupture pull force 30%, tempering is divided into 2 stages, and the first stage is 360 DEG C, and second stage is 375 DEG C;
(4) steel spool, the large-scale stranding machine of feeding on steel wire coil;
(5) before steel wire twines into one, toward steel wire on pour leaching lubricant;
(6) steel wire for twining into one imports punch die, forms cable wire;
(7) cable wire passes through a succession of straightener, by the pressure at right angle that straightener applies, effectively eliminates steel wire before winding By the memory of volume upper bobbin, prevent steel wire from scattering;
(8) cable wire carries out 2 pre- tensioning, and pre- tensioning for the first time is cable wire minimum breaking force to the tension that cable wire applies Then 40%, holding 50min relax 15 minutes, it is cable wire minimum fracture tension that second of pre- tensioning, which applies tension to cable wire, 30%, 100min is kept, is then gradually relaxed;
(9) stabilization processes are tempered, under the tension for granting cable wire 40%-50% minimum breaking load, carry out 360 DEG C of tempering Processing;
(10) to cable wire coating.
Embodiment two
A kind of preparation method of the closed cable wire of high intensity, includes the following steps:
(1) pretreatment:Pickling, phosphatization;
(2) high-tensile steel wires drawing,;
(3) tempering simultaneously carries out steel wire applying tension and tempering, and tension is the 30% of its rupture pull force, Tempering temperature is divided into 2 stages, and the first stage is 360 DEG C, and second stage is 375 DEG C;
(4) steel spool, the large-scale stranding machine of feeding on steel wire coil;
(5) before steel wire twines into one, toward steel wire on pour leaching lubricant;
(6) steel wire for twining into one imports punch die, forms cable wire;
(7) cable wire passes through a succession of straightener, by the pressure at right angle that straightener applies, effectively eliminates steel wire before winding By the memory of volume upper bobbin, prevent steel wire from scattering;
(8) cable wire carries out 2 pre- tensioning, and pre- tensioning for the first time is cable wire minimum breaking force to the tension that cable wire applies Then 40%, holding 50min relax 10 minutes, it is cable wire minimum fracture tension that second of pre- tensioning, which applies tension to cable wire, 30%, 80min is kept, is then gradually relaxed;
(9) stabilization processes are tempered, under the tension for granting the minimum breaking load of cable wire 50%, carry out 375 DEG C of temperings;
(10) to cable wire coating.
It is provided for the embodiments of the invention technical solution above to be described in detail, specific case used herein The principle and embodiment of the embodiment of the present invention are expounded, the explanation of above embodiments is only applicable to help to understand this The principle of inventive embodiments;At the same time, for those skilled in the art, according to an embodiment of the present invention, in specific embodiment party There will be changes in formula and application range, in conclusion the contents of this specification are not to be construed as limiting the invention.

Claims (4)

1. a kind of preparation method of the closed cable wire of high intensity, it is characterised in that:
Include the following steps:
(1) pretreatment;
(2) high-tensile steel wires drawing;
(3) tempering;
(4) steel spool, the large-scale stranding machine of feeding on steel wire coil;
(5) before steel wire twines into one, toward steel wire on pour leaching lubricant;
(6) steel wire for twining into one imports punch die, forms cable wire;
(7) cable wire passes through a succession of straightener, by the pressure at right angle that straightener applies, effectively eliminates steel wire and is rolled up before winding The memory of upper bobbin, prevents steel wire from scattering;
(8) cable wire carries out 2 pre- tensioning, the tension that pre- tensioning for the first time applies to cable wire for cable wire minimum breaking force 40- 50%, 50-60min is kept, is then relaxed 10-15 minutes, second of pre- tensioning applies tension to cable wire as the fracture of cable wire minimum The 30-45% of tension keeps 80-100min, then gradually relaxes;
(9) stabilization processes are tempered, under the tension for granting cable wire 40%-50% minimum breaking load, carry out 360-375 DEG C of tempering Processing;
(10) to cable wire coating.
2. a kind of preparation method of closed cable wire of high intensity according to claim 1, it is characterised in that:
The pretreatment of the step (1) includes pickling, phosphatization.
3. a kind of preparation method of closed cable wire of high intensity according to claim 2, it is characterised in that:
The concrete operations of the step (3) are:Steel wire is carried out simultaneously to apply tension and tempering, tension is its rupture pull force 25-30%, tempering temperature is 360-375 DEG C.
4. a kind of preparation method of closed cable wire of high intensity according to claim 3, it is characterised in that:
Step (3) tempering is divided into 2 stages, and the first stage is 360-370 DEG C, and second stage is 370-375 DEG C.
CN201810461268.3A 2018-05-14 2018-05-14 A kind of preparation method of the closed cable wire of high intensity Pending CN108817271A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810461268.3A CN108817271A (en) 2018-05-14 2018-05-14 A kind of preparation method of the closed cable wire of high intensity

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810461268.3A CN108817271A (en) 2018-05-14 2018-05-14 A kind of preparation method of the closed cable wire of high intensity

Publications (1)

Publication Number Publication Date
CN108817271A true CN108817271A (en) 2018-11-16

Family

ID=64148750

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810461268.3A Pending CN108817271A (en) 2018-05-14 2018-05-14 A kind of preparation method of the closed cable wire of high intensity

Country Status (1)

Country Link
CN (1) CN108817271A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109930407A (en) * 2019-04-17 2019-06-25 安徽省力通稀土钢缆有限公司 A kind of production technology of corrosion prevention oiling PC steel strand wires

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20020005036A1 (en) * 2000-05-30 2002-01-17 Young-Jo Kim Wire cable for window regulators of auto mobiles
CN101676489A (en) * 2008-09-17 2010-03-24 贵州钢绳股份有限公司 Stainless steel wire rope serial production line equipment specially used for space flight and technique thereof
CN103485220B (en) * 2013-10-15 2015-09-30 贵州钢绳股份有限公司 A kind of manufacture method of high-strength wire rope for traction structure
CN106012623A (en) * 2016-07-29 2016-10-12 贵州钢绳股份有限公司 Multilayer stand steel wire manufacturing method
CN106498787A (en) * 2016-12-08 2017-03-15 贵州钢绳股份有限公司 35W × 7 structure high intensity major diameter producing technique of steel cable

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20020005036A1 (en) * 2000-05-30 2002-01-17 Young-Jo Kim Wire cable for window regulators of auto mobiles
CN101676489A (en) * 2008-09-17 2010-03-24 贵州钢绳股份有限公司 Stainless steel wire rope serial production line equipment specially used for space flight and technique thereof
CN103485220B (en) * 2013-10-15 2015-09-30 贵州钢绳股份有限公司 A kind of manufacture method of high-strength wire rope for traction structure
CN106012623A (en) * 2016-07-29 2016-10-12 贵州钢绳股份有限公司 Multilayer stand steel wire manufacturing method
CN106498787A (en) * 2016-12-08 2017-03-15 贵州钢绳股份有限公司 35W × 7 structure high intensity major diameter producing technique of steel cable

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109930407A (en) * 2019-04-17 2019-06-25 安徽省力通稀土钢缆有限公司 A kind of production technology of corrosion prevention oiling PC steel strand wires

Similar Documents

Publication Publication Date Title
CN103161086B (en) Production method of minuteness steel wire rope
CN108486478B (en) A 1960MPa grade galvanized steel wire rope for marine engineering and its production method
CN106216427A (en) The production method of 1 × 7 21.6mm, 1860MPa high strength steel strand
JPH0199714A (en) Manufacture of steel wire for reinforcing rubber product and steel wire thereof
CN106012623B (en) Multi-strand wire rope manufacturing method
CN108176720A (en) 1 × 7-21.6mm, 1860MPa cable production line techniques
CN102658462A (en) Manufacturing method of aluminum-lithium alloy circular-disc-shaped forging piece
WO2017121312A1 (en) Hot galvanizing profile wire production equipment
CN108817271A (en) A kind of preparation method of the closed cable wire of high intensity
CN103469659A (en) Steel wire rope stranding device
WO2010101154A1 (en) Method of producing steel wire
CN102974654A (en) Vertical pay-off rack damper
CN203695649U (en) Multi-station pay-off rack with brake device
CN103962401B (en) A production method of low-defect high-strength steel wire
JP5551462B2 (en) Method for producing high carbon steel wire and high carbon steel wire obtained thereby
CN108930044A (en) The processing method of steel bead wire
CN206032862U (en) Servo pay -off on diamond electroplating equipment
CN101176966A (en) Indented wire stabilizing treatment technique
CN107956174B (en) Manufacturing method of steel wire rope with diameter phi 264mm for large ocean engineering
CN112853782A (en) High-strength high-elongation prestressed steel strand and manufacturing method thereof
CN103305674A (en) Method for controlling thickness of surface decarburized layer of hot-finished rod for steel cord
CN105239431A (en) Double take-up double twisting machine capable of inwardly-releasing and outwardly taking up
CN103978053A (en) Production process for drawn copper rod wire
CN113680840B (en) Drawing process of high-carbon steel filaments
CN103480677A (en) Straightener bracket device of wire-rewinding machine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181116

RJ01 Rejection of invention patent application after publication