CN105571323A - Mounting technology of furnace top - Google Patents
Mounting technology of furnace top Download PDFInfo
- Publication number
- CN105571323A CN105571323A CN201610054242.8A CN201610054242A CN105571323A CN 105571323 A CN105571323 A CN 105571323A CN 201610054242 A CN201610054242 A CN 201610054242A CN 105571323 A CN105571323 A CN 105571323A
- Authority
- CN
- China
- Prior art keywords
- module
- steel
- furnace roof
- fiber
- furnace
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F27—FURNACES; KILNS; OVENS; RETORTS
- F27D—DETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
- F27D1/00—Casings; Linings; Walls; Roofs
- F27D1/02—Crowns; Roofs
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Furnace Housings, Linings, Walls, And Ceilings (AREA)
Abstract
本发明涉及一种炉顶安装工艺,首先将制作完成的若干长条形的模块吊装并列放置在炉墙上,该模块包括钢结构及纤维模块,所述钢结构沿长轴方向设置一对C型钢,并在C型钢两侧端面设置若干通孔;然后选用长度与纤维模块长度相同的纤维毯,折叠后竖直且对齐固定在相邻纤维模块之间,接着用螺栓穿过将相邻C型钢之间的通孔使其紧固拉紧;最后检查模块缝隙及模块与炉墙之间纤维毯压缩密度,当检查达标后,在炉顶表面进行涂料喷涂。本发明的优点在于:炉顶安装工艺主要将模块依次吊装在炉墙上,然后在相邻模块之间插入纤维毯并通过螺栓进行锁紧,整个炉顶可在炉墙上端安装时进行调整,同时对单个模块进行吊装,吊装方便,安装效率高。
The invention relates to a furnace roof installation process. Firstly, a plurality of manufactured elongated modules are hoisted and placed side by side on the furnace wall. The modules include a steel structure and a fiber module. The steel structure is provided with a pair of C steel, and set a number of through holes on both sides of the C-shaped steel; then choose a fiber blanket with the same length as the fiber module, fold it vertically and fix it between adjacent fiber modules, and then use bolts to pass through the adjacent C The through holes between the section steels make it tight; finally check the module gap and the compression density of the fiber blanket between the module and the furnace wall. After the inspection is up to standard, paint is sprayed on the surface of the furnace roof. The advantage of the present invention is that: the installation process of the furnace roof mainly hoists the modules on the furnace wall in sequence, and then inserts fiber blankets between adjacent modules and locks them with bolts. The entire furnace roof can be adjusted when it is installed on the furnace wall. At the same time, a single module is hoisted, which is convenient for hoisting and high installation efficiency.
Description
技术领域technical field
本发明涉及一种炉顶安装工艺,属于钢铁制造行业用加热炉的炉顶安装技术领域。The invention relates to a furnace top installation process, which belongs to the technical field of furnace top installation of heating furnaces used in the iron and steel manufacturing industry.
背景技术Background technique
在钢坯的生产制造过程中,需将其放置在加热炉中进行加热,以便提高钢的塑性及改变结构内的结晶组织,从而达到使用标准,而在上述过程中加热炉起到了极大的作用,同时为达到指定加热温度及保证工作效率,亟需设计合适的炉顶。传统的炉顶采用若干小型模块,在横向和纵向上拼接而成,拼接工作量大;当通过锚固件固定完成后无法实现紧固拉紧,导致若干小型模块之间形成的无数间隙内密封不完全,且间隙内设置的材料密度不够,当使用一段时间后材料受热收缩,从而发生脱落,严重影响工作效率,因此急需研制一种拼装工作量小且工作效率高的炉顶安装工艺,经检索,未发现与本发明相同或相似的技术方案。In the manufacturing process of steel billets, it needs to be placed in a heating furnace for heating in order to improve the plasticity of the steel and change the crystallization structure in the structure, so as to meet the use standard, and the heating furnace has played a great role in the above process At the same time, in order to achieve the specified heating temperature and ensure work efficiency, it is urgent to design a suitable furnace roof. The traditional furnace roof adopts a number of small modules, which are spliced horizontally and vertically, and the splicing workload is heavy; when the anchors are fixed, it cannot be tightened and tightened, resulting in poor sealing in the countless gaps formed between several small modules. Complete, and the density of the material set in the gap is not enough. After a period of use, the material will shrink due to heat, which will cause it to fall off, which seriously affects the work efficiency. Therefore, it is urgent to develop a furnace roof installation process with a small assembly workload and high work efficiency. After searching , no technical solutions identical or similar to the present invention have been found.
发明内容Contents of the invention
本发明要解决的技术问题是提供一种拼装工作量小且工作效率高的炉顶安装工艺。The technical problem to be solved by the present invention is to provide a furnace roof installation process with a small assembly workload and high work efficiency.
为解决上述技术问题,本发明的技术方案为:一种炉顶安装工艺,其创新点在于:所述安装工艺具体如下:In order to solve the above-mentioned technical problems, the technical solution of the present invention is: a furnace roof installation process, the innovation of which is that the installation process is specifically as follows:
(1)将制作完成的若干长条形的模块吊装并列放置在炉墙上,所述模块包括钢结构及固定在钢结构下端的纤维模块;所述钢结构包括沿长轴方向相对设置的一对C型钢、连接C型钢的钢板及若干方钢;所述C型钢沿长轴方向的两侧端面上均布设置若干通孔;所述纤维模块由若干层沿长轴方向设置的纤维毯压缩而成;(1) Hoist several strip-shaped modules that have been manufactured and place them side by side on the furnace wall. The modules include a steel structure and a fiber module fixed at the lower end of the steel structure; the steel structure includes a For C-shaped steel, steel plates connected to C-shaped steel and several square steels; several through holes are evenly distributed on both end faces of the C-shaped steel along the long axis direction; the fiber module is compressed by several layers of fiber blankets arranged along the long axis direction made;
(2)选用长度与纤维模块长度相同的纤维毯,并折叠使其宽度与纤维模块的高度相同,其中经折叠重合的面上涂抹胶水固定;然后将折叠完成的纤维毯竖直且对齐放置在相邻纤维模块之间,并用不锈钢针将其固定在纤维模块上;(2) Choose a fiber blanket with the same length as the fiber module, and fold it so that its width is the same as the height of the fiber module, and apply glue to the folded overlapping surface; then place the folded fiber blanket vertically and aligned on the between adjacent fiber modules, and fix it on the fiber module with stainless steel pins;
(3)当纤维毯固定完成后各模块沿长轴方向及垂直于长轴方向均对齐设置,此时相邻C型钢端面的通孔也对齐,然后分别使用若干螺栓依次穿过相邻C型钢端面的通孔,并沿模块的拼装方向紧固拉紧,拉紧之后通过螺母锁紧;(3) After the fiber blanket is fixed, each module is aligned along the long axis and perpendicular to the long axis. At this time, the through holes on the end faces of the adjacent C-shaped steel are also aligned, and then several bolts are used to pass through the adjacent C-shaped steel in sequence. The through hole on the end face is tightened along the assembly direction of the module, and then locked by the nut after tension;
(4)检查各模块之间纤维毯的压缩密度,当检查达标后,在炉顶表面进行涂料喷涂,喷涂后12h加热炉即可点火。(4) Check the compression density of the fiber blanket between each module. When the inspection reaches the standard, spray the paint on the surface of the furnace roof, and the heating furnace can be ignited 12 hours after spraying.
进一步的,所述步骤(4)中炉顶表面进行两次涂料喷涂,两次间隔时间为6h。Further, in the step (4), the surface of the furnace roof is sprayed with paint twice, and the interval between the two times is 6 hours.
进一步的,所述步骤(4)中各模块之间纤维毯的压缩密度通过对比法进行检测,纤维模块的密度为128kg/m3,通过观察相邻纤维模块之间的纤维毯密度大于纤维模块自身压缩密度时检测达标。Further, the compression density of the fiber blanket between the modules in the step (4) is detected by a comparison method, the density of the fiber module is 128kg/m 3 , and the density of the fiber blanket between adjacent fiber modules is greater than that of the fiber module When the self-compressed density is detected, it reaches the standard.
本发明的优点在于:The advantages of the present invention are:
(1)炉顶安装工艺主要将模块依次吊装在炉墙上,然后在相邻模块之间插入纤维毯并通过螺栓进行锁紧,整个炉顶可在炉墙上端安装时进行调整,同时对单个模块进行吊装,吊装方便,安装效率高。(1) Furnace roof installation process mainly hoisting the modules on the furnace wall in sequence, and then inserting fiber blankets between adjacent modules and locking them with bolts. The entire furnace roof can be adjusted when installing on the top of the furnace wall. The module is hoisted, which is convenient for hoisting and high installation efficiency.
(2)炉顶表面通过涂料进行两次喷涂,提高炉顶的表面强度,增强热辐射且节能效果好,同时该涂料耐高温、耐腐蚀、抗冲击力强、附着力强不易脱落,能有效保证炉顶的使用寿命,安装工艺合理。(2) The surface of the furnace roof is sprayed twice with paint, which improves the surface strength of the furnace roof, enhances heat radiation and has a good energy-saving effect. To ensure the service life of the furnace top, the installation process is reasonable.
(3)通过对比法检测各模块之间纤维毯的压缩密度,保证炉顶的密封性及工作效率,同时能够有效防止结构发生脱落。(3) The compression density of the fiber blanket between the modules is detected by the comparison method to ensure the sealing and working efficiency of the furnace roof, and at the same time, it can effectively prevent the structure from falling off.
附图说明Description of drawings
图1为本发明一种炉顶安装工艺中钢结构的结构示意图。Fig. 1 is a structural schematic diagram of a steel structure in a furnace roof installation process according to the present invention.
图2为本发明一种炉顶安装工艺中纤维毯连接的结构示意图。Fig. 2 is a structural schematic diagram of fiber blanket connection in a furnace roof installation process of the present invention.
图3为本发明一种炉顶安装工艺中钢结构的连接结构示意图。Fig. 3 is a schematic diagram of the connection structure of the steel structure in a furnace roof installation process according to the present invention.
图4为本发明一种炉顶安装工艺中炉顶的安装结构示意图。Fig. 4 is a schematic diagram of a furnace roof installation structure in a furnace roof installation process according to the present invention.
具体实施方式detailed description
本发明公开了一种炉顶安装工艺,该安装工艺具体如下:The invention discloses a furnace roof installation process, which is specifically as follows:
(1)将制作完成的若干长条形的模块7吊装并列放置在炉墙上,该模块7包括钢结构8及固定在钢结构8下端的纤维模块9;如图1所示,钢结构8包括沿长轴方向相对设置的一对C型钢1、连接C型钢1的钢板3及若干方钢2;其中C型钢1沿长轴方向的两侧端面上均布设置若干通孔4;纤维模块9由若干层沿长轴方向设置的纤维毯压缩而成;(1) Hoist several strip-shaped modules 7 that have been manufactured and place them side by side on the furnace wall. The modules 7 include a steel structure 8 and a fiber module 9 fixed at the lower end of the steel structure 8; as shown in Figure 1, the steel structure 8 It includes a pair of C-shaped steel 1 arranged opposite to each other along the long axis direction, a steel plate 3 connected to the C-shaped steel 1, and several square steels 2; among them, a number of through holes 4 are uniformly arranged on both sides of the C-shaped steel 1 along the long-axis direction; the fiber module 9 is formed by compressing several layers of fiber blankets arranged along the long axis direction;
(2)如图2所示,选用长度与纤维模块9长度相同的纤维毯10,并折叠使其宽度与纤维模块9的高度相同,其中经折叠重合的面上涂抹胶水固定;然后将折叠完成的纤维毯10竖直且对齐放置在相邻纤维模块9之间,并用不锈钢针11将其固定在纤维模块9上;(2) As shown in Figure 2, choose a fiber blanket 10 with the same length as the fiber module 9, and fold it so that its width is the same as the height of the fiber module 9, and apply glue on the folded overlapping surface; then complete the folding The fiber blanket 10 is placed vertically and aligned between adjacent fiber modules 9, and is fixed on the fiber module 9 with stainless steel pins 11;
(3)如图3和图4所示,当纤维毯10固定完成后各模块7沿长轴方向及垂直于长轴方向均对齐设置,此时相邻C型钢1端面的通孔4也对齐,然后分别使用若干螺栓5依次穿过相邻C型钢1端面的通孔4,并沿模块7的拼装方向紧固拉紧,拉紧之后通过螺母6锁紧;(3) As shown in Figures 3 and 4, after the fiber blanket 10 is fixed, the modules 7 are aligned along the long axis and perpendicular to the long axis, and the through holes 4 on the end faces of the adjacent C-shaped steel 1 are also aligned. , and then use several bolts 5 to pass through the through holes 4 of the end faces of the adjacent C-shaped steel 1 in turn, and tighten and tighten along the assembly direction of the module 7, and then lock them with nuts 6 after tension;
(4)通过对比法检查各模块7之间纤维毯10的压缩密度,纤维模块9的密度为128kg/m3,通过观察相邻纤维模块9之间的纤维毯10密度大于纤维模块9自身压缩密度时检测达标;当检查达标后,在炉顶表面进行两次涂料喷涂,中间的间隔时间为6h,当喷涂后12h加热炉即可点火。(4) Check the compression density of the fiber blanket 10 between the modules 7 by comparison method. The density of the fiber module 9 is 128kg/m 3 . By observing that the density of the fiber blanket 10 between adjacent fiber modules 9 is greater than that of the fiber module 9 itself When the density is up to the standard; when the inspection is up to the standard, the paint is sprayed twice on the furnace top surface, with an interval of 6 hours, and the heating furnace can be ignited 12 hours after spraying.
以上显示和描述了本发明的基本原理和主要特征。本行业的技术人员应该了解,本发明不受上述实施例的限制,上述实施例和说明书中描述的只是说明本发明的原理,在不脱离本发明精神和范围的前提下,本发明还会有各种变化和改进,这些变化和改进都落入要求保护的本发明范围内。本发明要求保护范围由所附的权利要求书及其等效物界定。The basic principles and main features of the present invention have been shown and described above. Those skilled in the industry should understand that the present invention is not limited by the above-mentioned embodiments. What are described in the above-mentioned embodiments and the description only illustrate the principle of the present invention. Without departing from the spirit and scope of the present invention, the present invention will also have Variations and improvements all fall within the scope of the claimed invention. The protection scope of the present invention is defined by the appended claims and their equivalents.
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610054242.8A CN105571323B (en) | 2016-01-27 | 2016-01-27 | A kind of furnace roof mounting process |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610054242.8A CN105571323B (en) | 2016-01-27 | 2016-01-27 | A kind of furnace roof mounting process |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN105571323A true CN105571323A (en) | 2016-05-11 |
| CN105571323B CN105571323B (en) | 2018-06-29 |
Family
ID=55881734
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201610054242.8A Active CN105571323B (en) | 2016-01-27 | 2016-01-27 | A kind of furnace roof mounting process |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN105571323B (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108728130A (en) * | 2017-04-20 | 2018-11-02 | 五冶集团上海有限公司 | A kind of hole protective cover of coalingging for the online furnace roof maintenance of coke oven |
| CN116222222A (en) * | 2023-02-22 | 2023-06-06 | 中冶南方(武汉)热工有限公司 | A full-fiber roof structure for steel rolling heating furnace |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4791769A (en) * | 1984-04-19 | 1988-12-20 | Eltech Systems Corporation | Movable heat chamber insulating structure |
| CN201443971U (en) * | 2009-05-15 | 2010-04-28 | 山东鲁阳股份有限公司 | Air ventilation oxidizing furnace lining composite structure |
| CN201852454U (en) * | 2010-08-17 | 2011-06-01 | 中冶东方工程技术有限公司 | Coiler furnace |
| CN102121795A (en) * | 2011-03-03 | 2011-07-13 | 顾向涛 | Furnace top structure of heating furnace |
| CN102305542A (en) * | 2011-09-15 | 2012-01-04 | 顾向涛 | Fiber module for heating furnace and manufacturing method for fiber module |
| CN102312077A (en) * | 2011-09-06 | 2012-01-11 | 中冶南方(武汉)威仕工业炉有限公司 | Fixing device and method for refractory material in strip steel heat treatment furnace |
| CN203177655U (en) * | 2013-03-06 | 2013-09-04 | 河北钢铁股份有限公司邯郸分公司 | Furnace roof structure of roller hearth heating furnace |
-
2016
- 2016-01-27 CN CN201610054242.8A patent/CN105571323B/en active Active
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4791769A (en) * | 1984-04-19 | 1988-12-20 | Eltech Systems Corporation | Movable heat chamber insulating structure |
| CN201443971U (en) * | 2009-05-15 | 2010-04-28 | 山东鲁阳股份有限公司 | Air ventilation oxidizing furnace lining composite structure |
| CN201852454U (en) * | 2010-08-17 | 2011-06-01 | 中冶东方工程技术有限公司 | Coiler furnace |
| CN102121795A (en) * | 2011-03-03 | 2011-07-13 | 顾向涛 | Furnace top structure of heating furnace |
| CN102312077A (en) * | 2011-09-06 | 2012-01-11 | 中冶南方(武汉)威仕工业炉有限公司 | Fixing device and method for refractory material in strip steel heat treatment furnace |
| CN102305542A (en) * | 2011-09-15 | 2012-01-04 | 顾向涛 | Fiber module for heating furnace and manufacturing method for fiber module |
| CN203177655U (en) * | 2013-03-06 | 2013-09-04 | 河北钢铁股份有限公司邯郸分公司 | Furnace roof structure of roller hearth heating furnace |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108728130A (en) * | 2017-04-20 | 2018-11-02 | 五冶集团上海有限公司 | A kind of hole protective cover of coalingging for the online furnace roof maintenance of coke oven |
| CN116222222A (en) * | 2023-02-22 | 2023-06-06 | 中冶南方(武汉)热工有限公司 | A full-fiber roof structure for steel rolling heating furnace |
Also Published As
| Publication number | Publication date |
|---|---|
| CN105571323B (en) | 2018-06-29 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN203701350U (en) | Self-reset energy consumption node for aerated concrete externally hanging wallboard | |
| CN103821265B (en) | The Self-resetting energy dissipation node of gas concrete out-hung panel and construction method thereof | |
| CN108060782B (en) | The installation method and auxiliary mounting tool of girder steel element | |
| CN105571323B (en) | A kind of furnace roof mounting process | |
| CN206873716U (en) | A kind of antidetonation type unitized curtain wall | |
| CN108222338A (en) | A kind of curtain wall-connecting structure | |
| CN102733617A (en) | Safety net hanger | |
| CN114687511A (en) | Novel assembled internal heat-insulation light wallboard adopting layered alternate lap joint | |
| CN206172803U (en) | Clamp type ear plate | |
| CN209277551U (en) | The fastener being connected in parallel for steel I-beam | |
| CN103821336B (en) | A kind of fixed high-altitude long-span construction operation platform of rope and construction method thereof | |
| CN217232853U (en) | Fixture type limb protection auxiliary device | |
| CN105863132B (en) | A kind of dry hanging plate material system and its construction method | |
| CN215048056U (en) | Detachable and reusable steel beam hoisting fastener | |
| CN214575601U (en) | Outer scaffold is wall spare even | |
| CN202946322U (en) | Wind driven generator tower drum and wind driven generator thereof | |
| CN210898372U (en) | Novel bracket for cable bridge or medium pipeline | |
| CN209670064U (en) | A kind of Steel Structure Installation limiting and fixing device | |
| CN213296657U (en) | Energy-conserving fire prevention steel construction of green building | |
| CN105332451B (en) | A kind of external wall disassembly-free thermal-insulation form board | |
| CN217838037U (en) | Combined tool for auxiliary hoisting of rock wool sandwich board roof panel | |
| CN211396693U (en) | Safety rope fixing device capable of being fixed on H-shaped steel beams of various specifications | |
| CN212714379U (en) | Green protector of planting of hot in-Place recycling unit | |
| CN205153223U (en) | Heat preservation template is exempted from to tear open by fast assembly's outer wall | |
| CN103866980B (en) | The wooden bulkhead construction method of body of wall steel form |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| TR01 | Transfer of patent right | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20190103 Address after: 558200 East Side of Century Avenue of Dushan Economic Development Zone, Dushan County, Guizhou Province, Buyi and Miao Autonomous Prefecture, Southern Guizhou Province Patentee after: GUIZHOU NANFANG TECHNOLOGY CO.,LTD. Address before: 226000 Huiping Town Industrial Park, Qidong, Nantong City, Jiangsu Province Patentee before: JIANGSU SOUTH ENERGY SAVING TECHNOLOGY Co.,Ltd. |
|
| TR01 | Transfer of patent right | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20210831 Address after: 226265 Huiping Town Industrial Park, Qidong City, Nantong City, Jiangsu Province Patentee after: Jiangsu Nanfang Technology Co.,Ltd. Address before: 558200 East Side of Century Avenue of Dushan Economic Development Zone, Dushan County, Guizhou Province, Buyi and Miao Autonomous Prefecture, Southern Guizhou Province Patentee before: GUIZHOU NANFANG TECHNOLOGY Co.,Ltd. |
|
| PE01 | Entry into force of the registration of the contract for pledge of patent right | ||
| PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of invention: A furnace top installation process Granted publication date: 20180629 Pledgee: Bank of China Limited by Share Ltd. Qidong branch Pledgor: Jiangsu Nanfang Technology Co.,Ltd. Registration number: Y2024980018688 |
|
| PC01 | Cancellation of the registration of the contract for pledge of patent right | ||
| PC01 | Cancellation of the registration of the contract for pledge of patent right |
Granted publication date: 20180629 Pledgee: Bank of China Limited by Share Ltd. Qidong branch Pledgor: Jiangsu Nanfang Technology Co.,Ltd. Registration number: Y2024980018688 |
|
| PE01 | Entry into force of the registration of the contract for pledge of patent right | ||
| PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of invention: A furnace top installation process Granted publication date: 20180629 Pledgee: Bank of China Limited by Share Ltd. Qidong branch Pledgor: Jiangsu Nanfang Technology Co.,Ltd. Registration number: Y2025980019587 |